# CLP INDIA PVT. LTD v. GUJARAT URJA VIKAS NIGAM LTD. & ANR

- **Citation:** [2020] 6 S.C.R. 598
- **Court:** Supreme Court of India
- **Decided:** 2020-05-06
- **Case number:** Civil Appeal No. 2793 of 2010
- **Bench:** Arun Mishra, Vineet Saran, S. Ravindra Bhat
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/clp-india-pvt-ltd-v-gujarat-urja-vikas-nigam-ltd-anr-34104
- **Pages:** 22

## Headnote

Electricity Supply Act, 1948 - s.43(A) - Gujarat Electricity
Board (Gujarat Urja) entered into a power purchase agreement
(PPA) with CLP on 03.02.1994 - In terms of the PPA, Gujarat Urja
was under an obligation to purchase and CLP was under the
corresponding obligation to supply electricity - Prior PPA, the
Central Government had issued notification on 30.03.1992, one of
the conditions in it was the provision for incentive to units using
naphtha - After the signing of the PPA, an amendment notification
dated 06.11.1995 was issued by the Central Government amending
the notification (dated 30.03.1992), which provided that there would
no longer be any deemed Generation Incentive payable to any
generating company on available declaration of naphtha as fuel -
Gujarat Urja sought to enforce said notification - However, CLP
ignored the amended notification and billed Gujarat Urja for the
power supplied, w.e.f. December, 1997 and Gujarat Urja paid
deemed Generation Incentive - Thereafter, Gujarat Urja filed
application for recovery of the amounts from CLP paid during the
period from 1997-1998 to 2005-06 - GERC, by its order held that
the notification of 06.11.1995 was applicable and deemed
Generation Incentive is not payable to CLP - However, it permitted
recovery of only for a period of three years prior to the date of
filing of the petition: the recovery for the period prior to 14.09.2002
was held to be time-barred - APTEL upheld the order of the GERC
- On appeal, held: The two notifications dated 30.03.1992 and
06.11.1995 were issued u/s. 43(A) of the Electricity Supply Act, 1948
- Concededly, these notifications are statutory and are binding on
the parties - Any PPA between a generating company and the
purchaser of electricity is subject to such statutory notifications;
parties by agreement cannot override statutory provisions, or such
notifications, as far as they relate to matters of tariff - So, the
A
B
C
D
E
F
G
H
599
notification amended on 06.11.1995 was a statutory one and was
binding on both the parties - The effect of this statutory
incorporation by way of amendment was that incentive no longer
became payable - Also, the concurrent findings of the GERC and
APTEL in granting restricted refund calculable for the 3 year period
prior to Gujarat Urja's application are reasonable - The findings
of the lower authorities, therefore, are correct; no interference
required.
Electricity Supply Act, 1948 - s.43(A) - Gujarat Electricity
Board (Gujarat Urja) entered into a power purchase agreement
(PPA) with CLP on 03.02.1994 - In terms of the PPA, Gujarat Urja
was under an obligation to purchase and CLP was under
corresponding obligation to supply electricity - A supplementary
agreement was executed between the parties on 05.12.2003 - CLP
stated that the amount, i.e Rs. 53.90 crores was in fact due as a
loan - If it was deemed as a loan, then interest was payable on the
basis of normative repayment of principal amount during the period
of the loan, i.e. the loan would not remain as a constant - Gujarat
Urja resisted this claim - The GERC rejected the CLP's argument
on a plain reading of the clause in the supplementary agreement,
which stated that the agreement too recognized Rs.53.9 crores as
own Capital for which the cost of Own Capital @ 14% was to be a
pass through - The effective date for such recognition was from
01.07.2003 to 31.03.2009 and no amounts were due and payable
as interest after that date - This excluded any liability on part of
Gujarat Urja for the past period, i.e. December 1997 - The CLP
Limited was aggrieved by that portion of GERC's order which
rejected its claim on the deemed loan component prior to the period
2003 - The APTEL concurred with the decision of GERC - On
appeal, held: The clear agreement between the parties was that
interest on the sum of Rs.53.90 crores was payable for the specified
period 01.07.2003 to 31.12.2009 - Therefore, CLP's claim that any
amount was payable, for any period prior to 01.07.2

## Text

_Characters 0–39,921 of 54,627. This is a partial read: ask again with offset=39921 for what follows._

A
B
C
D
E
F
G
H
598
SUPREME COURT REPORTS
[2020] 6 S.C.R.
[2020] 6 S.C.R. 598
598
CLP INDIA PVT. LTD.
v.
GUJARAT URJA VIKAS NIGAM LTD. & ANR.
