# M/S Jai Goswami Electric Works Alld v. Union Of India & Ors

- **Citation:** (2016) 5 ILRA 788
- **Court:** High Court of Judicature at Allahabad
- **Decided:** 2016-05-19
- **Bench:** Sudhir Agarwal, Shamsher Bahadur Singh
- **Source:** https://unisonlegal.in/judgment/allahabad-high-court/m-s-jai-goswami-electric-works-alld-v-union-of-india-ors-43939
- **Pages:** 5

## Headnote

This writ petition filed under Article 226 of Constitution, petitioner has sought following relief:
5 All. M/S Jai Goswami Electric Works Alld. Vs Union Of India & Ors.

789
Issue a writ, order or direction in the nature of appropriate nature commanding the respondents to
make payment of balance amount against actual work done in respect of contracts Nos. 230-Elect
/TRD/ALD/WC/97/61 dated 19.11.97 and Contract No. 230/Elect/TRD/ALD/113 dated 19.3.98 within one
month from the date of passing order by this Hon'ble Court together with interest @ 2% per month."

We are clearly of the view that mandamus sought by petitioner is nothing but grant of a money decree
in extraordinary equitable jurisdiction under Article 226 which ought not to have been granted.

Held: Para-

Case Law discussed:
Hindustan Sugar Mills, M/s. Vs. State of Rajasthan AIR 1981 SC 1681,
Hindustan Petroleum Corporation Limited and another Vs. Dolly Das 1999 (4) SCC 450,
Kerala State Electricity Board and another Vs. Kurien E. Kalathil and others 2000 (6) SCC 293,
M/S Prabhu Construction Company through its Proprietor Vs. State of U.P. and another,
M/s R.S. Associate Vs. State of U.P. and others,
Alaska Tech Vs. State of U.P. 2014 (6) ADJ 591,

## Text

788 INDIAN LAW REPORTS ALLAHABAD SERIES
24. In the present case, documentary evidence is available on record to show that on
07.12.1987 Sri Om Pal Singh, Land Inspector, as representative of Collector, actually visited the
site along with Lekhpal, and in presence of witnesses, took possession of surplus land of petitioner
measuring 35980.53 sq. metre comprising four khasra numbers detailed therein. Thereafter
possession of said land was transferred to MDA on 27.06.1989.

25. Sri Sahai submitted that possession was not taken in presence of petitioner but as noted
above, presence of owner of land is not necessary. Therefore, for that reason alone, the documents
showing possession taken by respondents cannot be held to be invalid, particularly when document
clearly shows, when possession was taken, petitioner was not present but was out of station. This
fact has not been disputed at all. This fact mentioned in the possession memo shows that officials
actually visited the site and took possession of land in question.

26. In view of above discussion, we are of the view that possession of surplus land,
measuring 34980.03 sq. maters, which was so declared vide order dated 16.05.1979, has been taken
on 07.12.1987 by respondents, hence contention of petitioner that land is in her possession and
after promulgation of Act, 1999, now land is not vacant and cannot be taken by State is thoroughly
misconceived and rejected.

27. No other argument has been advanced. In view of above discussion, the writ petition
lacks merit. Dismissed.

28. Interim order, if any, stands vacated.
----------
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 19.05.2016

BEFORE

THE HON'BLE SUDHIR AGARWAL, J.
THE HON'BLE SHAMSHER BAHADUR SINGH, J.

Writ C No.- 42697 Of 2002

M/S Jai Goswami Electric Works Alld. ...Petitioner
Versus
Union Of India & Ors. ...Respondents

Counsel for the Petitioner:
Vishnu Gupta, B.C. Naik, Shashi Nandan

Counsel for the Respondents:
S.C.

This writ petition filed under Article 226 of Constitution, petitioner has sought following relief:
5 All. M/S Jai Goswami Electric Works Alld. Vs Union Of India & Ors.

789
Issue a writ, order or direction in the nature of appropriate nature commanding the respondents to
make payment of balance amount against actual work done in respect of contracts Nos. 230-Elect
/TRD/ALD/WC/97/61 dated 19.11.97 and Contract No. 230/Elect/TRD/ALD/113 dated 19.3.98 within one
month from the date of passing order by this Hon'ble Court together with interest @ 2% per month."

We are clearly of the view that mandamus sought by petitioner is nothing but grant of a money decree
in extraordinary equitable jurisdiction under Article 226 which ought not to have been granted.

