# M/S Progressive Construction Company v. Engineer-In-Chief & H.O.D., Pwd & Ors

- **Citation:** (2026) 2 ILRA 203
- **Court:** High Court of Judicature at Allahabad
- **Decided:** 2026-02-11
- **Case number:** Civil Misc. Arbitration Application No. 19 of 2025
- **Bench:** Subhash Vidyarthi
- **Source:** https://unisonlegal.in/judgment/allahabad-high-court/m-s-progressive-construction-company-v-engineer-in-chief-h-o-d-pwd-ors-54235
- **Pages:** 5

## Text

2 All. M/S Progressive Construction Company Vs. Engineer-In-Chief & H.O.D., Pwd & Ors.
203
delays also run counter to the essence of the right to speedy trial under Article 21 of the
Constitution of India, 1950.

21. In view of the above discussion, this Court finds no illegality or irregularity in the
impugned order as more than sufficient opportunities of defence were provided by the trial court.
Therefore, the prayer for quashing the impugned judgment and order dated 16.10.2025, as well as
to quash the entire proceeding is refused. This Court is of the considered view that such matters
which are affected by unnecessary delay at the ends of the parties should be expedited, and an
endeavour should be made to dispose of them within the statutory period unless there are orders of
the higher courts staying the proceeding. This judgment be placed before the learned District and
Sessions Judge concerned. The office to do needful.

22. With the above observation and directions, the application is finally disposed of.
---------
(2026) 2 ILRA 203
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: LUCKNOW 11.02.2026

BEFORE

THE HON'BLE SUBHASH VIDYARTHI, J.

Civil Misc. Arbitration Application No. 19 of 2025

M/S Progressive Construction Company ...Appellant
Versus
Engineer-In-Chief & H.O.D., Pwd & Ors. ...Respondents

Issue for Consideration
Issue pertains to whether, in exercise of jurisdiction u/s 11(6) of Arbitration and Conciliation Act, 1996, the
High Court can appoint a sole arbitrator for adjudication of disputes between the parties, notwithstanding the
arbitration agreement providing for a panel of three arbitrators, in a situation where the parties have failed to
constitute the arbitral tribunal in terms of the agreed procedure and the applicant seeks such modification to
reduce costs.

Headnotes
Arbitration and Conciliation Act, 1996 - s. 11(6) - Appointment of Arbitrator - Arbitration Clause -
Deviation from agreed procedure - Failure of parties to appoint arbitrators - Power of Court - The
applicant, entered into a contract dated 06.11.2015 with the opposite parties, namely the
Engineer-in-Chief and others of the Public Works Department, which contained an arbitration
clause (Clause 25.1.3) providing for resolution of disputes through arbitration - Upon arising of
disputes, the applicant invoked the arbitration clause and requested the appointment of an
arbitrator in terms of agreement - The Executive Engineer, Construction Division-II, PWD, by
letter dated 06.12.2024, recommended the appointment of an arbitrator to the competent
authority, however, no arbitrator was appointed by respondents in accordance with the agreed
procedure - Consequently, the applicant filed the instant application u/s 11(6) of Arbitration and
Conciliation Act, 1996 before the High Court seeking appointment of an arbitrator, while the
respondents did not dispute the existence of arbitration agreement, nor that the Executive
204 INDIAN LAW REPORTS ALLAHABAD SERIES
Engineer, by letter dated 06.12.2024, had requested the Superintending Engineer to appoint an
arbitrator.

Held: Although the arbitration agreement contained provision for constituting a panel of three arbitrators -
one arbitrator to be appointed by each of the parties and the third arbitrator or the umpire being appointed by
the two arbitrators, the parties fail to appoint their arbitrators, an application u/s 11(6) of the Arbitration and
Conciliation Act, 1996 is filed and a party requests that it is not willing to bear the high cost of arbitration to
be conducted by a panel of three arbitrators and in order to reduce the costs, it requests appointment of a
sole arbitrator, the Court can accede to the request - Accordingly, arbitrator appointed for adjudication
of the disputes between the parties, thus, application allowed. [Para 12, 13] (E-13)

Case Law Cited
Union of India v. Singh Builders Syndicate: (2009) 4 SCC 523; 24 Secure Services Pvt. Ltd. v. Competent
Automobile Ltd. 2024 SCC OnLine Delhi 4358; referred to

Jhajharia Nirman Ltd. v. South Western Railways through Dy. Chief Engineer/IV Construction reported in
2024 SCC OnLine Del 7133 - followed

List of Acts
Arbitration and Conciliation Act, 1996

List of Keywords
Arbitration application; s. 11(6) of Arbitration and Conciliation Act, 1996; Appointment of arbitrator;
Adjudication of disputes; Contract dated 06.11.2015; Arbitration clause (Clause 25.1.3); Request for
appointment; Recommendation by Executive Engineer; Failure to appoint arbitrator; Existence of arbitration
agreement; Panel of three arbitrators; Agreed procedure; Failure of parties to constitute tribunal; Request for
appointment of sole arbitrator; Reduction of cost of arbitration; Proposed name of arbitrator; Application
allowed

Case Arising From
ORIGINAL JURISDICTION: (Civil Misc. Arbitration Application No. - 19 of 2025)

From the Judgment and Order passed by the Superintending Engineer, Hamirpur Circle, Public Works
Department, Hamirpur

Appearances for Parties
Adv. for the Applicant:
Vipul Rai

Adv. for the Opposite Party:
C.S.C

(Delivered by Hon'ble Subhash Vidyarthi, J.)