(Civil Appeal No. 2793 of 2010)
MAY 06, 2020
 [ARUN MISHRA, VINEET SARAN AND
S. RAVINDRA BHAT, JJ.]
Electricity Supply Act, 1948 - s.43(A) - Gujarat Electricity
Board (Gujarat Urja) entered into a power purchase agreement
(PPA) with CLP on 03.02.1994 - In terms of the PPA, Gujarat Urja
was under an obligation to purchase and CLP was under the
corresponding obligation to supply electricity - Prior PPA, the
Central Government had issued notification on 30.03.1992, one of
the conditions in it was the provision for incentive to units using
naphtha - After the signing of the PPA, an amendment notification
dated 06.11.1995 was issued by the Central Government amending
the notification (dated 30.03.1992), which provided that there would
no longer be any deemed Generation Incentive payable to any
generating company on available declaration of naphtha as fuel -
Gujarat Urja sought to enforce said notification - However, CLP
ignored the amended notification and billed Gujarat Urja for the
power supplied, w.e.f. December, 1997 and Gujarat Urja paid
deemed Generation Incentive - Thereafter, Gujarat Urja filed
application for recovery of the amounts from CLP paid during the
period from 1997-1998 to 2005-06 - GERC, by its order held that
the notification of 06.11.1995 was applicable and deemed
Generation Incentive is not payable to CLP - However, it permitted
recovery of only for a period of three years prior to the date of
filing of the petition: the recovery for the period prior to 14.09.2002
was held to be time-barred - APTEL upheld the order of the GERC
- On appeal, held: The two notifications dated 30.03.1992 and
06.11.1995 were issued u/s. 43(A) of the Electricity Supply Act, 1948
- Concededly, these notifications are statutory and are binding on
the parties - Any PPA between a generating company and the
purchaser of electricity is subject to such statutory notifications;
parties by agreement cannot override statutory provisions, or such
notifications, as far as they relate to matters of tariff - So, the
A
B
C
D
E
F
G
H
599
notification amended on 06.11.1995 was a statutory one and was
binding on both the parties - The effect of this statutory
incorporation by way of amendment was that incentive no longer
became payable - Also, the concurrent findings of the GERC and
APTEL in granting restricted refund calculable for the 3 year period
prior to Gujarat Urja's application are reasonable - The findings
of the lower authorities, therefore, are correct; no interference
required.
Electricity Supply Act, 1948 - s.43(A) - Gujarat Electricity
Board (Gujarat Urja) entered into a power purchase agreement
(PPA) with CLP on 03.02.1994 - In terms of the PPA, Gujarat Urja
was under an obligation to purchase and CLP was under
corresponding obligation to supply electricity - A supplementary
agreement was executed between the parties on 05.12.2003 - CLP
stated that the amount, i.e Rs. 53.90 crores was in fact due as a
loan - If it was deemed as a loan, then interest was payable on the
basis of normative repayment of principal amount during the period
of the loan, i.e. the loan would not remain as a constant - Gujarat
Urja resisted this claim - The GERC rejected the CLP's argument
on a plain reading of the clause in the supplementary agreement,
which stated that the agreement too recognized Rs.53.9 crores as
own Capital for which the cost of Own Capital @ 14% was to be a
pass through - The effective date for such recognition was from
01.07.2003 to 31.03.2009 and no amounts were due and payable
as interest after that date - This excluded any liability on part of
Gujarat Urja for the past period, i.e. December 1997 - The CLP
Limited was aggrieved by that portion of GERC's order which
rejected its claim on the deemed loan component prior to the period
2003 - The APTEL concurred with the decision of GERC - On
appeal, held: The clear agreement between the parties was that
interest on the sum of Rs.53.90 crores was payable for the specified
period 01.07.2003 to 31.12.2009 - Therefore, CLP's claim that any
amount was payable, for any period prior to 01.07.2003, was not
tenable - Had CLP wished so, nothing prevented it to claim for it
during negotiations and have it included as a term of the contract -
Once having settled for a specified sum, on an amount Rs.53.90
crores that was only fictionally a loan - and treated as such, for
purpose of fixing interest payable, considering the equity infused,
in excess of the tariff regulations, the absence of any like item,
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
A
B
C
D
E
F
G
H
600
SUPREME COURT REPORTS
[2020] 6 S.C.R.
such as interest for prior period, precludes a claim - The findings
of the lower authorities are therefore, sound and reasonable.
Dismissing the appeals, the Court
HELD: 1. The submissions of parties are with respect to
two notifications dated 30.03.1992 and 06.11.1995. These
Notifications were under Section 43(A) of the Supply Act.
Concededly, these notifications are statutory and are binding on
the parties. Any PPA between a generating company and the
purchaser of electricity is subject to such statutory notifications;
parties by agreement cannot override statutory provisions, or
such notifications, as far as they relate to matters of tariff.
