# GANGA RETREAT AND TOWERS LTD. AND ANR v. STATE OF RAJASTHAN AND ORS

- **Citation:** [2003] Supp. 6 S.C.R. 1134
- **Court:** Supreme Court of India
- **Decided:** 2003-12-19
- **Bench:** R.C. Lahoti, Ashok Bhan
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/ganga-retreat-and-towers-ltd-and-anr-v-state-of-rajasthan-and-ors-19522
- **Pages:** 38

## Headnote

Urban Land Ceiling and Regulation Act, 1976-Sections 6(1) read
with section 15 and sections 20 and 38-Contract Act, 1872-Sections 18,
19, 21, 22 and 56-Public auction-Property described as ji-ee hold,
C ceiling free and vacant with Floor Area Ratio (FAR) as 2.00-Company
declared successful bidder, however payment delayed as per schedulePayment along with interest on delayed payment and also registration
charges and stamp duty paid-Execution of sale deed and possession
delivered to Company-Application for sanction of building plans for
construction-Meanwhile, FAR reduced to 1. 75 owing to change- in
D Bye laws-Building plans approved with FAR 1. 75-State issued notice to
Company for holding land in excess of ceiling limits-Grant of exemption
subject to condition that property would not be alienated without prior
permission of the Government-Company fully knowing that FAR approved as 1. 75 and property not ceiling free commencing construction
E activities and also re-submitting plans for approval of FAR as 2. 00-Writ
Petition seeking declaratory reliefs that there was frustration or impossibility of performance of contract; and that FAR 1. 75 not applicable-Also
claimed refund of registration charges, stamp duty and cost of construction
incurred with interest--On appeal Held: Company having known about the
F reduction of FAR from 2. 00 to 1. 7 5 and that the land was not ceiling free
affirmed the contract by getting their plans approved with FAR 1. 75 and
started construction activities as such they cannot annul and avoid a
concluded contract and flX liability on the Government-There was no
frustration or impossibility of performance of contract-When the ComG pany applied for approval of building plans, law in force at that time would
apply--Doctrine of promissory estoppel is not available when any action
is desired to be taken in contravention of the provisions of law-Jaipur
Development Authority Act, 1982-Section 90-Rajasthan Municipalities
Act, 1954-Section 298-Administrative Law.
H
Constitution of India, 1950-Articles 226 and 136-Petition
1134
GANGA RETREAT AND TOWERS LTD. v. STATE
1135
"· involving disputed questions of fact in relation to completed contract of A
sale of land-Maintainability of-Held: Such petitions cannot be adequately
adjudicated upon in exercise of writ jurisdiction-Filing of suit would be
efficacious remedy-However, Supreme Court decided the dispute on
merits on account of lapse of time.
Respondent-State carried out public auction of a property describing it as free-hold, ceiling free, vacant property with Floor Area
Ratio (FAR) as 2.00 provided by 1989 Bye-laws. Appellant-Company
was declared successful bidder. Appellants delayed the payment as per
B
the schedule and later made the payment along with interest for
delayed payment and also paid registration charges and stamp duty. C
Thereafter, sale deed was executed and it was repeated that FAR would
be 2.00. Appellants were then delivered possession. Thereafter, appellants applied for sanction of plans for constructing the property as per
FAR 2.00 and deposited under protest the map approval charges
demanded. Meanwhile, Municipal Corporation revised its bye~laws D
and by 1996 Regulation FAR was reduced to 1.75. Municipal Corporation approved the plans as per FAR 1.75 and immediately appellants
commenced construction activities with the belief that the remaining
FAR would be approved. Competent Authority issued· notice to the
appellants under section 38 of Urban Land Ceiling and Regulation Act, E
1976 alleging that the appellants were holding land in excess of the
ceiling limits and had not filed the return. Appellants submitted that
as the property had been sold ceiling free there was no need tt; file
return and as such applied for exemption. Appellant was granted
exemption from ceiling subject to the conditions that para-meters of F
Municipal Corporation regarding construction would be applicable
and that the property would not be alienated without pr

## Text

_Characters 0–39,988 of 90,717. This is a partial read: ask again with offset=39988 for what follows._

A
GANGA RETREAT AND TOWERS LTD. AND ANR.
B
v.
STATE OF RAJASTHAN AND ORS.
DECEMBER 19, 2003
[R.C. LAHOTI AND ASHOK BHAN, JJ.]