1. Heard Shri Abhishek Dwivedi, Advocate holding brief of Shri Vipul Rai, the learned
counsel for the applicant and Shri S.K. Khare, the learned Standing Counsel for the State.

2. By means of the instant application filed under Section 11(6) of the Arbitration and
Conciliation Act, the applicant is seeking appointment of an arbitrator for adjudication of the
disputes between the parties arising out of a contract dated 06.11.2015.
2 All. M/S Progressive Construction Company Vs. Engineer-In-Chief & H.O.D., Pwd & Ors.
205

3. Clause 25.1.3 of the agreement contains an arbitration clause. The applicant had requested
the opposite parties for appointment of arbitrator as per the aforesaid arbitration clause.

4. On 06.12.2024, the Executive Engineer, Construction Division-II, Public Works
Department wrote a letter to the Superintending Engineer, Hamirpur Circle, Public Works
Department, Hamirpur recommended appointment of an arbitrator as per the Clause 25.1.3 but
when arbitrator was not appointed in spite of this recommendation, the applicant has filed this
application.

5. The opposite parties have filed objections against the application which principally contains
pleas of the opposite parties disputing the correctness of the claims of the applicant. However,
while deciding an application under Section 11(6) of the Arbitration and Conciliation Act, this
Court is not required to examine correctness of the claims of the applicant and that has to be done
by the arbitrator.

6. The State has not disputed the existence of arbitration agreement and it has not disputed that
through the aforesaid letter dated 06.12.2024, the Executive Engineer had himself requested the
Superintending Engineer to appoint an arbitrator.

7. As arbitrator has not been appointed by the opposite parties, occasion has arose for this
Court to appoint an arbitrator.

8. The learned counsel for the applicant has stated that although the arbitration clause contains
a provision for arbitration by a panel of three arbitrators, the opposite party has not appointed the
arbitrators in terms of the aforesaid clause. Now, that the Court has to appoint the arbitrator, the
applicant requests that to reduce the cost of arbitration, a single arbitrator be appointed in place of a
Tribunal consisting of three arbitrators.

9. In Union of India v. Singh Builders Syndicate: (2009) 4 SCC 523, the appellant had
challenged an order of the Delhi High Court appointing a retired Judge of the High Court as sole
arbitrator to decide the disputes arising in respect of a construction contract between the Northern
Railways and the respondent, whereas arbitration clause in the contract between the parties
required two serving gazetted railway officers of equal status being appointed as arbitrators, one by
the contractor from a panel made available by the General Manager of the Northern Railways and
the other by the Northern Railways, and the two arbitrators so appointed, in turn appointing an
umpire. The High Court was of the view that the matter was pending since 1999 and that the
cumbersome process of constituting an Arbitral Tribunal in terms of the arbitration agreement and
the delays on the part of the Railways in complying with the provisions of the arbitration
agreement, led to the arbitration becoming virtually a non-starter and no useful purpose would be
served by reconstituting a three-Member Arbitral Tribunal. Therefore, the High Court allowed the
petition and appointed a retired Judge of the Delhi High Court as the arbitrator. The said order was
challenged by filing an appeal before the Hon'ble Supreme Court The question that arises for
consideration by the Hon'ble Supreme Court was whether the appointment of a retired Judge of the
High Court as sole arbitrator should be set aside and an Arbitral Tribunal should again be
206 INDIAN LAW REPORTS ALLAHABAD SERIES
constituted in the manner provided in the arbitration agreement. Upholding the order of the High
Court and dismissing the appeal, the Hon'ble Supreme Court held that:-

"13. The position after the new Act came into force, is different, as explained by this
Court in Northern Railway Admn., Ministry of Railway v. Patel Engg. Co. Ltd. [(2008) 10 SCC
240] This Court held that the appointment of arbitrator(s) named in the arbitration agreement is
not mandatory or a must, but the emphasis should be on the terms of the arbitration agreement
being adhered to and/or given effect, as closely as possible.