Therefore, the rights and obligations of the parties under the
PPA have to be read subject to the statutory provisions. The
provisions of the PPA, if they are contrary to the statutory
provisions, cannot be given effect to. [Paras 19 and 20][611-D-F]
2. In view of the fact that the notification amended on
06.11.1995 was a statutory one, there cannot be any doubt that it
was binding upon the parties. Therefore, the earlier notification
which left it free to the parties to negotiate on various aspects,
including on the incentive payable, stood amended by Note 2,
which was added to clause 1.6 of the tariff. The effect of this
statutory incorporation by way of amendment was that incentive
no longer became payable. The arguments by the CLP, in the
opinion of the Court, that the parties were bound only by the
terms of the agreement and that the amendment notification being
prospective, could not have altered the terms of the tariff,
especially the incentive payable, are insubstantial and have no
force. The concurrent findings on this aspect, therefore, are sound
and do not call for interference. Likewise, the change of law
provision (Clause 6.5 of the PPA) clearly contemplated that any
amendment to the prevailing tariff notification (dated 30.03.1992)
would bind the parties. Since Note (2) was an amendment, which
dealt with the issue of incentive, it cannot now be said that it was
inapplicable. The findings of the lower authorities, therefore, are
correct; no interference is called for. [Para 25][614-D-F;
615-A-B]
A
B
C
D
E
F
G
H
601
3. The next question is whether the GERC and APTEL fell
into error in granting restricted refund calculable for the 3 year
period prior to Gujarat Urja's application. The concurred findings
on this aspect, in the opinion of this court, are reasonable. There
is merit in CPL's submission that the earliest point in time, when
the cause of action arose, was in May,1996, when Gujarat Urja
rejected its contention that incentive was payable in terms of the
PPA, notwithstanding the notification of 06.11.1995. Despite this
stated position, meetings continued to be held and, what is more,
incentive amounts, were paid to CLP. No doubt, no document
conclusively stated that CLP's claim was accepted. This Court
does not find any merit in the submission of Gujarat Urja that the
issue was kept alive, due to a series of communications. In this
regard, APTEL's findings about inapplicability of Section 18 of
the Limitation Act, are correct. There was no admission on the
part of CLP, at least of the kind, that extended the time for
preferring an application for recovery of excess payments. It has
been consistently ruled by this court that repeated letters, or
exchange of communications, do not extend the period of
limitation, provided by law. [Para 26][615-B-E]
4. The third, and last issue, is with respect to payment of
interest on deemed equity. The debt-equity ratio in this case,
was disturbed; accordingly Rs.53.9 crores was treated as
"deemed" or normative loan, for which the parties had to agree
the rate of interest payable, in accordance with the tariff
notification. It was in the light of these developments that the
supplementary agreement was entered into. [Para 28][616-B]
5. It is apparent, that the parties did not harbor any doubt
about the period for which the specified interest was payable on
such deemed loan. The rate of interest was fixed; likewise, the
date from which payment obligations were to arise, too were
known. Also, the date upto which the interest on such deemed
loan payments were to be made, was known and fixed. In these
circumstances, CLP's claim that the payment of interest for a
prior period was outstanding, and constituted Gujarat Urja's
liability, is insubstantial. In a recent judgment a similar issue had
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
A
B
C
D
E
F
G
H
602
SUPREME COURT REPORTS
[2020] 6 S.C.R.
arisen. The court quoted from the decision in National Thermal
Power Corporation Ltd. v. Madhya Pradesh State Electricity Board
where another previous decision was cited with approval on the
issue that the express provision for something, in an agreement,
meant that other similar matters stood excluded. [Para 29]
[616-D-F]
6. In the present case, the clear agreement between the
parties was that interest on the sum of Rs.53.90 crores was
payable for the specified period 01.07.2003 to 31.12.2009.
Therefore, CLP's claim that any amount was payable, for any
period prior to 01.07.2003, was not tenable. Had CLP wished so,
nothing prevented it to claim for it during negotiations and have
it included as a term of the contract. Once having settled for a
specified sum, on an amount (Rs.53.90 crores) that was only
fictionally a loan - and treated as such, for purpose of fixing interest
payable, considering the equity infused, in excess of the tariff
regulations, the absence of any like item, such as interest for
prior period, precludes a claim. But it was really part of the equity
component. Therefore, interest was per se not payable, but could
be paid in terms of the tariff notification or the agreement. No
claim on any other legal or equitable considerations could have
been made. The findings of the lower authorities are therefore,
sound and reasonable. [Para 31][619-E-G]
India Thermal Power Ltd. v. State of M.P. & Ors. (2000)
3 SCC 379 : [2000] 1 SCR 925; Binani Zinc Ltd. v.
Kerala State Electricity Board (2009) 11 SCC 244 :
[2009] 4 SCR 636; Tata Power Company Ltd. v. Adani
Electricity Mumbai Ltd. & Ors. 2019 (7) SCALE 297 :
[2019] 6 SCR 845; Damodar Valley Corporation v.
Central Electricity Regulatory Commission & Ors. 2018
(15) SCALE 451 : [2018] 14 SCR 433 - relied on.
Hari Shankar Singhania v. Gaur Hari Singhania (2006)
4 SCC 658 : [2006] 3 SCR 726; Sri Ram Mills Ltd. v.
Utility Premises Ltd. (2007) 4 SCC 599 : [2007] 4 SCR
279; S.S. Rathore v. State of Madhya Pradesh (1989) 4
SCC 582 : [1989] 1 Suppl. SCR 43; Union of India v.
Har Dayal (2010) 1 SCC 394 : [2009] 15 SCR 1126;
A
B
C
D
E
F
G
H
603
Schlumberger Asia Services Ltd. v. Oil and Natural Gas
Corporation Ltd. (2013) 7 SCC 562; Uttar Haryana
Bijli Vitran Nigam Ltd. And Ors. v. Adani Power Ltd. &
Ors. (2019) 5 SCC 325 : [2019] 4 SCR 487; National
Thermal Power Corporation Ltd. v. Madhya Pradesh
State Electricity Board (2011) 5 SCC 580 : [2011] 11
SCR 651 - referred to.
