# Smt. Ahmadunnisa v. Smt. Jubeda

- **Citation:** (2016) 5 ILRA 1714
- **Court:** High Court of Judicature at Allahabad
- **Decided:** 2016-05-05
- **Bench:** Pramod Kumar Srivastava
- **Source:** https://unisonlegal.in/judgment/allahabad-high-court/smt-ahmadunnisa-v-smt-jubeda-43810
- **Pages:** 7

## Headnote

Shri R.C. Singh

Held -

Para 1: The Court heard both parties and examined the records.
Para 2: Plaintiff (Ahmadun Nisha) sued for specific performance based on a 1973 agreement to sell.
Defendant (Jubeda) received half the consideration, agreeing to transfer the property once the government
lifted the ban on urban sales.
Para 3: Defendant denied the intent to sell, claiming the document was meant to be a tenancy agreement and
that the plaintiff committed fraud by misrepresenting the nature of the deed.
Para 4: The Trial Court originally decreed the suit in favor of the plaintiff, ordering the execution of the sale
deed.
Para 5: The Trial Court found the defendant's "tenancy" defense concocted, noting the defendant admitted to
the registered deed and receipt of money.
Para 6: The Trial Court ruled the document was executed with a "conscious mind" in the presence of the
defendant's husband, and the plaintiff was ready and willing to perform.
Para 7: On appeal, the First Appellate Court reversed the decree, dismissing the suit as time-barred because it
was filed years after the government ban was lifted.
Para 8: The plaintiff filed this Second Appeal against the dismissal.
Para 9: Two legal questions were framed: whether limitation started from the date of refusal and whether the
court could dismiss the suit without a specific plea that "time was of the essence."
Para 10: It is admitted the ban was lifted in November 1975. The contract required execution within one
month of that lifting. The suit was only filed in 1986.
Para 11: Appellant argued the suit was timely because the "refusal" only happened in 1986 after a legal
notice.
Para 12: Respondent argued time was the essence; the cause of action arose in 1975, making a 1986 filing
nearly nine years late.
5 All. Smt. Ahmadunnisa Vs Smt. Jubeda

1715
Paras 13-17: The Court reviewed various precedents (Bhajan Lal, Jamil Ahmad, etc.) regarding Article 54 of
the Limitation Act, which sets a three-year window from either the "fixed date" or the "date of notice of
refusal."
Para 18: The Court noted the plaintiff's own plaint admitted the cause of action first arose in November 1975.
Para 19: Since the contract fixed a date (one month after the ban lifted), the deadline was December 1975.
Para 20: Under the Limitation Act, the suit should have been filed by December 1978. No explanation was
given for the eight-year delay.
Para 21: The Court rejected the claim that a 1984 refusal reset the clock; the suit was already "dead" by
limitation in 1978.
Para 22: The Court concluded that since a specific timeframe was linked to a known event (lifting the ban),
time was the essence. The First Appellate Court's finding of a time-bar was correct.
Para 23: The Trial Court's initial judgment was found to be erroneous for failing to appreciate these facts.
Para 24: The First Appellate Court's judgment is confirmed as legally sound.
Para 25: The Second Appeal is dismissed.

List of Citations
Bhajan Lal and another Vs. Bal Govind and another, 2007 (4) AWC 3832.
Jamil Ahmad Vs. Sayeed Ahmad and others, 2008 (1) AWC 736.
The Gunwantbhai Mulchand Shah and others Vs. Anton Elis Farel and others, 2006 (2) AWC 1475
(SC).
Ahmmadsahab Abdul Mulla (D) by proposed L.Rs. Vs. Bibijan and others, 2009 (2) AWC 1863
(SC).
R.K. Parvatharaj Gupta Vs. K.C. Jayadeva Reddy, 2006 (2) AWC 1336 (SC).

## Text

1714 INDIAN LAW REPORTS ALLAHABAD SERIES
----------
APPELLATE JURISDICTION
CIVIL SIDE
DATED: ALLAHABAD 05.05.2016

BEFORE

THE HON'BLE PRAMOD KUMAR SRIVASTAVA, J.

