# Smt. Aaisha Siddique v. Senior Terminal Manager, IOC Terminal and anotherher

- **Citation:** (2002) 3 ILRA 874
- **Court:** High Court of Judicature at Allahabad
- **Decided:** 2002-10-01
- **Case number:** Civil Misc. Writ Petition No. 38940 of 2002
- **Bench:** M. Katju, R. Tiwari
- **Source:** https://unisonlegal.in/judgment/allahabad-high-court/smt-aaisha-siddique-v-senior-terminal-manager-ioc-terminal-and-anotherher-40027
- **Pages:** 2

## Headnote

Land Acquisition Act- section 3- even
assuming
that
there
was
some
construction on the land in question, this
Court
cannot
interfere
with
the
acquisition because the word 'land' in
section 3 of the Land Acquisition Act
includes 'Buildings and trees' also. Hence
even assuming that the land was abadi
or there were constructions on the land
in question, in our opinion the said land
can
be
acquired
under
the
Land
Acquisition Act and this Court cannot
interfere.

Held in para 19

Moreover, we are of the opinion that in
fact the land in question was agricultural
land and it was only after the notification
under Section 4 that the petitioner tried
to give a colour that the land was abadi
and there were constructions.
Case Law referred:
AIR 1971 SC 1033,
(1986) 4 SCC 251, (1996) 10 SCC 721, 1991
AWC 1210, 1989 AWC 1137, (1991) AWC 341,
AIR 1969 SC 255, 1980 ACJ 583

## Text

http://www.allahabadhighcourt.nic.in
874 INDIAN LAW REPORTS ALLAHABAD SERIES [2002
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 1.10.2002

BEFORE
THE HON'BLE M. KATJU, J.
THE HON'BLE R. TIWARI, J.

Civil Misc. Writ Petition No. 38940 of 2002

Smt. Aaisha Siddique

...Petitioner
Versus
Senior Terminal Manager, IOC Terminal
and another

 ...Respondents

Counsel for the Petitioner:
Sri W.H. Khan

Counsel for the Respondents:
Sri P. Padia

Constitution
of
India-
226-
Tender
submitted beyond 10 minute- Prescribed
Period 12-00 No.- whether the Court can
extend it by 10 minute ? - "No" if 10
minutes extended , why not 10 hours on
ten months- one has to be strict in such
matter.

Held - para 3

In our opinion, time is of the essence in
such
matters,
otherwise
the
legal
position will be totally chaotic. For
example, if in an election on the election
day the voting can take place from 8.00
a.m. to 4.00 p.m. and a voter reaches the
polling station at 4.10 p.m. and states
that he be allowed to cast his vote, in our
opinion he cannot be allowed to do so,
whatsoever may be reason for the delay.
Similarly, this Court cannot extend the
time for submission of the tenders. If we
extend it by 10 minute, then why not for
10 hours or ten days ? Where will the
line be drawn. Hence the only correct
view can be that one has to be strict in
such matters. Since the petitioner did
not reach in time her tender it cannot be
accepted.

(Delivered by Hon'ble M. Katju, J.)

1. Heard learned counsel for the
parties.

2. The petitioner has prayed that the
respondents be directed to entertain and
consider
the
petitioner's
tender
in
pursuance of the tender notice 29.7.2002.
The last date and time of submitting the
tender in pursuance of the tender notice
dated 29.7.2002 was 21.8.2002 by 12.00
Noon. It has been alleged in paragraph 4
of the writ petition that because of traffic
jam the petitioner's driver could not reach
at the office of the respondents at 12.00
noon but reached there at 12.10 p.m., that
is, he was late by 10 minutes. Although,
in paragraphs 6 and 9 of the counter
affidavit it has been stated that in fact the
petitioner's tender was not given on
21.8.2002 but was given on 22.8.2002,
but even assuming that the allegation of
the petitioner is correct there is no doubt
that the tender was late by 10 minutes.

3. In our opinion, time is of the
essence in such matters, otherwise the
legal position will be totally chaotic. For
example, if in an election on the election
day the voting can take place from 8.00
a.m. to 4.00 p.m. and a voter reaches the
polling station at 4.10 p.m. and states that
he was late by 10 minutes because of a
traffic jam and insists that he be allowed
to cast his vote, in our opinion he cannot
be allowed to do so, whatsoever may be
reason for the delay. Similarly, this Court
cannot extend the time for submission of
the tenders. If we extend it by10 minutes,
then why not for 10 hours or ten days ?
Where will the line be drawn. Hence the
only correct view can be that one has to
be strict in such matters. Since the
http://www.allahabadhighcourt.nic.in
3 All] Smt. Aaisha Siddique V. Senior Terminal Manager, IOC Terminal and anotherher 875
petitioner did not reach in time to submit
her tender it cannot be accepted.

4. The writ petition is dismissed.
---------
ORIGINAL JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD OCTOBER 9, 2002

BEFORE
THE HON'BLE M. KATJU, J.
THE HON'BLE RAKESH TIWARI, J.

Civil Misc. Writ Petition No. 43250 of 2000

Manveer Singh and another ...Petitioner
Versus
State of U.P. and others ...Respondents

Counsel for the Petitioners:
Sri S.G. Hasnain

Counsel for the Respondents:
Sri B.D. Mandhyan
S.C.

Land Acquisition Act- section 3- even
assuming
that
there
was
some
construction on the land in question, this
Court
cannot
interfere
with
the
acquisition because the word 'land' in
section 3 of the Land Acquisition Act
includes 'Buildings and trees' also. Hence
even assuming that the land was abadi
or there were constructions on the land
in question, in our opinion the said land
can
be
acquired
under
the
Land
Acquisition Act and this Court cannot
interfere.

Held in para 19

Moreover, we are of the opinion that in
fact the land in question was agricultural
land and it was only after the notification
under Section 4 that the petitioner tried
to give a colour that the land was abadi
and there were constructions.
Case Law referred:
AIR 1971 SC 1033,
(1986) 4 SCC 251, (1996) 10 SCC 721, 1991
AWC 1210, 1989 AWC 1137, (1991) AWC 341,
AIR 1969 SC 255, 1980 ACJ 583

(Delivered by Hon'ble M. Katju, J.)

1. This writ petition alongwith
connected writ petition no. 3301 of 2001
are being disposed of by a common
judgment.

2. Heard learned counsel for the
parties.

3. The petitioners had challenged the
impugned notification dated 21.11.1996
published
by
public
notice
dated
24.8.1999 under Section 4 (1) of the Land
Acquisition Act and the notification dated
23.8.2000 published through public notice
dated 23.8.2000 under Section 6/17 of the
Land Acquisition Act vide Annexure 7
and 10 to the writ petition. The petitioners
have also prayed for mandamus directing
the respondent not to proceed in the
matter of acquisition proceedings and not
to demolish the constructions on the land
in dispute.

4. The petitioner no. 1 claims to be
owner of plot no. 30 and the petitioner no.
2 of plot no. 31 in village Wajidpur,
paragana and Tahsil Khurja, district
Bulandshahr. It is alleged in paragraph 3
of the writ petition that the said land has
been used by the petitioners as abadi land.
The Khasra entries are Annexure 1 and 2
to the writ petition. In paragraph 4 of the
writ petition it is alleged that the
petitioners have raised constructions over
the said land and then sought permission
to change the nature of the land under
Section 143 of the U.P.Z.A. & L.R. Act.
On the application of the petitioner the
S.D.M., Khurja after receiving report of