Case Law Reference
[2006] 3 SCR 726
referred to
Para 16
[2007] 4 SCR 279
referred to
Para 16
[2000] 1 SCR 925
relied on
Para 23
[2009] 4 SCR 636
relied on
Para 23
[2019] 6 SCR 845
relied on
Para 23
[1989] 1 Suppl. SCR 43
referred to
Para 26
[2009] 15 SCR 1126
referred to
Para 26
(2013) 7 SCC 562
referred to
Para 26
[2019] 4 SCR 487
referred to
Para 29
[2011] 11 SCR 651
referred to
Para 29
[2018] 14 SCR 433
relied on
Para 30
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2793
of 2010.
From the Judgment and Order dated 19.01.2010 of the Appellate
Tribunal for Electricity, New Delhi in Appeal No. 44 of 2009.
With
C. A. No. 2969/2010
Sajjan Povaya, C. A. Sundaram, Sr. Advs., V. Mukherjee,
Pukhrambam Ramesh Kumar, Ms. Raveena Dhamija, Karun Sharma,
Akshat Jain, Prati Bhanu, Anand Ganesan, Ms. Hemantika Wahi,
Shubham Arya, Ms. Jesal Wahi, Ms. Puja Singh, Ms. Rohini Musa,
Abhishek Gupta, Zafar Inayat, Ms. Ranjitha Ramachandran, Ms. Puja
Singh, Advs. for the appearing parties.
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
A
B
C
D
E
F
G
H
604
SUPREME COURT REPORTS
[2020] 6 S.C.R.
The Judgment of the Court was delivered by
S. RAVINDRA BHAT, J.
1. The present judgment will dispose of two appeals preferred
under Section 125 of the Electricity Act, 2003. One appeal
(CA 2969/2010) has been preferred by the Gujarat Urja Vikas Nigam
Ltd. (hereafter,"Gujarat Urja"or "GUVN"); the second (CA 2793/2010)
has been preferred by CLP (India) Pvt. Ltd. (formerly, Gujarat Torrent
Energy Corporation Ltd; later, Gujarat Paguthan Energy Corporation
Ltd, a generating company, hereafter collectively "CLP"). Both appeals
challenge a common order of the Appellate Tribunal for
Electricity"APTEL" hereafter).
2. The erstwhile Gujarat Electricity Board (GEB) (now "Gujarat
Urja") entered into a power purchase agreement ("PPA"with CLP on
03.02.1994. In terms of the PPA, Gujarat Urja was under an obligation
to purchase - and CLP was under corresponding obligation to supply -
635 MW of electricity; the tenure of the agreement was 20 years. In
terms of Section 43(A) of the Electricity Supply Act, 1948, (hereafter
"the Act"), a generating company may enter into a contract for the sale
of electricity with the Electricity Board and the tariff for the sale of
electricity shall be determined by the authority through the notification
issued by the Central Government. Prior the PPA in this case, the Central
Government had issued a notification under Section 43A, on 30.03.1992,
specifying the controlling norms, terms and conditions for determination
of tariff for sale of electricity by the generating company to the Electricity
Boards. One of those conditions was the provision for incentive to units
using naphtha. On 17.01.1994, an amendment to the notification dated
30.03.1992 was made providing for Note (1) stating that the incentive
for generation above the target availability of 68.49% for fixed cost
recovery was to be capped.
3. After the signing of the PPA between the parties, an amendment
notification dated 06.11.1995 was issued by the Central Government
amending the notification (dated 30.03.1992). By this, the Central
Government provided that there would no longer be any deemed
Generation Incentive payable to any generating company on available
declaration of Naphtha as fuel. Based on this notification, the Electricity
Board sought to enforce the said notification claiming that this generating
company is not entitled to get the incentive for deemed generation. The
Electricity Board also sent a letter dated 18.04.1996 informing the CLP,
A
B
C
D
E
F
G
H
605
that it proposed to amend the Clause 7.5.2.1 of the PPA to the effect
that no deemed generation shall be admissible beyond the level of
generation in respect of Naphtha. CLP did not agree to the proposal and
by its reply dated 24.04.1996 stated that the notification of 06.11.1995
was inapplicable. Gujarat Urja did not agree to CLP's position and
reiterated its earlier position about the change in the incentive terms. A
meeting was held in respect of various issues on 06.10.1997 during which
several issues were discussed and decisions taken, between the parties.
However, the minutes of meeting did not record any decision on the
issue of incentive restricted in terms of the notification dated 06.11.1995.
There was some more correspondence and meetings, which however,
did not lead to any result in regard to both parties accepting that the
incentive was payable in terms of the notification of November,1995.
Ultimately, with effect from December 1997, CLP started billing Gujarat
Urja for the power supplied, including the incentive (ignoring the amending
notification); Gujarat Urja continued to pay deemed generation incentive
from June, 1998 to 2000.
4. The Union Ministry of Power issued a notification (dated
09.06.1998) which clarified profits on operating norms; several
components such as station heat rate, auxiliary consumption and
secondary fuel consumption were eliminated and income tax on incentives
was no longer permitted (as a pass through in tariff). It was stated that
this was prospective in operation and would apply to power purchase
agreements which were not executed and delivered by the parties by
09.06.1998. For a long time, incentive continued to be paid, ignoring the
notification of 06.11.1995 by Gujarat Urja, to CLP. On 05.12.2003, CLP
and Gujarat Urja entered into a supplementary agreement, amending
the PPA, to incorporate concessions offered by CLP to reduce tariff.
Pursuant to execution of the supplementary agreement dated 05.12.2003,
Gujarat Urja issued a letter to CLP stating that all the outstanding issues
stood fully and finally resolved. Gujarat Urja continued to pay deemed
generation incentive from 05.12.2003 to 23.02.2005. In February, 2005,
a high-level committee was constituted to examine the issue of recovery
of excess payouts made on the basis of deemed generation incentive.
The receipt of the report, of that committee, led Gujarat Urja to file an
application for recovery of the amounts from CLP (Petition No.874/
2006 under Section 86(1)(f) of the Act, before the Gujarat Electricity
Regulatory Commission ("GERC"), claiming for recovery of deemed
generation incentive paid to CLP during the period from 1997-98 to 200506.
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
[S. RAVINDRA BHAT, J.]
A
B
C
D
E
F
G
H
606
SUPREME COURT REPORTS
[2020] 6 S.C.R.
5. CLP resisted Gujarat Urja's application, contending that
principles of estoppel precluded recovery; that in any event, parties had
not agreed to change the terms of the PPA and that the previous
correspondence evidenced that the matter had been closed, which meant
that Gujarat Urja could not claim recovery of any so-called excess
amounts. The GERC, by its order held that Note 2 (introduced by the
notification of 06.11.1995) was applicable to the project and thus deemed
generation incentive is not payable to CLP. However, it permitted recovery
of only for a period of three years prior to the date of filing of the petition:
the recovery for the period prior to 14.09.2002 were held to be timebarred.
6. The second appeal, i.e. CA 2793/2010 by CLP Limited, questions
the impugned order of the APTEL which had upheld the rejection of its
claim for interest on deemed loan component.
7. The facts as far as this appeal is concerned are that a
supplementary agreement was executed between the parties on
05.12.2003. In terms of Article 4.6 of the Supplementary Agreement,
original clause 7.5.14(a) of the PPA dated 03.02.1994 was substituted1 .
CLP stated that the amount, i.e ` 53.90 crores was in fact due as a loan.
If it was deemed as a loan, then interest was payable on the basis of
normative repayment of principal amount during the period of the loan,
i.e. the loan would not remain as a constant. In this regard, CLP had
relied upon Clause 1.5 of the notification dated 30.03.19922. The PPA
dated 03.02.1994 by Schedule VII Clause 7.5.10 defined "Interest on
Loan Capital" in the following terms:
7.5.10: Interest on Loan Capital-shall mean the sum of all
payment of interest along with bank charges and all
associated financing costs paid to the bank annually on the
outstanding loans paid by GTEC, converted, as of the first
day of the fortnight for the applicable fixed charge, into the
1 The substituted term, i.e. the new clause 7.5.14(a) reads as follows:
 "The parties have agreed to recognize an amount of Rs.53.90 crores as"Own
Capital"deployed to meet with the Capital Cost and allowance of Payment of cost in the
form of "Cost of Own Capital"@ the rate of 14% per annum effective from 1.7.2003 and
up to 31.12.2009. No payment of any nature will accrue after the said date on the said
amount."
2 Clause 1.5 reads as follows:
 "1.5................(a) Interest on loan capital shall be computed on the outstanding loans,
including the schedule of repayment, as per the financial package approved by the
Authority....."
A
B
C
D
E
F
G
H
607
currencies in which it is payable employing exchange rates
at bank's selling rate prevailing on that day obtained from
the source mutually agreed."
8. The CERC Tariff Regulations, 2001 which provided for
"Interest on loan capital"[clause 2.7(a)] and CERC Tariff
Regulations, 2004 were relied upon.
They are set out below:
''2.7(a)Interest on loan capital
Interest on loan capital shall be computed on the outstanding
loans, duly taking into account the schedule of repayment as
per the financial package approved by the Authority or an
appropriate independent agency, as the case may be."
9. CERC Tariff Regulations, 2004 inter alia provides as under:
"20.Debt-Equity Ratio:(1) In case of alia generating
stations, declared under commercial operation on or after
1.4.2004,debt-equity ratio as on the date of commercial
operation shall be 70:30 for determination of tariff. Where
equity employed is more than 30%,the amount of equity
for determination of tariff shall be limited to 30% and the
balance amount shall be considered as the normative loan.
Provided that in case of a generating station where actual
equity employed is less than 30%, the actual debt and equity
shall be considered for determination of tariff.
(2) The debt and equity amount arrived at in accordance
with clause (1) shall be used for calculating interest on
loan, return on equity, Advance against Depreciation and
Foreign Exchange Rate Variation."
10. Gujarat Urja resisted this claim. After adjudication, the GERC
rejected the CLP's argument on a plain reading of the clause, saying
that for the first time in the supplementary agreement, which stated that
the agreement too recognized ` 53.9 crores as own Capital for which
the cost of Own Capital @ 14% was to be a pass through. The effective
date for such recognition was from 01.07.2003 to 31.03.2009 and no
amounts were due and payable as interest after that date. It was
specifically stated that this condition constituted the complete bargain to
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
[S. RAVINDRA BHAT, J.]
A
B
C
D
E
F
G
H
608
SUPREME COURT REPORTS
[2020] 6 S.C.R.
the extent it provided for treatment of cost of Own Capital @ 14% per
annum for a defined period. The agreement had to be and was given
prospective operation. This excluded any liability on part of Gujarat Urja
for the past period, i.e. December 1997. It was also held that the claim
made in 2010 was substantially barred to the extent it sought for any
amount of interest beyond a period of three years.
11. The CLP claimed on another issue, i.e. interest on ` 14.48
crores @ 16% per annum from July 2000 to 30.06.2003 was payable. In
terms of the supplementary agreement, the condition specifically stated
that GPEC (i.e. CLC) had further deployed a sum of ` 14,48,40,831/-
from its internal accrual to complete shortfall and disbursal of loan by
the lenders, which agreed to allow payment on this amount @ 16% per
annum from July 2000 to 30.06.2012. Gujarat Urja stated that this interest
was payable on reducing balance terms, not as bullet payment of interest.
12. The CERC ruled that it was quite clear that the parties had
agreed to allow interest at the said rate, @ 16% on the said sum, i.e.
14.48 crores. Therefore, Gujarat Urja could not argue that interest was
payable on the reducing balance method and that the payment of interest
on a bullet repayment method was not permissible. The Commission,
i.e. GERC noted that the statutory notification, i.e. clause 1.5 of the
notification dated 30.03.1992 did not prohibit calculation of interest on
bullet repayment as regards clause 7.5.10 in Schedule VII of the PPA
dated 03.02.1994, the subject matter or its content was deemed loan.
On this second aspect, therefore, the terms of the contract contained in
the supplementary agreement directing 16% per annum interest on `14.48
crores is bullet repayment, was upheld.
13. The CLP Limited was aggrieved by that portion of GERC's
order which rejected its claim on the deemed loan component prior to
the period 2003. It appealed to the APTEL (Appeal No.44/2009). The
APTEL concurred with the decision of the GERC and held that clause
7.5.14(a) of the supplementary agreement did not oblige Gujarat Urja to
refund interest paid upon the deemed loan component upon the equity
portion treated as deemed loan, i.e. ' 53.9 crores for any period prior to
01.07.2003. Therefore, CLP's appeal was rejected. It, therefore, has
appealed to this Court on the said findings.
Analysis and Findings
14. Section 43A of the Electricity (Supply) Act, 1948 (hereafter
"the Supply Act") reads as follows:
A
B
C
D
E
F
G
H
609
"43A. Terms, conditions and tariff for sale of electricity by
Generating Company.-
(1) A Generating Company may enter into a contract for the
sale of electricity generated by ita) with the Board constituted for the State or any of the States
in which a generating station owned or operated by the
company is located;
b) with the Board constituted for any other State in which it is
carrying on its activities in pursuance of sub-section(3) of
section 15A; and
(c) with any other person with consent of the competent
government or governments.
(2) The tariff for the sale of electricity by a Generating
Company to the Board shall be determined in accordance with
the norms regarding operation and the Plant Load Factor as
may be laid down by the Authority and in accordance with
the rates of depreciation and reasonable return and such other
factors as may be determined, from time to time, by the Central
Government, by notification in the Official Gazette:
 Provided that the terms, conditions and tariff for such sale
shall, in respect of a Generating Company, wholly or partly
owned by the Central Government, be such as may be
determined by the Central Government and in respect of a
Generating Company wholly or partly owned by one or more
State Governments be such as may be determined, from time
to time, by the government or governments concerned."
15. At the outset, it is noticeable that on the issue, whether amounts
paid to CLP, for the period 1998 to 2005 onwards, were in excess of
what was actually payable by Gujarat Urja, the findings of GERC and
the APTEL are concurrent. This court does not discern any
unreasonableness or facial omission of material factors, to warrant
appellate review. Nevertheless, the court would proceed to deal with
the submissions made on this aspect. Gujarat Urja contends that the
concurrent findings, to the extent they limit the refund to a period up-to
2002 are erroneous, because in effect CLP has been unjustly enriched.
Learned senior counsel for Gujarat Urja, Mr. C.A. Sundaram, argued
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
[S. RAVINDRA BHAT, J.]
A
B
C
D
E
F
G
H
610
SUPREME COURT REPORTS
[2020] 6 S.C.R.
that once the GERC found, on a plain reading and interpretation of the
tariff order of 1992 - as amended by the notification dated 06.11.1995,
that incentive could not be paid in the same manner as was contemplated
by the parties, when they entered into the PPA (on 03.02.1994), as a
matter of law, the amounts paid were excess; consequently, both in law
as well as in equity, CLP was under an obligation to refund the entire
excess, from the time it was not entitled to those amounts.
16. On the question of limitation, learned senior counsel argued
that the APTEL erred in law, in not following the decisions of this court
in Hari Shankar Singhania v. Gaur Hari Singhania3 and Sri Ram
Mills Ltd.v. Utility Premises Ltd.4 in considering that the issue was not
time-barred. Counsel submitted that the question was engaging the
attention of the parties and CLP was aware of the fact that the Central
Electricity Authority and the Central Government had taken decisions
on this aspect. Moreover, as a matter of law, by reason of the amendment,
to the notification (dated 06.11.1995), CLP could not have legitimately
claimed more tariff based on the incentive policy that was no longer
applicable. Therefore, the amounts paid to the extent they were not in
conformity with the said amendment, had to be refunded in entirety.
17. On behalf of CLP it was urged, by Mr. Sajan Poovayya, learned
senior counsel, that both the authorities below erred in their interpretation
of the terms of the PPA, the notification of 30.03.1992 and the amendment
of 06.11.1995. It was argued that CLP's generation station is gas-based
and not a Naphtha based station. The notification dated 06.11.1995 applied
only to 100% Naphtha based stations and not to gas based stations like
that of CLP, where Naphtha was used as a secondary fuel when the
Gas was not available. The expression "Naphtha based station" used in
the notification is a term of art; it refers merely to the physical
characteristic of the plant and not to the nature of fuel to be used. It was
further contended that the amending notification of 06.11.1995 itself
makes a distinction between gas based stations and naphtha based
stations. CLP's plant, in terms of PPA is a gas based, not Naphtha based.
Therefore, the notification dated 06.11.1995 would not apply to its plant.
Also, urged counsel, since the PPA was entered into on 03.02.1994, the
amendment notification dated 06.11.1995 would not apply to the preexisting PPA, since it has a prospective effect. It was lastly submitted
3 (2006) 4 SCC 658
4 (2007) 4 SCC 599
A
B
C
D
E
F
G
H
611
that Clause 6.5 of the PPA dated 03.02.1994 regarding change of law is
clarificatory in nature. It deals only with the earlier part to protect the
interest of the GPEC for change in law. "The change in law" referred to
in Clause 6.5 covers amendment to notification dated 30.03.1992.
Therefore, the financial difficulties resulting from the amendment
notification dated 06.11.1995 are to be compensated in favour of the
CLP.
18. It was argued that Note(2) of the amended notification dated
06.11.1995 unambiguously states that it applies only to Naphtha based
stations for whom generation incentive was inapplicable. Therefore, the
gas based units like CLP were clearly not covered by Note(2) since
they used naphtha only as an alternative fuel or substitute fuel. Therefore,
the findings given by the GERC and APTEL to the effect that Naphtha
based station include those that are capable of firing Naphtha also as a
fuel, and not mean those which are capable of firing only Naphtha, is
wrong.
19. The submissions of parties are with respect to two notifications
dated 30.03.1992 and 06.11.1995. These Notifications were under Section
43(A) of the Supply Act. Concededly, these notifications are statutory
and are binding on the parties. Any PPA between a generating company
and the purchaser of electricity is subject to such statutory notifications;
parties by agreement cannot override statutory provisions, or such
notifications, as far as they relate to matters of tariff.
20. Therefore, the rights and obligations of the parties under the
PPA have to be read subject to the statutory provisions. The provisions
of the PPA, if they are contrary to the statutory provisions, cannot be
given effect to. In terms of the PPA of 03.02.1994, "fuel" is defined as
follows:
"Fuel natural gas and/or any liquid fuel selected by Gujarat
Torrant Electricity Company (GTEC) (now CLP) for use in
power station for generating electricity"
'fuel management' is defined as follows:
"Fuel Management:-The power station of the GTEC is
designed to use natural gas and liquid fuel as fuel. GTEC
shall decide selection and use and proportion gas and other
fuel in best economic way depending on the situation from
time to time."
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
[S. RAVINDRA BHAT, J.]
A
B
C
D
E
F
G
H
612
SUPREME COURT REPORTS
[2020] 6 S.C.R.
21. The kind of alternative fuel and its long-term purchase contract
could be jointly decided by CLP and Gujarat Urja. The cost of the alternate
fuel when used by CLP shall be taken into account for calculation of
variable charges as defined in Schedule VII (of the PPA). Clause 7.1
and Clause 7.4 of Schedule VII to the PPA are relevant.5 Under the
former, Gujarat Urja had to purchase power from CLP on the basis of the
notification of 30.03.1992 of the Central Government. It further provided that
the tariff for the first 6000 Kwh/kw (i.e 68.5% PLF - i.e. plant load factor) of net
availability in any year was to be the sum of (a) the fixed charge and (b) the
variable charge (i.e those terms defined by clauses 7.2 and 7.3). For all excess
energy of actual and deemed generation in excess of 68.5%, the tariff payable
was to be the sum of (a) incentive and (b) variable charge. Clause 7.4 provided
for incentive, which was to be @ 0.575% for every 1% increase in the generation
above the normative level of 6000 hours per kWH/KW (i.e 68.5% PLF) in
accordance with the notification S.O. 251(E), dated 30.03.1992 (as amended on
17.01.1994).
22. The argument of CLP that its unit was essentially gas-based
and that the definition of naphtha-based unit meant only that unit which
depended entirely on naphtha as a fuel, or that which used naphtha at
least to the extent of 50%, in our opinion is not correct.