Held: Para-

Case Law discussed:
Hindustan Sugar Mills, M/s. Vs. State of Rajasthan AIR 1981 SC 1681,
Hindustan Petroleum Corporation Limited and another Vs. Dolly Das 1999 (4) SCC 450,
Kerala State Electricity Board and another Vs. Kurien E. Kalathil and others 2000 (6) SCC 293,
M/S Prabhu Construction Company through its Proprietor Vs. State of U.P. and another,
M/s R.S. Associate Vs. State of U.P. and others,
Alaska Tech Vs. State of U.P. 2014 (6) ADJ 591,

(Delivered by Hon'ble Sudhir Agarwal, J.
&
Hon'ble Shamsher Bahadur Singh, J.)

1. Heard learned counsel for petitioner and perused the record.

2. By means of this writ petition filed under Article 226 of Constitution, petitioner has
sought following relief:

(a) issue a writ, order or direction in the nature of appropriate nature commanding
the respondents to make payment of balance amount against actual work done in respect of
contracts
Nos.
230-Elect
/TRD/ALD/WC/97/61
dated
19.11.97
and
Contract
No.
230/Elect/TRD/ALD/113 dated 19.3.98 within one month from the date of passing order by this
Hon'ble Court together with interest @ 2% per month."

3. Petitioner is Railway Contractor and pursuant to an agreement for work, he has
performed some work but his payment has not been made. Since payment has been approved by
competent authority, therefore, prayer has been made that respondents be directed to make
payment.

4. When questioned as to how for realization of money pursuant to a contractual work writ
petition under Article 226 is maintainable, learned counsel for petitioner placed reliance on Apex
Court's decision in Hindustan Sugar Mills, M/s. Vs. State of Rajasthan AIR 1981 SC 1681.

5. We have considered the above decision in Hindustan Sugar Mills, M/s. Vs. State of
Rajasthan (supra) and find that sale of cement and price was controlled by Cement Control Order,
1967 issued under the provisions of Essential Commodities Act, 1955 (hereinafter referred to as
790 INDIAN LAW REPORTS ALLAHABAD SERIES
"Act, 1955"). The Company supplied cement to the Central Government through Director General
of Supplies and Disposals. The amount of sales tax payable by Company on the aforesaid cement
was to be paid by Government which was disputed on the ground that there was contract for such
payment and matter was decided by Court holding that there is no legal liability on the Central
Government to pay amount of sales-tax. However, having said so, Court also observed that in a
democratic society governed by rule of law, a Government is expected to be inspired by ethical and
moral values and should do what is fair and just to the citizen, regardless of legal technicalities.
Court expected that Central Government will not seek to defeat legitimate claim of assessee for
reimbursement of sales tax on the amount of the freight by adopting a legalistic attitude. Thereafter
a Review Application was filed by Company showing that there was a Clause in Rate Contract of
Director General of Supplies and Disposals providing that sales tax, if legally leviable, will be paid
in addition to the price given in clause of the Rate Contract. In that view of the matter, Review
Application was allowed and observation that Central Government was not bound to pay amount of
sales tax legally was deleted and Court said as under:

"Where there is such a clause the Central Government is bound to pay the amount
of sales tax on the freight component of the price and we hope and trust that the Central
Government will honour its legal obligation and not drive the appellant to file a suit for recovery of
the amount of such sales tax. We hopefully expect that the Central Government will not try to shirk
its legal obligation by resorting to any legal technicalities for we maintain that in a democratic
society governed by the rule of law, it is the duty of the State to do what is fair and just to the
citizen and the state should not seek to defeat the legitimate claim of the citizen by adopting a
legalistic attitude but should do what fairness and justice demand."

6. There was no issue raised, argued and decided by Court that for the purpose of recovery
of money pursuant to contract, writ petition under Article 226 would be maintainable. This
question has been considered specifically in Hindustan Petroleum Corporation Limited and
another Vs. Dolly Das 1999 (4) SCC 450 wherein Court said that in absence of any constitutional
or statutory rights being involved, a writ proceeding would not lie to enforce contractual
obligations even if it is sought to be enforced against State or to avoid contractual liability arising
thereto. In the absence of any statutory right, Article 226 cannot be availed to claim any money in
respect of breach of contract or tort or otherwise.

7. In Kerala State Electricity Board and another Vs. Kurien E. Kalathil and others
2000 (6) SCC 293, Court said that interpretation and implementation of a clause in a contract
cannot be subject-matter of a writ petition. Whether a contract envisages actual payment or not is a
question of construction of contract. If a term of contract is violated, ordinarily remedy is not the
writ petition under Article 226. A contract would not become statutory simply because it is for
construction of a public utility and it has been awarded by a statutory body. A statute may
expressly or impliedly confer power on a statutory body to enter into contracts in order to enable it
to discharge its functions. Disputes arising out of the terms of such contracts or alleged breaches
have to be settled by the ordinary principles of law of contract. The fact that one of the parties to
the agreement is a statutory or public body will not by itself affect the principles to be applied. The
5 All. M/S Jai Goswami Electric Works Alld. Vs Union Of India & Ors.