14. It was further held in Northern Railway case [(2008) 10 SCC 240] that the Chief
Justice or his designate should first ensure that the remedies provided under the arbitration
agreement are exhausted, but at the same time also ensure that the twin requirements of subsection (8) of Section 11 of the Act are kept in view. This would mean that invariably the court
should first appoint the arbitrators in the manner provided for in the arbitration agreement. But
where the independence and impartiality of the arbitrator(s) appointed/nominated in terms of the
arbitration agreement is in doubt, or where the Arbitral Tribunal appointed in the manner
provided in the arbitration agreement has not functioned and it becomes necessary to make fresh
appointment, the Chief Justice or his designate is not powerless to make appropriate alternative
arrangements to give effect to the provision for arbitration."

10. The aforesaid judgment has been followed by the Delhi High Court in the case of 24
Secure Services Pvt. Ltd. v. Competent Automobile Ltd.; 2024 SCC OnLine Delhi 4358, as per
the Arbitration Clause, there had to be a panel of three Arbitrators but the parties could not appoint
one arbitrator each and, therefore, an application was filed under Section 11(6) of the Act. The
Delhi High Court held that: -

"22. In Union of India (UOI) v. Singh Builders Syndicate, (2009) 4 SCC 523 the High
Court rejected the contention on behalf of the Government that the Court was not vested with any
powers to appoint a Sole Arbitrator in distinction to the Arbitration Agreement which provided for
the Tribunal of three members. The Apex Court upheld the order of this Court appointing a Sole
Arbitrator by observing that the appointment of the Sole Arbitrator was valid. 23. In view of the
submissions made as well as Clause 7 of the Services Agreement dated 16.08.2021 which provides
for arbitration and the petitioner has raised the arbitrable disputes and without prejudice to the
rights and contentions of the parties, the present petition is allowed. Mr. Sidharth Sharma Adv.
Mobile No. 7400111111, is hereby appointed as the Arbitrator to adjudicate the disputes between
the parties."

11. This decision has been followed by Delhi High Court in the case of Jhajharia Nirman
Ltd. v. South Western Railways through Dy. Chief Engineer/IV Construction reported in 2024
SCC OnLine Del 7133 wherein also, the arbitration clause contained a stipulation of appointment
of an Arbitral Tribunal consisting of three arbitrators but the parties had failed to constitute the
Tribunal by consent.

12. I find myself in agreement with the aforesaid decision taken by the Delhi High court in the
aforesaid cases and I am also of the view that although the arbitration agreement contained
provision for constituting a panel of three arbitrators ? one arbitrator to be appointed by each of the
2 All. M S Kalicharan Pandey & Company Vs. Union of India & Ors.
207
parties and the third arbitrator or the umpire being appointed by the two arbitrators, the parties fail
to appoint their arbitrators, an application under Section 11(6) of the Act is filed and a party
requests that it is not willing to bear the high cost of arbitration to be conducted by a panel of three
arbitrators and in order to reduce the costs, it requests appointment of a sole arbitrator, this Court
can accede to the request.

13. Accordingly, I propose the name of Hon'ble Mr. Justice V. K. Mathur (Retd.), a former
Judge of this Court, resident of Flat No.- 203, Samiah Melrose Square, Vrindawan Colony, Sector
6C, Near C.N.G. Pump, Lucknow (U.P.) / 304, Radium Apartments, New Hyderabad, Lucknow,
U.P., Mobile Nos. 8004928876, 9717779924 to act as an arbitrator for adjudication of the disputes
between the parties.

14. Office is directed to communicate this order to Hon'ble Mr. Justice V. K. Mathur for
obtaining his consent.

15. List after receipt of service.
----------
(2026) 2 ILRA 207
APPELLATE JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 11.02.2026

BEFORE

THE HON'BLE PIYUSH AGRAWAL, J.

Arbitration And Conciliation Appl. U/S11(4) No. 33 of 2024

M S Kalicharan Pandey & Company ...Appellant
Versus
Union of India & Ors. ...Opposite Parties

Issue for Consideration
Issue pertains to whether, in exercise of powers u/s 11(6) of Arbitration and Conciliation Act, 1996, the High
Court is required to appoint a sole Arbitrator upon prima facie satisfaction of the existence of a valid
arbitration agreement between the parties and the failure of the parties to mutually agree upon such
appointment, without delving into the merits of the underlying dispute.

Headnotes
Arbitration and Conciliation Act, 1996 - s. 11(6) - Appointment of Arbitrator - Arbitration
Agreement - Arbitration Clause - Appointing Authority - Scope of - The applicant, invoked the
arbitration clause contained in the agreement between the parties by issuing a notice dated
11.08.2023 to the respondents, namely the Union of India and others, seeking resolution of
disputes through arbitration - The respondents, however, vide reply dated 10.10.2023, denied
the invocation of arbitration - In view of existence of disputes between the parties and the
failure to arrive at a consensual appointment of an arbitrator in terms of agreed procedure, the
applicant instituted the instant application u/s 11(6) of Arbitration and Conciliation Act, 1996
before the High Court for appointment of a sole arbitrator.