Second Appeal No.- 743 Of 1989

Smt. Ahmadunnisa ...Appellant
Versus
Smt. Jubeda ...Respondent

Counsel for the Appellant:
Shri Shashi Nandan

Counsel for the Respondent:
Shri R.C. Singh

Held -

Para 1: The Court heard both parties and examined the records.
Para 2: Plaintiff (Ahmadun Nisha) sued for specific performance based on a 1973 agreement to sell.
Defendant (Jubeda) received half the consideration, agreeing to transfer the property once the government
lifted the ban on urban sales.
Para 3: Defendant denied the intent to sell, claiming the document was meant to be a tenancy agreement and
that the plaintiff committed fraud by misrepresenting the nature of the deed.
Para 4: The Trial Court originally decreed the suit in favor of the plaintiff, ordering the execution of the sale
deed.
Para 5: The Trial Court found the defendant's "tenancy" defense concocted, noting the defendant admitted to
the registered deed and receipt of money.
Para 6: The Trial Court ruled the document was executed with a "conscious mind" in the presence of the
defendant's husband, and the plaintiff was ready and willing to perform.
Para 7: On appeal, the First Appellate Court reversed the decree, dismissing the suit as time-barred because it
was filed years after the government ban was lifted.
Para 8: The plaintiff filed this Second Appeal against the dismissal.
Para 9: Two legal questions were framed: whether limitation started from the date of refusal and whether the
court could dismiss the suit without a specific plea that "time was of the essence."
Para 10: It is admitted the ban was lifted in November 1975. The contract required execution within one
month of that lifting. The suit was only filed in 1986.
Para 11: Appellant argued the suit was timely because the "refusal" only happened in 1986 after a legal
notice.
Para 12: Respondent argued time was the essence; the cause of action arose in 1975, making a 1986 filing
nearly nine years late.
5 All. Smt. Ahmadunnisa Vs Smt. Jubeda

1715
Paras 13-17: The Court reviewed various precedents (Bhajan Lal, Jamil Ahmad, etc.) regarding Article 54 of
the Limitation Act, which sets a three-year window from either the "fixed date" or the "date of notice of
refusal."
Para 18: The Court noted the plaintiff's own plaint admitted the cause of action first arose in November 1975.
Para 19: Since the contract fixed a date (one month after the ban lifted), the deadline was December 1975.
Para 20: Under the Limitation Act, the suit should have been filed by December 1978. No explanation was
given for the eight-year delay.
Para 21: The Court rejected the claim that a 1984 refusal reset the clock; the suit was already "dead" by
limitation in 1978.
Para 22: The Court concluded that since a specific timeframe was linked to a known event (lifting the ban),
time was the essence. The First Appellate Court's finding of a time-bar was correct.
Para 23: The Trial Court's initial judgment was found to be erroneous for failing to appreciate these facts.
Para 24: The First Appellate Court's judgment is confirmed as legally sound.
Para 25: The Second Appeal is dismissed.

List of Citations
Bhajan Lal and another Vs. Bal Govind and another, 2007 (4) AWC 3832.
Jamil Ahmad Vs. Sayeed Ahmad and others, 2008 (1) AWC 736.
The Gunwantbhai Mulchand Shah and others Vs. Anton Elis Farel and others, 2006 (2) AWC 1475
(SC).
Ahmmadsahab Abdul Mulla (D) by proposed L.Rs. Vs. Bibijan and others, 2009 (2) AWC 1863
(SC).
R.K. Parvatharaj Gupta Vs. K.C. Jayadeva Reddy, 2006 (2) AWC 1336 (SC).

(Delivered by Hon'ble Pramod Kumar Srivastava, J.)

1. Heard the arguments of learned counsel for the parties and perused the records.

2. Original suit no. 2315 of 1986 (Smt. Ahmadun Nisha v. Smt. Jubeda) was filed for
specific performance of contract. The plaint case in brief was that registered agreement to sell dated
05.03.1973 was executed between the parties, by which defendant Smt. Jubeda had agreed to sell
her property in question to plaintiff Smt. Ahmadunnisa for a consideration of Rs. 4,000/- and had
received advance consideration of Rs. 2,000/-. It was agreed that defendant will execute the saledeed of this property to plaintiff after withdrawal of ban of sale of urban property by government.
But later on, defendant had not executed the sale-deed in spite of reminder, then plaintiff had sent
her legal notice dated 03.03.1980 and also orally requested. The plaintiff has been ready ad willing
to perform his part of contract by paying remaining consideration for getting the sale-deed executed
but defendant was not willing to perform her part of contract, therefore, plaintiff had filed suit for
specific performance of aforesaid registered agreement for sale.