Urban Land Ceiling and Regulation Act, 1976-Sections 6(1) read
with section 15 and sections 20 and 38-Contract Act, 1872-Sections 18,
19, 21, 22 and 56-Public auction-Property described as ji-ee hold,
C ceiling free and vacant with Floor Area Ratio (FAR) as 2.00-Company
declared successful bidder, however payment delayed as per schedulePayment along with interest on delayed payment and also registration
charges and stamp duty paid-Execution of sale deed and possession
delivered to Company-Application for sanction of building plans for
construction-Meanwhile, FAR reduced to 1. 75 owing to change- in
D Bye laws-Building plans approved with FAR 1. 75-State issued notice to
Company for holding land in excess of ceiling limits-Grant of exemption
subject to condition that property would not be alienated without prior
permission of the Government-Company fully knowing that FAR approved as 1. 75 and property not ceiling free commencing construction
E activities and also re-submitting plans for approval of FAR as 2. 00-Writ
Petition seeking declaratory reliefs that there was frustration or impossibility of performance of contract; and that FAR 1. 75 not applicable-Also
claimed refund of registration charges, stamp duty and cost of construction
incurred with interest--On appeal Held: Company having known about the
F reduction of FAR from 2. 00 to 1. 7 5 and that the land was not ceiling free
affirmed the contract by getting their plans approved with FAR 1. 75 and
started construction activities as such they cannot annul and avoid a
concluded contract and flX liability on the Government-There was no
frustration or impossibility of performance of contract-When the ComG pany applied for approval of building plans, law in force at that time would
apply--Doctrine of promissory estoppel is not available when any action
is desired to be taken in contravention of the provisions of law-Jaipur
Development Authority Act, 1982-Section 90-Rajasthan Municipalities
Act, 1954-Section 298-Administrative Law.
H
Constitution of India, 1950-Articles 226 and 136-Petition
1134
GANGA RETREAT AND TOWERS LTD. v. STATE
1135
"· involving disputed questions of fact in relation to completed contract of A
sale of land-Maintainability of-Held: Such petitions cannot be adequately
adjudicated upon in exercise of writ jurisdiction-Filing of suit would be
efficacious remedy-However, Supreme Court decided the dispute on
merits on account of lapse of time.
Respondent-State carried out public auction of a property describing it as free-hold, ceiling free, vacant property with Floor Area
Ratio (FAR) as 2.00 provided by 1989 Bye-laws. Appellant-Company
was declared successful bidder. Appellants delayed the payment as per
B
the schedule and later made the payment along with interest for
delayed payment and also paid registration charges and stamp duty. C
Thereafter, sale deed was executed and it was repeated that FAR would
be 2.00. Appellants were then delivered possession. Thereafter, appellants applied for sanction of plans for constructing the property as per
FAR 2.00 and deposited under protest the map approval charges
demanded. Meanwhile, Municipal Corporation revised its bye~laws D
and by 1996 Regulation FAR was reduced to 1.75. Municipal Corporation approved the plans as per FAR 1.75 and immediately appellants
commenced construction activities with the belief that the remaining
FAR would be approved. Competent Authority issued· notice to the
appellants under section 38 of Urban Land Ceiling and Regulation Act, E
1976 alleging that the appellants were holding land in excess of the
ceiling limits and had not filed the return. Appellants submitted that
as the property had been sold ceiling free there was no need tt; file
return and as such applied for exemption. Appellant was granted
exemption from ceiling subject to the conditions that para-meters of F
Municipal Corporation regarding construction would be applicable
and that the property would not be alienated without prior permission
of the State Government. Appellants re-submitted the plans for
approval of FAR as 2.00 or to refund the proportionate amount
consequent upon the reduction in FAR.
Aggrieved appellants then filed writ petition seeking reliefs that
declaration be passed to the effect that the contract of sale of property
has become impossible <'f performance as the FAR 2.00 as mentioned
G
in the sale-deed is reduced to FAR 1.75; that the Regulations of 1996
were not applicable; and that the stamp duty and registration charges H
1136
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
A be refunded. Respondents raised .preliminary objections that the
declaratory reliefs claimed could not be granted in the writ jurisdiction. Single Judge rejected the preliminary objections and held that the
auction sale and sale deed were null and void and the contract was
frustrated and as such all consequent actions taken by either of the
B parties were invalidated and appellants were entitled to be restituted
to the original position as it existed prior to the auction and execution
of sale deed and respondents were directed to refund all the payments
received by appellants. Division Bench held that it was a completed
contract involving highly disputed questions of fact which could not be
C adjudicated upon by High Court in exercise of its writ jurisdiction and
set aside the order of Single Judge leaving it open to the appellants to
seek their remedy in the Civil Court. Hence the present appeals.
