# Gyanendra Kumar v. U.O.I. & Ors

- **Citation:** (2025) 2 ILRA 627
- **Court:** High Court of Judicature at Allahabad
- **Decided:** 2025-02-10
- **Case number:** Writ C No. 28993 of 2024
- **Bench:** Shekhar B. Saraf, Vipin Chandra Dixit
- **Source:** https://unisonlegal.in/judgment/allahabad-high-court/gyanendra-kumar-v-u-o-i-ors-53014
- **Pages:** 2

## Text

2 All. Gyanendra Kumar Vs. U.O.I. & Ors.
627
been sent to the allottees as a formality, no
genuine efforts have been made to recover
the dues.

62. The consortium members are
bound by the terms of the lease, which
requires them to pay interest and penal
interest on the outstanding dues as per the
lease agreement.

63. Considering the entire facts and
circumstances of the case, we are of the
firm opinion that since the entire delay is
on the part of the sub-allottees, there is no
question of restructuring or rescheduling
the payment schedule.

64. In this petition, the petitioner has
although claimed damages of Rs.200
crores. However, this prayer is thoroughly
misconceived, as damages cannot be
awarded in the present proceedings.

65.
In
the
given
facts
and
circumstances of the case, this Court finds
that the petitioner company itself opted out
of the Sports City project. The petitioner
company could not demonstrate as to how
and in what manner its rights are affected
and therefore, no relief can be granted to
the petitioner in the instant writ petition.

66. The writ petition sans merit and is,
accordingly, dismissed.

67. Parties to bear their own cost.
----------
(2025) 2 ILRA 627
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 10.02.2025

BEFORE

THE HON'BLE SHEKHAR B. SARAF, J.
THE HON'BLE VIPIN CHANDRA DIXIT, J.

Writ C No. 28993 of 2024

Gyanendra Kumar ...Petitioner
Versus
U.O.I. & Ors. ...Respondents

Counsel for the Petitioner:
Saurabh Srivastava

Counsel for the Respondents:
A.S.G.I., C.S.C., Komal Mehrotra

A. Civil Law - Constitution of India,1950Article 226- Clause 8.5.6 of Marketing
Discipline
Guidelines,2012-delay
in
issuance of show cause notice-mandatory
nature
of
time
limit-the
petitioner
challenged a show cause notice issued
beyond permissible period of 30 days from
the
date of
sample test results, as
prescribed in Guidelines 2012-The court
observed that the said clause mandates
issuance of notice within 30 days-in the
present case, no valid explanation was
provided for the delay of over two monthsthe impugned show cause notice was
quashed and liberty was granted to the
respondents to conduct a fresh inspection
in accordance with law.(Para 1 to 7)

The writ petition is disposed of. (E-6)

List of Cases cited:
Indian Oil Corp. Ltd & ors.Vs R.M. Service
Centre & ors. (2019) 19 SCC 662
(Delivered by Hon'ble Shekhar B. Saraf, J.
&
Hon'ble Vipin Chandra Dixit, J.)

1. Heard learned counsel for the
parties and perused the record.

2. This writ petition under Article
226 of the Constitution of India has been
filed whereby the petitioner is aggrieved by
the order of show cause notice dated
08.09.2023, wherein the petitioner has been
show caused with regard to alleged
discrepancy found in the joint inspection.
628 INDIAN LAW REPORTS ALLAHABAD SERIES
3. In the present case, the factual
matrix is that the inspection by the
respondent authorities was carried out on
04.03.2023 and the samples' test came out
on 23.06.2023. The respondent authorities
sat over the sample tests for the period of
two and half month and then issued a show
cause notice on 08.09.2023. The relevant
Clause 8.5.6 of Marketing Discipline
Guidelines, 2012 reads as follows :-

 "8.5.6 in respect of all cases of
irregularities, a show cause notice, within
30 days from the date of inspection will be
issued to the dealer indicating all the
irregularities. However, in case samples of
MS/HSD were drawn during inspection
then the show cause notice will be issued
within 30 days of test results. The show
cause notice should be issued along with
all reports and other documents, etc. which
forms the basis of the notice."

4. From the perusal of the said
clause, it is patently clear that show cause
notice is required to be issued within 30
days from the date of inspection and if the
samples are taken during the inspection,
this show cause notice is required to be
issued 30 days from the date of test results
but in the present case, show cause notice
has been issued after more than 2 months
from the date of receipt of test results. No
proper explanation has been provided by
the respondent authorities to indicate the
reasons of such delay.

5.
Upon
further
reading
of
aforesaid clause, we are of the view that
this clause is mandatory in nature. Even if
some flexibility is provided for the two
months delay cannot be accepted. The
judgment relied upon by the respondents
being Indian Oil Corporation Ltd. and
Ors. vs. R.M. Service Centre and Ors.
reported in (2019) 19 SCC 662 is factually
different and would not apply in the present
case as in the Hon'ble Supreme Court
judgment, the clause referred used the word
"preferably", but in the present case, the
words are different and there does not
appear to be any ambiguity with regard to
the time provided for issue of show cause
notice in the said clause.

6. In light of the same, the present
show cause notice cannot be sustained on
the ground that the same has been issued
with an inordinate delay. Accordingly, the
show cause notice is quashed and set aside
and the respondent authorities are granted
liberty to carry out fresh inspection and
draw samples and act in accordance with
law.

7. With the above direction, the
writ petition is disposed of.
----------
(2025) 2 ILRA 628
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 07.02.2025

BEFORE

THE HON'BLE SHEKHAR B. SARAF, J.
THE HON'BLE VIPIN CHANDRA DIXIT, J.

Writ C No. 33222 of 2023

Span Infra Developers Pvt. Ltd
 ....Petitioner
Versus
State of U.P. & Ors. ...Respondents

Counsel for the Petitioner:
Ravi Anand Agarwal, Shreya Gupta

Counsel for the Respondents:
Abhimanyu Singh, C.S.C.

A. Civil Law -Constitution of India,1950Article
226-Urban
Land(Ceiling
and