3. Defendant Smt. Had filed written statement in original suit, by which plaint case was not
denied. It was further pleaded that defendant had no intention to sell her property nor she had
executed any agreement for sale, and not received any advance consideration. In fact plaintiff's
husband needed a house for rent and he showed his willingness to defendant for taking her house
on tenancy for which defendant was ready. But defendant's husband had asked to get the document
of tenancy prepared and registered, for which plaintiff came with her husband to court. The
1716 INDIAN LAW REPORTS ALLAHABAD SERIES
defendant received Rs. 2000/- as advance rent. The plaintiff's husband, with ulterior motive,
colluded with scribe and witnesses who prepared the document. In place of document of tenancy,
they prepared the document of agreement for sale by playing fraud on defendant and her husband.
Plaintiff had filed this suit for specific performance of contract on basis of incorrect facts. This suit
is time barred and is liable to be dismissed.

4. After framing issues, accepting evidences and affording opportunity of hearing to
parties, the Court of 4th Additional Munsif, Gorakhpur had decreed the original suit by its judgment
dated 18.01.1988 and directed the defendant to receive remaining consideration of Rs. 2,000/- from
plaintiff and execute the sale-deed of disputed property, failing which plaintiff would be entitled to
get the sale-deed executed through court.

5. In this judgment, trial court had appreciated the evidences and contentions of the parties
and gave specific finding that in this matter execution of registered deed of contract of sale and
receiving of Rs. 2000/- has been admitted by defendant. But it is not proved that plaintiff had taken
any house on rent from defendant, or that any such amount was ever returned by defendant to
plaintiff. Trial court held that defence of defendant is concocted version.

6. The trial court had also held that in this matter registered agreement to sell was executed
in presence of husband of defendant who is government official and had played active role in the
transaction in question; and also that there is no evidence that transaction in question was for
tenancy, or that any amount of Rs. 2,000/- was refunded by defendant. Trial court had given finding
that document in question was executed by conscious mind, and there is no evidence that any
forgery was committed by plaintiff. On the basis of evidences the trial court had also given finding
that the plaintiff has been ready and willing to perform is part of contract regarding execution of
sale-deed, which is proved from evidences. On the basis of these findings, trial court had decreed
the original suit.

7. Against the judgment of trial court, Civil Appeal no. 64 of 1988 (Smt. Jubeda v. Smt.
Ahmadun Nisha) was preferred by defendant of the original suit. This appeal was heard and
allowed by the judgment dated 13.01.1989 of 10th Additional District Judge, Gorakhpur. In this
judgment the first appellate court had not framed the point of determination but decided the civil
appeal with finding that after raising of ban on sale of property in question, the belated suit was
filed beyond period of limitation, without any proper explanation of such delay; therefore suit is
dismissed as being barred by time.

8. Aggrieved by the judgments of the first appellate court, present second appeal has been
preferred by the plaintiff of the original suit.

9. At the time of admission of this appeal following substantial questions of law were
adopted:
5 All. Smt. Ahmadunnisa Vs Smt. Jubeda

1717
(1) Whether the court below has wrongly held that the suit was barred by limitation
inasmuch as the period of limitation actually commenced from the date of refusal of the defendant
from execution the sale-deed?

(2) Whether the court below was justified in setting aside the judgment of the Trial
Court in the absence of any pleading in the w.s. that time was essence of the contract?

10. It has been admitted fact between the parties that at the time of execution of registered
agreement for sale dated 5.3.1973, government had imposed ban on sale of urban immovable
property. It is mentioned in said deed of agreement to sell that after lifting of said ban sale-deed in
question will executed within one month. It is also proved from the evidences that Government had
lifted ban for the sale of transfer of immovable urban property in the month of November, 1975.
According to plaint averment, defendant resiled from the terms of agreement to sell, therefore she
had given registered notice dated 3.9.1986 to defendant for execution of sale-deed and when
defendant had failed to execute sale-deed, then she was forced to institute the original suit for
specific performance of contract.

11. Learned counsel for the plaintiff-appellant contended that, in fact, the defendantrespondent had refused the execution of sale-deed in year 1986, then plaintiff had given her the
legal notice and instituted original suit thereafter within time, therefore, suit is not time barred. He
further contended that in this matter, the time was not essence of the contract, therefore when
plaintiff refused to execute sale-deed in year 1984 and year 1986 after service of notice dated
3.9.1986, then original suit was instituted on 29.9.1986. He contended that in such matter cause of
action arises from the time of refusal by defendant, therefore the cause of action arose after legal
notice dated 3.9.1986.