Appellants contended that there is no absolute bar to the
maintainability of the writ petition under Article 226 in contractual
D matters; that the appellants purchased the property on. a representa-.
tion made by the respondents that the FAR was 2.00 and that the
property was free hold and ceiling free; that the appellants were
,persuaded to make high bid on this representation that the land was
, ceiling free amounted to misrepresentation under section 18 of the
E Contract Act and the contract became voidable at the option of the
a°'ppellants under Section 19; that the contract was frustrated and
incapable of being performed in terms of Section 56; that the appellants have invested huge sums of money after borrowing from the Bank
at high rates of interest without any return for the last so many years;
that in the conveyance deed FAR was again mentioned as 2;0 and at
F the stage there was clear misrepresentation; that the right to avoid
contract or rescind the contract can be waived but there is no principle
of law which requires the exercise of the right of repudiation of the
contract to be done immediately on coming to know about the
misrepresentation or breach of contract; that it was open to the
G aggrieved party to persuade the defaulting party to rectify the situation
and to wait till the defaulting party refuses to rectify its default before
exercising its right of repudiation of the contract; that a contract or
other transaction foduced or tainted by fraud is not void, but only
voidable at the opinion of the parties defrauded, unless it is avoided,
H the transaction is valid; that because of the very strict condition
GANGA RETREAT AND TOWERS LTD. v. STATE
1137
contained in the terms of auction, appellants inspite of having knocked A
the doors of the court had to start with the construction otherwise they
ran the risk of their right to the property being forfeited; that the
condition imposed by the exemption order that the plot would not be
transferred without prior approval of the State Government were
contrary to the representation contained in the auction notice that the B
properfy was freehold; that the appellants could avoid the transaction
at any time; that the State Government has the complete control over
the Development Authority and could direct it to adhere to FAR 2.0
as against FAR 1.75 provided under the 1996 Regulations; and that
Government had the power to cancel or modify the Bye-laws framed
by the Board and failure to do SO· reflects that the Government did not
intend to stick to the representation made by it in the auction notice
or sale deed.
c
Respondents contended that contractual disputes can be raised in
proceedings under Article 226 is misconceived; that the points involved D
in the writ petition are highly disputed questions of fact which cannot
be decided without taking evidence and therefore, the order of the
Division Bench was right; that the date on which auction went in
favour of appellants there was no misrepresentation since the FAR on
that date was 2.0; that the FAR was changed by virtue of change in E
\aw, which could not have been envisaged at the time the contract was
entered into; that the contract was frustrated and incapable of being
performed is misconceived as Section 56 does not apply to the ;ases
of completed transfer; that the delay in the execution of the conveyance
deed was pre-dominantly on account of causes attributable to the
appellants; that the appellants executed and accepted the conveyance F
even after the reduction of the FAR voluntarily and having raised
construction clearly declared their intention to proceed with the
contract; that having declared their intention to proceed with the
contract the appellanl:s were bound by their affirmation; that the
appellants having failed to rescind the contract immediately on coming G
to know of the breach or misrepresentation by the Government, it
could not exercise their right of rescinding the contract or avoiding it;
that the stand of the State has always been that it is not going to enforce
any of the conditions stated in the exemption order and as on today
also the staPd is the same which is admitted by appellants.
H
1138
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
A
Dismissing the appeals, the Court
HELD : 1.1. The petition involving disputed questions of fact in
relation to a completed contract of sale of land cannot be adequately
adjudicated upon in exercise of writ jurisdiction, but, despite holding
.the same in the exercise ofpowe~ under Article 136 of the Constitution,
B appeal cannot be dismissed on this account at this stage because that
is likely to result in the miscarriage of justice on account of lapse of
time which may now result in the foreclosure of all other remedies
which could be availed of by the appellants in the ordinary course. At
the present stage the alternative remedy of filing the suit would not be
C efficacious. Keeping in view the peculiar facts and the fact that it will
not be a sound exercise of judicial discretion to relegate the petitioners
to take recourse to the remedy of civil suit belatedly at the present
stage, the dispute is examined on merits. (1152-E-G; 1153-E-F)
D
Kera/a State Electricity Board & Anr. v. Kurien E. Kalathil & Ors.,
[2000] 6 sec 293, referred to.
2.1. Every contract including one by auction is subject to provisions of law. Whenever any action is taken in performance. of a
contract, it must conform to the law in force at the tlme when action
E is taken. In the instant case, when the appellants applied for approval
of building plans it is the law in force at that time which would be
applicable. Doctrine of promissory estoppel is not available when any
action is desired to be taken in contravention of the provisions of law.
The terms and conditions of the sale as announced were in accordance
F with law and no guarantee was given nor could have been given ·that
the law would not change, or that the terms and conditions would be
enforceable even in violation of law which may be in force. FAR was
a matter of law and was fixed either by the Development Authority or
the Municipal Corporation in exercise of its statutory powers. When
the contract was entered into, FAR approved was 2.00 and its
G subsequent reduction in 1996 to 1.75 would not invalidate contract or
be treated as a breach of the contract. (1164-C-E]
2.2. Appellants are not entitled to any relief in the realm of the
law of contracts. In spite of having acquired knowledge of the true facts
H assuming that there was any mistake or misrepresentation to begin
GANGA RETREAT AND TOWERS LTD. v. ST A TE
1139
with and having learnt that the title which was sought to be conferred A
on them by the respondents was not such full title as they had
contemplated it to be, they proceeded to have the sale deed executed
and registered in their favour, seeking extensions of time and paying
interest for the period of delay in payment. The contract stood
accomplished into a demise and the transaction ended. It is writ l~rge B
that the appellants had elected to stand by the contract by digging the
land, sinking the basement and raising about 9 floors above, investing
crores of rupees. They have by their own conduct rendered the position
irreversible and restitution impractical. No authority or law is shown
based whereon the appellants may annul and avoid a concluded
contract and fix liability on respondents for the cost of their construe- C
tion which may have voluntarily chosen to raise in spite of being aware
of all the relevant facts and circumstances. As such frustration of
contract or impossibility of performance of the contract is not made
out. (1169-B-D]
2.3. As per the terms and condition of the auction notice failure
D
to deposit the amount as stipulated could result in forfeiture of the
amount already deposited by the successful bidder and result in
cancellation of the bid. Appellants did not deposit the amount as per
the schedule of payment. The delay in the execution of the conveyance E
was principally attributable to the appellants. Had the appellants made
the payments as per schedule of the payment given in the auction notice
and submitted the requisite stamp duty the conveyance deed would
have been executed prior to the amendment in law. Further, the
appellants despite having the knowledge of the reduction of FAR F
requested the respondent to execute the conveyance deed as such the
plea of misrepresentation or mistake on account of change of FAR is
not made out on the admitted facts. (1156·:-A-B; 1156-D-G]
· 2.4. The appellant's pleadings of misrepresentation and mistake in
the alternative, in the facts and circumstances of the case are mutually G
destructive. Under section 21 a contract is not voidable because it was
caused by a mistake as to any law in force in India. Appellants cannot
rely on the pleading of mistake on their part or misrepresentation on the
part of the respondents as to the applicability of Urban Ceiling Law and
FAR as provided by .the bye-laws, both being the laws in force in India. H
1140
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
A The vitiating effect of alleged mistake shall stand obliterated no sooner
it is found that the appellants have, in spite of the so-called mistake being
discovered, yet, chosen to stand by the contract, ratifying the same by
their conduct and went ahead to exercise the rights which accrued to
them under the same contract which they are pleading to be vitiated by
B the mistake. [1159-G-H; 1160-A-BI
2.5. The submission that in the conveyance deed the FAR was
again mentioned as 2.0 and at that stage there was a clear misrepresentation by respondent cannot be accepted. Assuming that there was
some misrepresentation the appellants had a couple of remedies, i.e.,
C to either rescind the contract or seek restitution or to affirm the
contract without prejudice to their right to seek damages by way of
restriction for the loss caused by the misrepresentation. Appellants
affirmed the contract which is clear from the fact that they immediately commenced construction on the land even though the building
D plans were on FAR 1.75. Affirmation of the contract and proceeding
with the construction clearly indicates that the appellants did not
rescind the contract nor reserved their right to seek restitution by
award of damages or seek restitution. [1156-G-H; 1157-A-D]
E
2.6. At the time of initiating the legal proceedings in the Court,
it was open to the appellants to either affirm the contract without
prejudice to their right seeking damages by way of restitution for loss
caused by alleged misrepresentation or to rescind the contract by
getting the declaration that the contract was not binding on the
F appellants. Appellants elected the first option. Had they rescinded the
contract and prayed for declaration that the contract was not binding
on them, then, on its being so declared, terms of the auction notice
would not have bound the appellants in any way and the Court while
granting the relief could have moulded the relief according to facts and
situation prevalent. Appellants cannot be permitted to sit on the fence
G in indecision and take a chance. By putting up the construction the
appellants have encumbered the property and the respondent cannot
be fastened with the liability to pay for the construction put up byappellants with full knowledge of true facts. (1157-G-H; 1158-A-C)
H
2.7. The Urban Land Ceiling and Regulation Act, 1976 itself has
GANGA RETREAT AND TOWERS LTD. v. STATE
1141
been repealed by the Notification of 7.10.1999. With the repeal of the A
Ceiling Act, all proceedings under the Ceiling Act have abated.
[1163-A-B]
Pandit Madan Swaroop Shrotiya Public Charitable Trust v. State of
UP. & Others, [2000) 6 SCC 325, referred to.
B
2.8. The process for obtaining exemption from land ceiling did
not in a~y manner affect the appellants as their plans were sanctioned
even before the question was raised as to the application of the Ceiling
Act to the prop.erty. Also the State Government has stated that it is
not going to enforce the conditions imposed under the exemption C
order. Immediately upon the sanction of building plans the process of
construction began which clearly implies that the appellants had never
intention of transferring the land as plots and therefore the condition
inhibiting the transfer of plots was irrelevant so far as the appellants
are concerned. Thus, the conditions imposed in the exemption order D
were not an impediment in any manner. [1162-G; 1163-D-E]
Sikkim Subba Associates v. State of Sikkim, (2001) 5 SCC 629;
Mis Motilal Padampat Sugar Mills Co. Ltd. v. State of UP. & Others,
(1979) 2 SCC 409 and Ningawwa v. Byrappa & Ors., (1968) 2 SCR 797,
distinguished.
H V. Rajan v. C.N Gopal and Ors., AIR (1975) SC 261, relied on.
E
Satyabrata Ghose v. Mugneeram Bangur and Co. and Anr., [1954)
SCR 310; Mis. Alopi Parshad and Sons Ltd. v. Union of India, [1960) 2
SCR 793 and Raja Dhruv Dev Chand v. Harmohinder Singh & Anr., F
[1968) 3 SCR 339, referred to.
Indian Contract and Specific Relief Acts by Pollock and Mui/a
Eleventh Edition, Volume I, pp. 269-270 and Chitty on Contracts
Volume I, Twenty-Eighth Edition 1999 para 25-003, referred to.
G
3. The power conferred by Section 90 of the Jaipur Development
Authority Act, 1982 cannot be exercised by the Government to give
directions to increase FAR in one individual or particular case. Policy
and guidelines can be issued for general application or for a class of
persons or area or based on some such other criteria as may withstand H
1142
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
A the test of Article 14 of the Consti.tution. As such the appellants cannot
claim a right to get exemption from the prevalent law nor heard to say
that since the Government had the power to give direction, its failure
to exercise the power of issuing direction, it has perpetuated the breach
of contract. [1170-B-CJ
B
4. Under section 298 of the Rajasthan Municipalities Act, 1959
general power is given to the Government that in case the Government
feels that the bye-laws framed or the orders issued are not reasonable
or are detrimental to the public interest or there is any other good
ground available, then, it can repeal the bye-laws wholly or in part or
C modify any rule or bye-law made by the Board after inviting objections. The power could not have bP.en exercised to suit the needs of an
individual case. [1170-G-H; 1171-A-B]
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 5188 of
D 2001.
E
From the Judgment and Order dated 9 . .5.2001 of the Rajasthan High
Court in D.B.C.S.A. (W) No. 895 of 1999.
WITH
C.A. Nos. 5189 and 5190 of 2001.
Shanti Bhushan, Dr. Abhishek M. Singhvi, M.R. Calla, Harish N.
Salve, Sunil Kumar Jain, S. Borthakur, Kamal Gupta, S.M. Mehta, Adv.
F General for State, Ms. Sandhya Goswami, J.B. Singh, Ms. Meenakshi
Sakhardande, Ms. Aparajita Singh, Pradeep Agarwal, Dr. P.C. Jain, A.P.
Dhamija, L.P. Singh, Punit Jain, Sushil Kumar Jain, Manish Singhvi and
Ashok K. Mahajan for the appearing ·parties.
G
The Judgment of the Court was delivered by
BHAN~ J. : Aggrieved by the judgment and order of the Division
Bench of Rajasthan at Jaipur in setting side the order of the Single Judge,
thereby, dismissing the writ petition filed by the appellants, the present
appeals have been filed. All the three appeals have been filed by the same
H set of appellants and against the same judgment. As three separate appeals
GANGA RETREAT AND TOWERS LTD. v. STATE [BHAN, J.]
l 143
were filed by the respondents before the Division Bench against the order A
of the Single Judge the appellants have filed three separate appeals. They
are taken up for disposal by a common order.
The State of Rajasthan (hereinafter referred to as "the Respondent
No. l ") decided to dispose of by public auction two prime properties B
situated in the heart of Jaipur City. One of the properties was known as
Dr. Helligs Bungalow, near Khasa Kothi State Hotel, M.I. Road, Jaipur and
the other was a plot of land situated near Khasa Kothi known as the site
of Food Craft Institute building on M.I. Road, Jaipur. In the present case
we are concerned with the first property only. Respondent No. I issued
advertisement for auction of Dr. Helligs Bungalow, which was scheduled C
to be held, according to the auction notification on 21.12.1994. In the
advertisement the property was described as free hold, ceiling free, vacant,
crest j·ewel property known as Dr. Helligs Bungalow (10,400 sq. yards).
The permitted use of the property was shown as hotel/commercial comp\ex/hote\ cum-commercial complex. The terms and conditions for the D
auction were also provided in the advertisement. Condition Nos. 7, 8, 9,
l 0, 12 and .13 relate to the controversies involved in this litigation and are
reproduced hereunder:
"7. Land measuring 1,400 sq. mtr. •hall be auctioned with the E
condition that the successful bidder shall have to surrender a strip
of land measuring 6.2 sq. mtr. for the road widening/parking of
commercial vehicle free of charges. He will be given the benefit
in terms of FAR, which is calculated on the basis of original plot
size.
8. Other parameters of this plot size have been approved by JDA
and are given as under:
Coverage
F.A.R.
No of floors
Maximum permissible
Height
62.5% F.A.R.
2.0
B+G+4
16.76 Mtrs.
F
G
H
1144
A
B
c
D
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
Parking provision
Set backs
Front towards
Front towards
Rear
IPCU per 200 sq. mtr. of built up area
15 mtrs. Station Front to'.vards roads.
15 mtrs. Circuit House 7.5 mtr.
At<!l Ban (After leaving 6.2 Mtrs.
for future road widening/parking
commercial vehicle.
6 Mtrs. as indicated in the plan.
9. The construction work on the plot should be commenced with
in one year from the date of handing over of possession of the
land and the building. Building construction should be done
within 3 years. If the party wants further extension beyond three
years that shall be given against the penalty of Rs. 20,000 (Rupees
twenty thousand) p.m. but in no case the period shall be extended
more than 2 years.
l 0. After the full atnount due against the plot as deposited by the
E
purchaser the Patta of the plot will be issued in favour of the
purchaser which would enable him to start construction on the plot
in accordance to the approved plan and under architectural control
as per specifications given by JDA.
F
12. The land shall be used for construction of Hotel/Commercial
Complex/Hotel cum commercial complex only. If he uses this
property for other than this purpose, he would have to seek prior
permission from the Government ofRajasthan against payment of
charges as the Government may fix thereof.
G
H
13. The purchaser shall have to strictly abide by the parameters
and set backs as laid down in condition No. 8. Any violation of
these terms and conditions shall lead to the forfeiture of his right
on this prope1ty and hence the property shall stand reverted to the
Government without payment of any compensation for the land
and the building thereupon."
GANGA RETREAT AND TOWERS LTD. v. STATE [BHAN, J.]
1145
Mis Ganga Retreat and Towers Ltd., a company registered under the A
Indian Companies Act, 1956 (formerly known as Mis Lok Hotels and
Resorts Limited), the appellants herein were declared as the successful
bidder in the auction held. The appellants' bid of Rs. 19,56,76,000 being
the highest was accepted and the property was knocked down in their
favour. The successful bidder, as per term No. 5, was required to pay the B
sale consideration, as per the following schedule:-
"(i) 10% of the final bi\i on the spot in cash or through Demand
Draft in favour of Director of Estate, Rajsthan, Jaipur (the
amount of Rs. 20.00 lacs deposited as earnest money shall
be allowed to be adjusted against this deposit of 10%).
C
(ii)
15% amount of the final bid will have to be deposited within
15. days from the date of acceptance, letter sent to the
successful bidder by the Government of Rajathan.
(iii) 75% amount of the final bid will have to be deposited by D
successful bidder within 60 days of the notice for deposition
of the full and final amount of the bid amount which the
party shall be informed by the Government of Rajasthan.
Failure to deposit the aforesaid amount at any stage, i.e., (i), (ii) E
and (iii) above will result in forfeiture of the amount already
deposited by the successful bidder and hence cancellation of the
bid."
The payment was not made as per schedule given above. The entire
sale consideration amounting to Rs. 19,56,76,000 was paid on 16.5.1995. F
As there was a delay in making the payment as per schedule the appellants
accepted their liability to pay interest for the delayec' payment. A sum of
Rs. 30,01,273 towards interest for delayed payment was made. Last
instalment of Rs. 83,562.72 P. towards the amount of interest was paid by
demand draft dated 21.08.1995. Total amount paid was Rs. 19,86,77,273. G
The cost and expenses for registration of patta, stamp duty and all other
incidental expenses were also to be borne by the purchaser. Sale deed
could not be executed in favour of the appellants as the appellants did not
furnish the stamp papers. After repeated letters including the letter dated
21.05.1996 the appellants submitted the requisite stamp duty and registra- H
1146
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
A tion charges amounting to Rs. I, 19,25,720 for execution of the sale deed
on 18.12.1996. Thereafter, the sale deed was executed and registered on
7.01.1997 and immediately thereafter possession was delivered to the
appellants. Term of the auction notice that Floor Area Ratio (for short
"FAR") would be 2.00 was also repeated in the sale deed.
B
c
The appellants thereafter applied for S<'.nction of plans for putting up
construction on the property and the Planning Cell of the Jaipur Municipal
Corporation (for short "the JMC") demanded a deposit of Rs. 1,48,79,887
towards map approval charges.
These charges were deposited under
protest by the appellants. According to the appellants the JMC had not
framed any Rules in this regard and that the charges were exorbitant an_d
without authority oflaw. The appellants also handed over 6.2 meters width
of strip land to the JMC of old Dr. Helligs bungalow as per their letter dated
2.5.1997 (Annexure IV).
D
On 11.4.1997, the
Additional Director and Competent authority
under the Urban Land Ceiling and Regulation Act, 1976 (for short "the
Ceiling Act") issued a notice to the appellants under Section 38 of the
Ceiling Act, alleging that the appellants were holding land in excess of
ceiling limits and had not filed the return as required under Section 6(1)
E read with Section 15 of the Act. The appellants replied to the aforesaid
notke on 17.4.1997 pointing out that the Respondent No. 1 had sold the
property as free from ceiling limit and therefore, there was no need to file
a return. As the explanation was not accepted by the competent authority,
the appellants applied for exemption under Section 20 of the Act. The
F appellants also submitted the return in the prescribed form with a covering
letter dated 19.4.1997. On 3.5.1997 the Competent Authority issued a
notice under Section 8(3) of the Ceiling Act enclosing a draft statement
as to vacant land. Simultaneously, application filed under Section 20 of
the Act for exemption was processed.
On 11.8.1997, the competent
authority granted exemption to the appellants on certain conditions. It was
G stipulated that the exemption was being granted subject to the terms and
conditions stated in the conveyance deed dated 7.1.1997 and that it could
be used only for the purposes set out in the conveyance deed. It was also
stipulated that for any construction on the land, plans will have to be
submitted for sanction to the JMC and all the standards regarding
H construction shall be applicable as per the norms of the JMC. Another
•,
t ..
'
r
\5.
GANGA RETREAT AND TOWERS LTD. v. STATE [BHAN, J.]
1147
corldition put was .that the land would not be transferred or conveyed in A
any manner to ;my one without prior permission of the State Government
except offering it as security to the financial institutions for raising loan.
As this clause has given rise to the controversy on which lengthy arguments ,
have been addressed, the same is reproduced below for reference:
"5) That the sale, gift or any transfer of the plot will not be closed
without prior approval of the State Government. But mo1igaging
the property to financial institution for taking loan without parting
with the possession the State Government will have no objection."
B
On 24.6.1996 the Jaipur Development Authority (for short "the C
JOA") revised its bye-laws. The revised building Bye-laws came into force
w.e.f. 24.6.1996 in which parameters in respect of commercial hotels and
commercial plots were amended. Vide Regulation No. 9.3.3 of the 1996
Regulations the FAR was reduced to 1. 75 instead of 2.00 as provided by
the Bye-laws of 1989.
D
Appellants submitted their building plans as per FAR 2.00. JMC on
22.2.1997 approved the building plans subject to FAR l.75 only as per
1996 Bye-laws as against FAR 2.0 permitted by the auction notice and the
conveyance deed.
On 10.10.97, after getting the land exempted from
ceiling, the Co1npany wrote to the JMC to re-examine the case and allow E
FAR "2.0 on the appellants' re-submitting the plans for approval or in the
alternative to advise the General Administration Depatiment to refund the
proportionate amount consequent upon the reduction in the FAR.
On 28.10.1997, the appellants wrote a letter to the Minister for Urban F
Development, Government of Rajas~han, for intervening in the ap,pellants'
favour in their dispute with the JMC which was not allowing FAR 2.0 as
promised in the terms of auction and the sale deed. Appellants also wrote
a letter to the Chief Minister on 17. l l .1997 for intervention in the matter
and for ordering the Secretary, Urban Development and Housing to clear G
the plans with FAR 2.0 as a special case urgently. On 18.12.1997 again,
a communication was addressed by the appellants to the Chief Secretary
giving the following three proposals:
"(A) to instruct Jaipur Nagar Nigam to allow F.A.R. 2 as per
Auction conditions. As F.A.R. 2 existed before the new Bye-laws H
A
B
c
1148
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
came into force in September, 1996. Plus to pay interest at 18%
p.a. for delayed period to clear our plans as compensation. The
delayed period may be calculated from the day we deposited our
plans for approval to the day the plans are approved. We have
paid interest on account of delay from our side.
(B) To refund the whole amount with interest, the registration
cost, the maps approval charges, the L.B.T. charges etc.
(C) To refund proportionate charges on all above for the reduced
F.A.R. from 2 to 1.75 i.e. 12.5% all above charges."
It was also stated in this letter that if no response was received to the
proposals in writing within fifteen days, the appellants shall go to the court
oflaw for redressal of their grievances. On 22.10.1997 the Chief Secretary
wrote to the Urban Development and Housing Department recommending
D the case of the appellants for grant of FAR 2.0 instead of FAR 1.75 in
compliance with the conditions of the auction. As no decision was taken,
the appellants filed S.B. Civil Writ Petition No. 195/98 against the State
ofRajasthan, Jaipur Development Authority, Jaipur Municipal Corporation
amongst others, who were officers of the State Government, claiming the
following reliefs.
E
F
G
H
"In the premises aforesaid the writ petition of the petitioner may
kindly be allowed with costs and by an appropriate writ, order or
direction, the Hon'ble Court may be pleased to:
(a)
declare that on account of the reasons set out herein and the
order dated 9th September, 1997 passed by the Municipal
Corporation, referring to approve maps upto 2.0 FAR the
contract of sale of the property described in this petition vi de
sale deed dated 7th Jan., 1997 stands frustrated or has
become i~possible of performance or invalid rendering the
sale deed dated 7th Jan., 1997 void.
(b)
declare that the Regulations of 1996 were not applicable to
the petitioner and the same cannot be enforced against the
petitioner by the Municipal Corporation, Jaipur or JDA in
view of the sale deed dated 7th Jan., 1997.
GANGA RETREAT AND TOWERS LTD. v. STATE [BHAN, J.]
1149
(c)
declare that the sale deed being a government grant was not A
required to be registered and no stamp duty was required to
be paid and consequently the petitioner is entitled to the
refund of the stamp duty and the registration charges.
(d)
direct the respondents jointly and severally to pay to the B
petitioner a sum of Rs. 5102.94 lakhs alongwith future
interest @ 18.5% per annum.
Any other appropriate writ order or direction which may be
considered just and proper in the facts and circumstances of the C
case may kindly also be issued in favour of the Petitioners."
On issuance of notice the respondents put in appearance and. filed
their replies. Apart from contesting on merits, preliminary objections were
raised regarding maintainability of the petition on the ground that declaratory relief claimed could not be granted in the writ jurisdiction. It was also D
contended that the reliefs claimed pertained to the concluded contract with
regard to the sale of property culminated by execution of the sale deed.
That the relief being claimed was based on breach of contract and the writ
petition was not the appropriate remedy for redressal of such grievances.
No petition could be entertained for either specifically enforcing the E
contract or/and for compensation for breach of contract. That the highly
disputed questions of fact were involved which could not be adjudicated
without adducing evidence. Such disputed questions of fact could not be
adjudicated by the High Court in exercise of its extra-ordinary jurisdiction
under Article 226 of the Constitution of India.
Learned Single Judge rejected the preliminary objections regarding
the maintainability of the petition and declared that the sale deed was
statutory in nature. It was a grant as well. The rights and the obligations
F
as incorporated in the sale deed were statutory in character as regards the
rights and obligation of the parties. No change could be effected thereafter G
on any pretext whatsoever in regard to the reducing the FAR from 2.0 to
1.75. In the auction notice property was described as free hold and ceiling
free. The action of the State in not acting upon the assurance given
amounted to a fraud, which invalidated the sale. Consequently, the learned
Single Judge declared that the auction sale held on 21.12.1994 and the H
1150
SUPREME COURT REPORTS [2003] SUPP. 6 S.C.R.
A consequent sale deed dated 7. l .1997 were null and void having no legal
sanctity. The contract was frustrated. All consequent actions taken by
either of the parties pursu!lnt to the auction and the sale deed were
invalidated and the appellants were declared entitled to be restituted to the
original position as it existed prior to the date of auction and execution of
B the sale deed. Consequently, the respondents were directed to refund to
the appellants, the payments recei"ed by the respective respondents,
pursuant to any term of the auction dated 21.12.1994 which included the
entire sale considerations as mentioned in the sale deed dated 7 .1.1997
along with all other payments made to the respondents by the appellants
towards stamp duty, registration charges, land and building taxes etc. with
C interest @ 18% per annum calculated from the date of receipt of such
amount by the respective respondents till the date of actl!al refund to the
appellants. It was also directed that the .JMC shall refund all payments
made by the appellants towards building map approval charges, additional
constructed area charges, licence fee, inspection charges, etc. along with
D interest @ 18% per annum from the date of receipt of said payments by
the appellants till the date of actual refund to the appellants. As regards
the damages claimed by the appellants for the incomplete construction
which by that time had been raised upto 9 stories (which was held to be
under compulsion), it was directed that it would be advisable that the State
E of Rajasthan cor,istitutes an expert Committee consisting of the Chief
Engineer PWD and Director, Town Planning Department or any other
officer having expertise to assess the value at the PWD rates and value the
construction on the site and after such valuation made by the Committee,
the amount assessed be refunded to the appellants within forty five days·
of the assessment.
F
As directed by the learned Single Judge, a Valuation Committee was
constituted by the State Government and the value of the construction as
per PWD rates was assessed at Rs. 9,97,51,003. From this amount, 10%
was deducted by the Committee as contractor's profit, which was included
in the analysis of BSR rates.
After deducting 10% amount, i.e., Rs.
G 99,75,100 amount payable to the appellants representing the construction
on the land was worked out by the Committee at Rs. 8,97,75,903.
Aggrieved by the aforesaid order of the learned Single Judge, appeals
were preferred before the Division Bench which were acc;epted. It was held
H that the sale of land by way of auction was neither statutory nor by way
GANGA RETREAT AND TOWERS LTD. v. STATE [BHAN, J.)
l 151
of grant.
Consequently, it was held that the rights and obligations A
incorporated in the sale deed were not statutory in character. That it was
a completed contract in which highly disputed questions of fact were
involved which could not be adjudicated upon by the High Court in
exercise of its writ jurisdiction. It was left open to the appellants to seek
their remedy in the Civil Court, if so advised.
At the outset, we may state that Shri Shanti Bhushan, learned senior
counsel appearing for the appellants fairly conceded that he would not be
able to support the findings recorded by the Single Judge to the effect that
B
the rights and obligations incorporated in the sale deed were statutory in C
character or that the sale of land by Respondent No. l to the appellants
were by way of grant.