23. The judgment of this court in India Thermal Power Ltd. vs.
State of M.P. & Ors.6 is an authority for the proposition that parties can
5 For convenience,they are set out as follows:
"7.1 Tariff
GEB shall purchase power from GTEC, generally on the basis of GOI notification
No.SO 251(E) dtd. 30-3-1992. The Tariff for the first 6,000 kWH/KW (i.e. 68.5 PLF) of
Net Availability in any year during the terms of this Agreement shall be the sum of (a)the
Fixed Charge and (b) the Variable Charge. For all the energy of actual and deemed
generation in excess of 68.4 % PLF in any Year ,the Tariff payable by GEB shall be the
sum of (a) the Incentive described below and (b) the Variable Charge. Any tax or impost
on or pertaining to sale of energy or capacity shall be payable by GEB over and above
the Tariff.
...
......
......
......
7.4 Incentive The incentive referred to in 7.1 above with respect to any fortnight
shall be in the form of additional return on equity at the rate of 0.575% for every 1%
increase in the generation above the normative level of 6000 hours per kWH/KW(i.e
68.5% PLF) in accordance with the amendment dated 17.1.94 to the said notification
No.SO 251(E)."
6 (2000) 3 SCC 379, where it was held pertinently that:
"Section 43 empowers Electricity Board to enter into arrangement for purchase
of electricity on such terms as may be agreed. Section 43-A(1) provides that a generating
company may enter into a contract for the sale of electricity generated by it with Electricity
A
B
C
D
E
F
G
H
613
agree to terms as they deem appropriate, for generation and sale of
electricity under Section 43A except that the tariff is to be in accordance
with the provision contained in Section 43A. The decision in Binani
Zinc Ltd. v. Kerala State Electricity Board7; Tata Power Company
Ltd. vs. Adani Electricity Mumbai Ltd. and Ors.8 too have taken a
similar approach.
24. Clause 6.5 of the PPA of 03.02.1994 dealt with a situation
concerning change of law. It also stated that any amendment in the
Central Government's notification dated 30.03.1992 would be taken into
account for tariff calculation.9 The relevant part of the notification of
Board. As regards the determination of tariff for the sale of electricity by a generating
company to the Board, Section 43(1)(2) provides that the tariff shall be determined in
accordance with the norms regarding operation and plant load factor as may be laid
down by the authority and in accordance with the rates of depreciation and reasonable
return and such other factors as may be determined from time to time by the Central
Government by a notification in the official gazette. These provision clearly indicate that
the agreement can be on such terms as may be agreed by the parties except that the tariff
is to be determined in accordance with the provision contained in Section 43-A(2)and
notifications issued thereunder. Merely because a contract is entered into in exercise of
an enacting power conferred by a statute that by itself cannot render the contract a
statutory contract. If entering into a contract containing prescribed terms and conditions
is a must under the statute than that contract becomes a statutory contract. If a contract
incorporate certain terms and conditions in it which are statutory then the said contract
to that extent is statutory. A contract may contain certain other terms and conditions
which may not be of a statutory character and which have been incorporated therein as
a result of a mutual agreement between the parties. Therefore, the PPAs can be regarded
as statutory only to the extent that they contain provisions regarding determination of
tariff and other statutory requirements of Section 43A(2)."
7 (2009) 11 SCC 244
8 2019(7) SCALE 297
9 The stipulation reads as follows:
"6.5 Change in Law: In the event that as a result of any laws or regulations
of any Governmental Authority or any national ,regional or municipal authority thereof
coming into effect after the date hereof, and in force at the date hereof being amended,
modified or repealed, the interest of GTEC in the Project and/or GTEC's projected
economic return net of tax (or other imposition) on its investment in the Project is
materially reduced prejudiced or otherwise adversely affected (including without
limitation, any restriction on the ability to convert Rupees or remit funds in foreign
currencies outside of India) then the parties hereto shall meet and endeavour to agree
on amendments to this Agreement to the effect that all of the increased cost or lost return
on investment incurred by GTEC that would result from complying with or being
subject to any such change in law shall be passed through to GEB under GTEC Tariff.
Any amendment in Government of India Notification No.S.O.251(E)dated 30.3.92 shall
be taken into account for Tariff calculation."
CLP INDIA PVT LTD v. GUJARAT URJA VIKAS NIGAM LTD.
[S. RAVINDRA BHAT, J.]
A
B
C
D
E
F
G
H
614
SUPREME COURT REPORTS
[2020] 6 S.C.R.
30.03.1992 which dealt with charges recoverable by the generating
company was clause 1.6.10 That condition was amended by the notification
dated 06.11.1995 which clearly stated, by Note(2) that:
"Note:2-For Naptha based thermal plants, the extent of
backing down, as ordered by Regional Electricity Boards,
beyond plant Load Factor of 6000 kwh/kw/year, shall not be
reckoned as generation achieved for incentive purpose."
25. There is no dispute that the PPA which the parties entered
into specifically referred to the notification of 30.03.1992 and further
went on to state that for the first Kwh/KW, a plant load factor of 68.5%
fixed charges and variable charges were deployed. For generation
achieved over and above this by the concerned unit - CLP, an incentive
@ 5.75% for every 1% increase over and above the fixed and variable
charge payable was agreed to. Significantly, the fixed and variable charges
are in consonance with the statutory notification of 30.03.1992 (which
was also later amended on 17.01.1994).