12. These contentions were refuted by learned counsel for the respondent, who contended
that in this particular matter, time was the essence of the contract, as it was specifically mentioned
in the contract in question that sale-deed would be executed within one month after lifting of the
ban on sale of immovable property. He contended that such ban was lifted in November, 1975, well
within knowledge of plaintiff, but he had not been willing to perform his part of contract, so he had
not given any notice till year 1996 and suit was filed after about nine years of arising of cause of
action. Therefore, it is time barred.

13. Learned counsel for the appellant relied on Bhajan Lal and another Vs. Bal Govind
and another, 2007 (4) AWC 3832, in which this Court had held as under:-

"14. From the aforesaid, it is clear, that for the purpose of institution of a suit for
specific performance, two dates are material, namely, the date fixed for specific performance of
agreement and if such date is not fixed, in that event, the date when the plaintiffs had notice that the
performance was refused. Consequently, the date of the execution of the agreement is immaterial.
What is material is, the date of the refusal of the performance of the agreement of the
defendants........"
1718 INDIAN LAW REPORTS ALLAHABAD SERIES
14. Appellant side had also relied on Jamil Ahmad Vs. Sayeed Ahmad and others, 2008
(1) AWC 736, in which Single Bench of this Court had held as under:-

"11.......The time of three years, for filing a suit begins to run from the date fixed
for the performance and if no such date is fixed, then from the date when the plaintiff had noticed
that the performance was refused.........."

15. The Gunwantbhai Mulchand Shah and others Vs. Anton Elis Farel and others,
2006 (2) AWC 1475 (SC), was also relied by appellant side in which the Apex Court had held:-

"8............But in a case where no time for performance was fixed, the Court had to
find the date on which the plaintiff had notice that the performance was refused and on finding that
date, to see whether the suit was filed within three years thereof....."

16. In Ahmmadsahab Abdul Mulla (D) by proposed L.Rs. Vs. Bibijan and others, 2009
(2) AWC 1863 (SC, the Apex Court had held as under:-

"7. The inevitable conclusion is that the expression 'date fixed for the
performance' is a crystallized notion. This is clear from the fact that the second part "time from
which period begins to run" refers to a case where no such date is fixed. To put it differently, when
date is fixed it means that there is a definite date fixed for doing a particular act......"

17. In R.K. Parvatharaj Gupta Vs. K.C. Jayadeva Reddy, 2006 (2) AWC 1336 (SC),
the Apex Court had held as under:-

"18. Thus, even though the time for performance was not fixed in the agreement
for sale, on receipt of the notice, the respondent had notice that the performance was being refused,
if he failed to fulfil his obligation under the contract within 15 days of receipt of the notice.

19. The suit was, therefore, in terms of the requirement of Article 54 of the
Limitation Act, should have been filed within a period of three years from the date of expiry of
fifteen days from the date of receipt of the said notice."

18. These verdicts make it clear that when there has been a date fixed in the contract for
sale, the limitation for suit for specific performance shall start running from time fixed in such
contract. It is also settled legal position that when any specific date is not fixed in contract for sale
and/or when time for execution of sale-deed is not essence of contract, then the limitation would
start from the date when defendant refused to perform his part of contract. In present matter, cause
of action, for the suit is mentioned in paragraph 12 of the plaint, which is as under:-

"12. That the cause of action for the suit for the first time arose in the month of
'Novr. 1975' when the ban for the transfer of immovable property was lifted by the State Govt. And
again in the month of Jan. 1978 when the plff approached the defdt for execution of sale-deed and
5 All. Smt. Ahmadunnisa Vs Smt. Jubeda

1719
again in the month of Novr. 1984 and finally on 3.9.1986 when the registered notice was sent and
the defdt failed to execute the sale-deed in favour of the plff after the expiry of the period
mentioned in the notice regarding the property situated in Mohalla Turkmanpur city of Gorakhpur
within the territorial and pecuniary jurisdiction of this Hon'ble court."

19. Admittedly, according to terms of written registered contract for sale, the sale-deed had
to be executed within one month from lifting of ban by Government on sale of such property and
said ban was lifted in November, 1975. There is no plaint averment that plaintiff had no knowledge
of the fact of lifting of such ban. Therefore, according to terms of contract sale-deed had to be
executed within one month from lifting of such ban in November, 1975, which is up to December,
1975.