791
disputes about the meaning of a covenant in a contract or its enforceability have to be determined
according to the usual principles of the Contract Act. Every act of a statutory body need not
necessarily involve an exercise of statutory power. Statutory bodies have power to contract or deal
with property like private parties. Such activities may not raise any issue of public law. When it is
not shown that contract is statutory and parties are within the realm of their authority, contract
between the parties is in the realm of private law. The disputes relating to interpretation of terms
and conditions of such contract cannot be agitated in a petition under Article 226 of the
Constitution. The Court further said:

"That is a matter for adjudication by a civil court or in arbitration if provided for in
the contract. Whether any amount is due and if so, how much and refusal of the appellant to pay it
is justified or not, are not the matters which could have been agitated and decided in a writ
petition."

8. Following the above authorities, a Division Bench of this Court in M/S Prabhu
Construction Company through its Proprietor Vs. State of U.P. and another (Writ C No.
25075 of 2014) decided on 05.05.2014 said as under:

"In the present case, there is nothing on the record which may persuade us to hold
that the contract is a statutory contract. The remedy of the contractor, if he is aggrieved by nonpayment, would be to either file an ordinary civil suit or if there is an arbitration agreement
between the parties, to invoke the terms of the agreement."

9. The Court also relied on its earlier decision in M/s R.S. Associate Vs. State of U.P. and
others (Writ-C No. 11544 of 2014) decided on 24.02.2014.

10. Again in Alaska Tech Vs. State of U.P. 2014 (6) ADJ 591, a Division Bench of this
Court observed as under:

"2. We are of the view that, in a matter of this nature which pertains to alleged nonpayment of dues under a contract for supply of goods, it would neither be prudent nor judicious for
this Court, in exercise of its jurisdiction under Article 226 of the Constitution, to grant relief, which
is in substance, is a prayer for a money decree. These matters, it must be emphasized, are not those
relating to statutory contracts but are purely non-statutory contracts. Whether work has been
satisfactorily performed, whether the rates which had been quoted are in accordance with the
terms of the contract, whether the goods were of a quality as mandated, and above all, whether the
claim is within limitation or otherwise, are issues which cannot appropriately be adjudicated upon
under Article 226 of the Constitution."

11. The same view has been reiterated in M/S Goyal Stationary Mart through its
Proprietor State of U.P. (Misc. Bench No. 10971 of 2015) decided on 27.11.2015, Budh Gramin
Sansthan Vs. State of U.P. 2014 (7) ADJ 29, Kaka Advertising Agency Vs. U.P. Technical
University and others 2014 (11) ADJ 227, M/s A.K. Constructions Vs. State of U.P. and others
792 INDIAN LAW REPORTS ALLAHABAD SERIES
(Misc. Bench No. 1909 of 2014) decided on 07.03.2014, Major Travels through Proprietor Vs.
State of U.P. and others (Misc. Bench No. 3472 of 2014) decided on 25.04.2014 and
Uttaranchal Paper Converters and Publishers through Proprietor Vs. State of U.P. and
others (Misc. Bench No. 3898 of 2015) decided on 13.05.2014.

12. In view thereof, we are clearly of the view that mandamus sought by petitioner is
nothing but grant of a money decree in extraordinary equitable jurisdiction under Article 226 which
ought not to have been granted.

13. It may also be noted at this stage that on behalf of respondents 1, 2 and 3 a counter
affidavit has been filed wherein claim of petitioner has been seriously disputed and it has been
pleaded that petitioner violated agreement conditions and enhanced rate was not approved by
competent authority. The alleged work performed by petitioner has also not been approved by
competent authority and, therefore, payment has been held up. Thus it is a clear case where even
the right of petitioner for payment has been seriously disputed disputing seriously various
assertions made by petitioner and the same need not be examined in writ jurisdiction under Article
226 even otherwise.

14. The writ petition is wholly devoid of merits. Dismissed with cost of Rs. 25,000/-.

15. Interim order, if any, stands vacated.
----------
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 12.05.2016

BEFORE

THE HON'BLE ASHWANI KUMAR MISHRA, J.

Writ A No.- 60557 Of 2015

Anil Kumar Pandey & Ors. ...Petitioners
Versus
State Of U.P. & Ors. ...Respondents

Counsel for the Petitioners:
Sanjai Kumar Pandey, Shrawan Kumar Tripathi

Counsel for the Respondents:
C.S.C., Ravindra Singh
.................................
Writ Petition Against Cane-growers' Co-operative Society Maintainable - U.P. Cane Co-operative
Service Regulations 1975 are Statutory in Nature - Reference made by Single Judge on the question
whether a writ petition under Article 226 of the Constitution of India would be maintainable against a Cooperative Cane Development Society at the instance of its employee for alleged breach of U.P. Cane Co-