20. Admittedly, plaintiff was not ready to perform his part of contract and had not taken
any step for execution of sale-deed, so cause of action for execution of sale-deed arose to plaintiffappellant firstly in November, 1975 and cause of action for the suit arose one month thereafter in
December, 1975, when defendant-respondent had not executed sale-deed. In these circumstances,
in view of the provisions of Section 54 of Indian limitation Act regarding three period of imitation
for institution of said suit, the original suit for specific performance of contract in question would
have been within time till December, 1978. But neither such suit was filed nor any satisfactory
explanation was given by plaintiff-appellant for not taking steps for filing the suit. Therefore,
original suit appears clearly barred by limitation.

21. When the suit had become time barred in December, 1978, then there was no reason for
plaintiff to wait again till year 1984 or 1986. According to plaintiff-appellant's case in year 1984
the defendant had refused to execute sale-deed but simply assured that whenever she would be
mentally prepared to execute the sale-deed, she will inform the plaintiff. This fact has not been
proved from evidences. Even, for the sake argument, if this fact is accepted to be true, this means
that plaintiff had refused even in 1984 to execute the sale and had not informed any particular time
for execution of sale-deed. From the perusal of paragraph 12 of the plaint, as above, which
discloses the cause of action for the suit, it is clearly evident that suit is time barred.

22. From the evidences, it is proved that parties had not taken any steps, without any reason
to execute sale-deed within one month from lifting of ban on such sale as agreed between them and
within three years thereafter. These acts of plaintiff in itself are proof of refusal by defendantrespondent to execute sale-deed. In present matter, definite time for execution of sale-deed was
agreed between the parties, which was within one month from the lifting of ban of sale by
Government and said ban was lifted in November, 1975 within knowledge of parties. Therefore,
after lapse of period of one month, the limitation for the original suit started running in December,
1975 and ended in December, 1978. Therefore, in light of legal position discussed in the citations
relied by appellant's side, suit was time barred because time was the essence of the contract and
definite period was fixed for execution of sale-deed in question in explicitly clear words in the
document of contract in question. These facts were properly and meticulously scrutinized and
discussed by first appellate court. The finding of first appellate court in this regard is based on
1720 INDIAN LAW REPORTS ALLAHABAD SERIES
proper appreciation of evidences and is found correct. In fact, cause of action for the suit arose in
December, 1975 and had run till December, 1978 because time was essence of the contract as
specifically mentioned in agreement to sell in question. So suit filed in year 1986 is clearly barred
by limitation and alleged refusal mentioned in plaint after notice dated 3.9.1986 cannot be accepted
as actual date of refusal. Refusal to perform her part of contract by defendant-respondent can be
properly inferred by circumstances as well as conduct of the parties. This was correctly done by the
lower appellate court. Accordingly, first substantial question of law is decided in negative, against
the appellant and in favour of the respondent.

23. On the basis of above discussion, it is proved that since specific time for execution of
sale-deed in question was given in contract for sale in question, which has been within knowledge
of the parties, therefore the time was essence of the contract in question, therefore the original suit
instituted after lapse of three years period of instituting suit ending in December, 1978, was time
barred. The findings of trial court in this regard were erroneous without appreciating the merits of
the facts. Therefore, they were rightly reversed by first appellate court, which was justified in
setting aside the judgment of trial court for this reason. Accordingly, second substantial question of
law is also decided against the appellant and in favour of the respondent.

24. In view of the above, it is hereby held that first appellate court had properly and
correctly appreciated the available facts, circumstances and adduced evidences, and thereafter gave
its correct finding by reversing the judgment of trial court and allowing the appeal and dismissing
the original suit. There appears no factual or legal error in the impugned judgment of first appellate
court. Therefore, said judgment is hereby confirmed.

25. Accordingly, this second appeal is dismissed.
--------
APPELLATE JURISDICTION
CRIMINAL SIDE
DATED: ALLAHABAD 04.05.2016

BEFORE

THE HON'BLE SHASHI KANT GUPTA, J.
THE HON'BLE KAUSHAL JAYENDRA THAKER, J.

Criminal Appeal No.- 766 Of 1984

Mahesh Kahar ...Appellant
Versus
State Of U.P. ...Respondent

Counsels for the Appellant:
Shri S.A.N. Shah, Shri Ajatshatru Pandey, G.S. Chaturvedi

Counsel for the Respondent: