# GODAVARMAN THIRUMULPAD v. UNION OF INDIA & ORS

- **Citation:** [2010] 15 S.C.R. 783
- **Court:** Supreme Court of India
- **Decided:** 2010-12-03
- **Case number:** I.A. Nos.! 2609-2610 of 2009
- **Bench:** S.H. Kapadia, Aftab Alam, K.S. Panicker Radhakrishnan
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/godavarman-thirumulpad-v-union-of-india-ors-26758
- **Pages:** 71

## Headnote

Forest Conservation Act, 1980: s. 2 - Forest land - Project
at NO/DA for building large scale memorial with extensive
D
stone work - Spread over an area of 33.43 hectares of land
- Whether the project area, a forest land - Held: In the
revenue records, none of the khasras (plots) falling in the
pr..oject area were ever shown as jungle or forest - The project
are.a was treated as an urban park - Trees planted on it were
E
allowed to stand and grow for about 12-14 years when they
were cut down to make the area clear for the project - Though
man made forest may equally be a forest as a naturally grown
one and non-forest land may also, with the passage of time,
change its character and become forest land, but this cannot
F
be a rule of universal application and must be examined in
the overall-facts of the case - The trees planted with the intent
to set up an urban park cannot turn into forest within a span
of 10 :to 12 years and the land that was forever agricultural
would hot be converted into the forest land - The project site
G
. is not forest land - Construction of the project without the prior
permission from the Central Government did not in any way
contravene s. 2 of the Act - Environment Protection Act, 1986.
Environment Protection Act, 1986: s. 3(3) -
State
783
H
784
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R.
A Government's project for building large scale memorial with
extensive stone work - Project at NO/DA - Requirement of
prior environmental clearance under the EIA Notification S. 0.
1533(E) dated September 14, 2006 - Held: The project in
question cannot be termed as a "Building and Construction
s project" falling under item B(a) of the Schedule to the EIA
Notification - Applying the test of 'Dominant Purpose or
Dominant Nature' of the project or the "Common Parlance"
test, the project could only be categorized under item B(b) of
the schedule as a Township and Area Development project"
c - But under that category it does not come up to the threshold
marker inasmuch as the total area of the project (33. 43
hectares) is less than 50 hectares and its built-up area even
if the hard landscaped area and the covered areas are put
together comes to 1,05,544.49 square metres, i.e., much
below the threshold marker of 1,50,000 square metres -
D Therefore, the project does not fall within the ambit of the EIA
notification - EIA Notification S.O. 1533(E) dated September
14, 2006 - Items B(a) and B(b) - Wild life.
E
Circular/Government order/Notification:
EIA Notification S.O. 1533(E) dated September 14, 2006
- Items B(a) and B(b) - "Building and Construction project"
and "Township project" - Distinction between.
EIA Notification S.O. 1533(E) dated September 14, 2006
F - Ambiguity in - Held: The Notification calls for second look
by the concerned authorities - Project activities under Item
B(a) and B(b) of the schedule to the notification need
description with greater precision and clarity - Environmental
laws.
G
Constitution of India, 1950: Article 21 - Construction of
project adjoining the Okhla Bird Sanctuary - Continuation of
the project challenged on the ground that it was a potential
hazard to the sensitive and fragile ecological balance of the
H Sanctuary- Held: Environment is one of the facets of the right
IN RE: CONSTRUCTION OF PARK AT NOIDA ANAND
785
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.0.1.
to life guaranteed under article 21 of the Constitution and if A
the Court perceives any project or activity as. harmful or
injurious to the environment it can step in - The question of
the likelihood of the project causing any adverse effects on
the Okhla Bird Sanctuary must, therefore, be examined from
this angle - Environmental impact assessment of the project
B
was done by expert agencies - None of the expert bodies took
the view that the project was so calamitous or ruinous for the
bird sanctuary that it be altogether scrapped in order to save
the Sanctuary - The expert bodies gave recommendations
which allowed the completi

## Text

_Characters 0–39,763 of 134,019. This is a partial read: ask again with offset=39763 for what follows._

[201 O] 15 (ADDL.) S.C:R. 783
I.A. NOS.2609-2610 OF 2009
A
IN
WRIT PETITION (CIVIL) N0.202 OF 1995
IN RE.:
'CONSTRUCtlON OF PARK AT NOIDA NEAR OKHLA
BIRD SANCTUARY ANAND ARYA & ANR. T.N.
B
GODAVARMAN THIRUMULPAD
v.
UNION OF INDIA & ORS.
DECEMBER 3, 2010
c
[S.H. KAPADIA, CJI, AFTAB ALAM AND K.S.
PANICKER RADHAKRISHNAN, JJ.]
Forest Conservation Act, 1980: s. 2 - Forest land - Project
at NO/DA for building large scale memorial with extensive
D
stone work - Spread over an area of 33.43 hectares of land
- Whether the project area, a forest land - Held: In the
revenue records, none of the khasras (plots) falling in the
pr..oject area were ever shown as jungle or forest - The project
are.a was treated as an urban park - Trees planted on it were
E
allowed to stand and grow for about 12-14 years when they
were cut down to make the area clear for the project - Though
man made forest may equally be a forest as a naturally grown
one and non-forest land may also, with the passage of time,
change its character and become forest land, but this cannot
F
be a rule of universal application and must be examined in
the overall-facts of the case - The trees planted with the intent
to set up an urban park cannot turn into forest within a span
of 10 :to 12 years and the land that was forever agricultural
would hot be converted into the forest land - The project site
G
. is not forest land - Construction of the project without the prior
permission from the Central Government did not in any way
contravene s. 2 of the Act - Environment Protection Act, 1986.
Environment Protection Act, 1986: s. 3(3) -
State
783
H
784
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R.
A Government's project for building large scale memorial with
extensive stone work - Project at NO/DA - Requirement of
prior environmental clearance under the EIA Notification S. 0.
1533(E) dated September 14, 2006 - Held: The project in
question cannot be termed as a "Building and Construction
s project" falling under item B(a) of the Schedule to the EIA
Notification - Applying the test of 'Dominant Purpose or
Dominant Nature' of the project or the "Common Parlance"
test, the project could only be categorized under item B(b) of
the schedule as a Township and Area Development project"
c - But under that category it does not come up to the threshold
marker inasmuch as the total area of the project (33. 43
hectares) is less than 50 hectares and its built-up area even
if the hard landscaped area and the covered areas are put
together comes to 1,05,544.49 square metres, i.e., much
below the threshold marker of 1,50,000 square metres -
D Therefore, the project does not fall within the ambit of the EIA
notification - EIA Notification S.O. 1533(E) dated September
14, 2006 - Items B(a) and B(b) - Wild life.
E
Circular/Government order/Notification:
EIA Notification S.O. 1533(E) dated September 14, 2006
- Items B(a) and B(b) - "Building and Construction project"
and "Township project" - Distinction between.
EIA Notification S.O. 1533(E) dated September 14, 2006
F - Ambiguity in - Held: The Notification calls for second look
by the concerned authorities - Project activities under Item
B(a) and B(b) of the schedule to the notification need
description with greater precision and clarity - Environmental
laws.
G
Constitution of India, 1950: Article 21 - Construction of
project adjoining the Okhla Bird Sanctuary - Continuation of
the project challenged on the ground that it was a potential
hazard to the sensitive and fragile ecological balance of the
H Sanctuary- Held: Environment is one of the facets of the right
IN RE: CONSTRUCTION OF PARK AT NOIDA ANAND
785
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.0.1.
to life guaranteed under article 21 of the Constitution and if A
the Court perceives any project or activity as. harmful or
injurious to the environment it can step in - The question of
the likelihood of the project causing any adverse effects on
the Okhla Bird Sanctuary must, therefore, be examined from
this angle - Environmental impact assessment of the project
B
was done by expert agencies - None of the expert bodies took
the view that the project was so calamitous or ruinous for the
bird sanctuary that it be altogether scrapped in order to save
the Sanctuary - The expert bodies gave recommendations
which allowed the completion of the project subject to certain c
co
1nditions - Therefore, project allowed to be completed,
subject to conditions suggested by the expert bodies -
Environmental. laws - Wild life ..
The petitioners/ applicants were residents' of NOIDA,
U.P. According to them, the project, undertaken at the
D
· instance of Uttar Pradesh -Government was a "huge
unauthorized construction". A very large number of trees
that were felled down for the project formed a "forest" as
the term was construed by the Supreme Court in its OJder
dated December 12, 1996 and the action of the Uttar E
Pradesh Government in cutting down a veritabie forest
without the prior permission of the Central Government
and then Supreme Court, was in gross violation of
section 2(ii) of the Forest (Conservation) Act, 1980 (FP
ACt). The project was spread over an area of 33.4J'.
F
hectares, equal to 334334.00 square metres of land
surrounded by a boundary wall made of stone, 2 metres
in height and 0.3 metres in thickness with the estimated
cost at Rs. 685 crores. At the site of the project, there
used to be a tree cover, thin to high- moderate in density
G,
and for clearing the ground for the project- 6186 trees
were cut down and 179 were shifted during construction.
The project involved massive constructions that. wer~
made without any prior environmental clearance from the
Central Government or t~s5
state Level En.vironment
H
786
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R.
A Impact Assessment Authority in complete breach of the
provisions of the Environment Protection Act, 1986 (EP
Act) and the notification issued under the Act. The project
was causing great harm, and was bound to further
devastate the delicate and sensitive ecological balance
B of the Okhla Bird Sanctuary to which the site of the
project lay adjacent and, therefore, was in complete
disregard of the Supreme Court's directions concerning
'buffer ·zones'.
C
The State of Uttar Pradesh denied all the allegations
ma·de by the applicants. According to the State
·Government, it was setting up a park to develop and
beautify the area in a unique way. The park was
. conceived as a fine blend of hard and soft landscaping
with· memorial structures and commemoration pieces.
D The construction of the park did not violate any law or
the order of the Court. There was no infringement of the
provisions of the FC Act or the EP Act or the notification
made under it. Further, it was contended that the setting
up of the park caused no harm to the bird sanctuary and
E the objections raised by the applicants to the
construction of the park were fanciful and imaginary and
actuated by oblique motives. According to the State
Government, the work on the project commenced in
January 2008. The applicants filed IA before the Central
F Empowered Committee (CEC) constituted by the
Supreme Court on March 5, 2009. The instant IA was filed
by the applicants before the Supreme Court on April 22,
2009. The State Government contended that by that time
50% of the construction work of the project was
G completed. The report from the CEC was received in the
Supreme Court on September 4, 2009. On October 9,
2009, the Supreme Court by an interim order restrained
the State Government from carrying on any further
constructions till further orders. By that time, according
IN RE: CONSTRUCTION OF PARK AT NOIDA ANAND
787
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.0.1.
to the government, 70-75% of the construction work of A
the project was completed.
It was contended for the applicants that over 6000
trees were cut down for clearing the area for construction
of the project and it was, thus, a case of forest land being
8
put to use for non-forest use in complete violation of
Section 2(ii) of the Forest Conservation Act; that the
construction of the project was started by the Uttar
Pradesh Government without obtaining the prior
environmental clearance in complete violation of the
notification issued on September 14, 2006 under Section
C
3(3) of the EP Act; and that the project being located·
adjoining the Okhla Bird Sanctuary which was a serious
concern.
Disposing of the IA, the Court
HELD: 1.1. In the revenue records, none of the
khasras (plots) falling in the project area was ever shown
D
as jungle or forest. According to the settlement year 1359
Fasli (1952A.D.) all the khasras were recorded as
E
agricultural land, Banjar (uncultivable) or Parti
(uncultivated). NOIDA was set up in 1976 and the lands
of the project area were acquired under the Land
Acquisition Act mostly between the years 1980 to 1983
(two or three plots were notified under sections 4/6 of the
F
Act in 1979 and one or two plots as late as in the year
1991). But the possession of a very large part of the lands
under acquisition (that now form the project site) was
taken over in the year 1983. From the details of the
acquisition proceedings, it would appear that though on
most of the plots there were properties of one kind or the
G
other, there was not a single tree on any of the plots
under acquisition. The records of the land acquisition
proceedings, thus, complemented the revenue record of
1952 in which the lands were shown as agricultural and
not as jungle or forest. There is no reason not to give due
H
788
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R
A credence to these records since they pertained to a time
when the impugned project was not even in anyone's
imagination and its proponents were no where on the
scene. According to the information from the Deputy
Horticulture Officer, NOIDA, plantations were taken up
B along with seed sowing of Subabul during the year 199495 to 2007-08. A total of 9,480 saplings were planted
(including 314 saplings planted before 1994-95). NOIDA
had treated this area as ·an "Urban Park". It is, thus, to
be seen that on a large tract of land (33.45 hectares in
c area) that was forever agricultural in character, trees were
planted with the object of creating an urban park (and not
for afforestation!). The trees, thus, planted were allowed
to stand and grow for about 12-14 years when they were
cut down to make the area clear for the project. The
0 satellite images tell that in October, 2006 there was thin
to moderately dense tree cover over about half of the
project site. But this fact was all but admitted; the State
Government admitted felling of over 6000 trees in 2008.
The trees planted with the intent to set up an urban park
cannot turn into forest within a span of 10 to 12 years and
E the land that was forever agricultural, would not be
converted into forest land. [Paras 20 to 23] [813-F-H; 814A-H; 815-A]
T.N. Godavarman Thirumulkpad v. Union of India & Ors.
F (1997) 2 SCC 267 - relied on.
T.N. Godavarman v. Union of India, (2006) 5 SCC 28;
Samatha v. State of Andhra Pradesh & Ors., (1997) 8 SCC
191; M. C. Mehta v. Union of India & Ors., (2004) 12 SCC
G 118; State of Bihar v. Banshi Ram Modi, (1985) 3 SCC 643
- referred to.
1.2. No doubt, man made forest may equally be a
forest as a naturally grown one. Non-forest land may also,
with the passage of time, change its character and
H become forest land. But this cannot be a rule of universal
IN RE CONSTRUCTION OF PARK AT NOIDAANAND
789
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.OJ
lapplication and must be examined in the overall facts of A
the case otherwise it would lead to highly anomalous
conclusions. The contention of the applicants was that
the two conditions in the guidelines adopted by the State
Level Expert Committee, I.e., (i) "trees mean naturally
grown perennial trees" and (ii) "the plantation done on
B
public land or private land will not be identified as forest
like area" were not consistent with the wide definition of
forest given in the December 12, 1996 order bf the Court
and the project are'a should qualify as forest on· the basis
of the main parameter fixed by the Committee. If the said c
contention is accepted and the criterion fixed by the State
Level Expert Committee that in the plains, a stretch of
land, with an area of 2 hectares or above, with the
minimum density of 50 trees/ hectare would be a deemed
forest is applied mechanically and with no regard to the
0 .
other factors a greater part of Lutyens Delhi would
perhaps qualify as forest. This was obviously not the
intent of'the order dated December 12, 1996. Th~ project .
site is not forest land and the construction of the project
without the prior permission from the Central
E
.
1
Government does not in any way contravene section 2
of the FC Act. [Paras 30, 31] [818-H; 819-A-E]
2.1. Before the CE~ the MoEF in its first response
dated August 22/24, 2009 had taken the stand that the
project would not require any prior environmental
F
clearance under the EIA notification 2006. It had further
stated that in the EIA notifica·tion 2006, all building/
construction projects/ area development projects and
townships, were categorized as category 'B' projects and
the 'general condition' prescribed in the notification was
G
not applicable to construction projects. It went on to say
that the project did not require any prior environmental
clearance under the EIA notification 2006 even though~
"being within the prescribed distance from a wildlife
,~
1
sanctuary/national park or inter-state boundary". The firs~ HI
790
SUPREME COURT REPORTS [2010] 15 (ADDL) SC R
A response of the MoEF before the CEC was evidently
based on the inputs received from the UP Government
about the nature of the project and the extent of
constructions involved in it. In the second response
before the CEC dated September 2, 2009, the MoEF stated
B that after its earlier letter of August 22, 24, 2009, the MoEF
had received further information about tile prcject from
various sources and the fresh findrngs raised farreaching issues of public concern that extended beyond
the parameters set by the EIA notification of 2006. It
c further stated that the certificate issued by the SEIAA of
UP stated that the total built-up covlred area was only
9 ~!42 square metres and the report of the CCF wcs not
clear :JS to the extent of the covered area vis-a-vis
conc:rete landscaping, pil!ar(s), platform(s), lawn(s), tree
lJ planting, etc. The MoEF was not fully in possession of the
basic facts relating to the project and its likely impact on
the environment. It left the decision in the hands of the
CEC. The CEC in its report to this Court dated September
4, 2009 held that the project was covered by the EIA
E notification 2006 and it requir-ed prior environmental
clearanc0 in terms of the notification. When the matter
finally cc1.ne up before the Court, the MoEF was once
again asked to take a clear stand on the issue whether
the project was covered by the EIA notification 2006. The
MoEF filed a brief affidavit on Octob£:r 21, 2009 in which
F it acknowledged that the CEC in its report dated
September 4, 2006 had stated that the State c.~ UP should
be directed to seek environmental clearance for the
project from the MoEF in terms of the notification. The
MoEF, however, reiterated its stand in very definite and
G unequivocal terms that the project in question did not fall
within the ambit of the EIA notification 2006 and no
environmental clearance was required for such kind of
projects. The stand of the MoEF was based on the
premise that the area of the project (33.43 hectares) was
H less than 50 hectares and its built up area (9,542 square
'
IN RE: CONSTRUCTION OF PARK AT NOIDA ANAND
791
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.OJ
metres) was less than 20,000 square metres. Having thus
A
made its stand clear, the MoEF went on to say that in case
the Court desired the project to be appraised from the
environmental angle it would do so and submit its
recommendations. It, however, put in a caveat that such
appraisals were made before the commencement of the
B
construction activity at the site and in the instant case the
project was already in the advanced stage of
construction. [Paras 34 to 37] [820-C-H; 821-A-C; 822-DH]
2.2. The EIA notification provided that all projects and
C
activities enumerated in its Schedule would require prior
environmental clearance before any construction work or
preparation of land for the project is started on the project
or activity. The projects and activities depending upon
. various factors such as the potential hazard to
D
environment, location, the extent of area involved, etc. are
categorized in categories 'A' or 'B'. For projects or
activities fa!!ing in category 'A', the competent authority
to grant prior environmental clearance is the MoEF and
for projects or activities falling in category 'B', the State
E
Environment Impact Assessment Authority (SEIAA). In
~.
certain cases a project or activity, though categorized in
category 'B' may be treated as category 'A' by application
of the general condition (on account of its location being
within a distance of ten km from a protected area notified
F
under the Wildlife (Protection) Act etc.). Further, projects
- or activities categorized as category 'B' may or may not
require an environmental impact assessment before the
grant of environmental clearance depending on the
nature and location specificity of the project. The projects
G
requiring an EIA report shall be termed as category '81'
and the remaining shall be termed as '82' and will not
require an EIA report. For categorization of projects into
81 and 82, the MoEF issue appropriate guidelines from
time to time. The schedule to the notification has a table
H
792
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R
A that is divided into five columns. The first column
contains the se~ial numbers, and the second the
description of the project or activities; the third column
lists those projects or activities that fall in category 'A' and
the fourth, those falllng in category 'B'; the fifth column
B against each Item Indicates whether any general or
specific condition applies to the project or activity
described In that Item. In some cases where the project
or the activity Is shown In column 4 as category 'B', the
application of the general condition is expressly indicated
c in column 5 of the table. [Para 45] [830-A-H; 831-A]
2.3. For the project under consideration, the relevant
entries in the schedule are 8(a) and 8(b). Both items 8 (a)
and 8 (b) are listed in column 4, i.e., in category 'B'. In
column 5, against any of the two items, there is no
D mention of application of the general condition but it is
expressly said that all projects in item 8(b) would be
appraised as category '81', that is to say, for a project
under item 8(b) the prior environmental clearance must
be preceded by an environmental impact assessment.
E Item 8(a) deals with Building and Construction projects
and the threshold mark that would bring the project
within the ambit of the notification is equal to or more than
20,000 square metres and less than 1,50,000 square
metres of 'built-up area'. It is further clarified that these
F - figures relate to built-up area for covered construction;
in case of facilities open to the sky, the built up area
would be the activity area. Item 8(b) deals with Townships
and Area Development projects and the threshold mark
for the project to come within the ambit of the notification
G is an area equal to or more than 50 hectares or built-up
area of more than 1,50,000 square metres. [Paras 46, 47]
[831-B-E]
2.4. Since in the schedule to the notification "Building
and Construction projects'' and "Townships and Area
H
IN RE: CONSTRUCTION OF PARK AT NOIDA ANAND
793
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.0.1.
Developments projects" are enumerated separately, the
A
former in item 8(a) and the latter in item 8(b), this would
normally suggest that the notification treats those two
kinds of projects separately and differently. It would,
therefore, be reasonable to say thatl an "Area
Development project" though involving a good deal of
B
construction w.ould yet not be a "Byilding and
Construction project". It is extremely difficult to accept the
-
contention that the categorization under' items 8 (a) and
8 (b) has no bearing on the nature and cha~acter of the
project and is based purely on the built I up area. A c
building and construction project is nothing but addition
of structures over the land. A township p~oject is the
development of a new area for residential, cdmmercial or
industrial use. A township project is di*erent both
quantitatively and qualitatively from a mere building and
0
construction project. Further, an area d~velopment
project may be connected with the township
development project and may be its first stage when
grounds are cleared, roads and pathways are laid out and
provisions are made for drainage, sewage, electricity and
telephone lines and the whole range of other civic
infrastructure. Or an area development project may be
completely independent of any township development
project as in case of creating an artificial lake, or an urban
forest or setting up a zoological or botanical park or a
recreational, amusement or a theme park. The essential
difference between items 8(a) and 8(b) lie.s not only in the
different magnitudes but in the difference in the nature
and character of the projects enumerated there under.
Therefore, the project in question cannot be termed as a
"Building and Construction project". Applying the test of G
'Dominant Purpose or Dominant Nature' of the project or
E
F
the "Common Parlance" test, i.e. how a common person
using it and enjoying its facilities would view it, the
project can only be categorized under item 8(b) of the
schedule as a Township and Area Development project".
H
794
SUPREME COURT REPORTS [2010] 15 (ADDL.) SC R
A But under that category it does not come up to the
threshold marker inasmuch as the total area of the project
(33.43 hectares) is less than 50 hectares and its built-up
area even if the hard landscaped area and the covered
areas are put together comes to 1,05,544.49 square
B metn;is, i.e., much below the threshold marker of 1,50,000
square metres. The inescapable conclusion, therefore, is
that the project does not fall within the ambit of the EIA
·notification S.O. 1533(E) dated September 14, 2006. This
is not to say that this is the ideal or a very happy outcome .
c but that is how the notification is framed and taking any
other view would be doing gross violence to the scheme
9f the notification. [Paras 53, 55, 56, 57, 58] [834-G-H; 836D-F; 837-B-F]
3.1. The report of the CEC succinctly would sum up
[, the situation. Though everyone, excepting the pr~ject
proponents, viewed the construction of the project
practically adjoining the bird sanctuary as a potential
hazard to the sensitive and fragile ecological balance of
the Sanctuary, there is no law to stop it. This unhappy
E and anomalous situation arose simply because despite
directions by this Court, the authorities in the Central and
the State Governments had so far not been able to evolve
a principle to notify the buffer zones around Sanctuaries
and National Parks to protect the sensitive and delicate
F ecological balance required for the sanctuaries. But the
absence of a statute will not preclude this Court from
examining the project's effects on the environment with
particular reference to the Okhla Bird Sanctuary. For, in
the jurisprudence developed by this Court, Environment
G is not merely a statutory issue. Environment is one of the
facets of the right to life guaranteed under article 21 of
the Constitution. Environment is, therefore, a matter
directly under the Constitution and if the Cou.rt perceives
any project or activity as harmful or injurious to the
H environment it would feel obliged to step in. The question
IN RE: CONSTRUCTION OF PARK AT NOIDAANAND
795
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.0.1.
of the likelihood of the project causing any adverse
A
effects on the Okhla Bird Sanctuary must, therefore, be
examined from this angle. [Paras 65, 66] [840-F-H; 841A-C]
B
3.2. In pursuance of the Court's directions, the MOEF
had asked the project proponents to have the
environmental impact assessment of the project done by
some expert agencies. NOIDA, the project proponent got
three studies made of the impact assessment of the
project. One is a joint study prepared by the Salim Ali
Centre for Ornithology and Natural History (SACON),
C
, Deccan Regional Station, Hyderabad and the All India
Network Project on Agricultural Ornithology, Aacharya
N.G. Ranga Agricultural University, Hyderabad; and the
third by a group of three individuals that was vetted by
the Indian Institute of Technology, New Delhi. None of the
D
expert bodies has taken the view that the project is so
calamitous or ruinous for the bird sanctuary that it needs
to be altogether scrapped in order to save the Sanctuary.
The expert bodies gave recommendations which allowed
the completion of the project subject to certain
conditions. On behalf of the State of U.P., it was
unequivocally stated that all the conditions laid in the
reports of the Expert Bodies were acceptable to the State
Government/ NOIDA in their entirety. In the light of the two
study reports and the report submitted by the EAC, there
was no justification for directing the demolition of the
constructions made in the project, as prayed for on behalf
E
F
of the applicants. The project is allowed to be completed,
subject, of course to the conditions suggested by the
three expert bodies. The report of the Wll focused on the
G
felling of trees resulting in the disappearance of the
woodland that acted as a protective buffer for the bird
sanctuary and its first recommendation is to compensate
the loss of vegetation. It secondly focused on the
I
increased artificial light at the project site, which is likely
H
796
SUPREME COURT REPORTS [2010) 15 (ADDL.) S.C.R
A to affect the migratory bird population in the long run.
Apart from this, the extent of stone and concrete
constructions in the name of "hard landscaping" is highly
out of proportion. In the modified layout plan, the project
proponents reduced the area under hard surface to
8 35.54% of the total project area. Even that is unacceptable
from the environmental point of view. The area under
hard surface, whether covered, uncovered (including
pathways and· boundary wall etc.) or of any kirid
whatsoever must not exceed 25% of the total project ·
C area; of the rest, 25% should be used for soft/green
landscaping and the remaining, preferably 50% must
have a thick cover of trees of the native variety. The
plantation of trees should be especially dense towards
the Okhla Bird Sanctuary on the western side of the
project area. Any construction work should commence
D only on completion of the planting of the trees. [Paras 68,
75, 76] [841-G-H; 842-A; 845-8-H; 846-A]
3.3. In order to ensure full compliance with the
recommendations of the expert bodies (which form part
E of the judgment) and the directions of this Court, the
construction of the project needs to be seen by an expert
committee. One member of the committee, preferably an
ornithologist will be nominated by the MoEF, the other
member will be nominated by the CEC in consultation
F with the amicus and the Chairman-cum-CEO of NOIDA will
be the member-secretary of the committee. The said
directions were given in the peculiar facts of this case and
nothing said in the judgment would form precedent when
the court hears the matter of the "buffer zones". The EIA
G · notification dated September 14, 2006 urgently calls for
a close second look by the concerned authorities. The
projects/activities under items 8(a) and 8(b) of the
schedule to the notification need to be described with
greater precision and clarity and the definition of built-up
H area with facilities open to the sky needs to be freed from
IN RE: CONSTRUCTION OF PARK AT NOIDA ANAND
797
ARYA, TN. GODAVARMAN THIRUMULPAD v. U.0.1.
its present ambiguity and vagueness. The question of A
application of the· general condition to the projects/
activities listed in the schedule also needs to be put
beyond any debate or dispute. The environmental impact
studies in this case were not conducted either by the
MoEF or any organization under it or even by any
B
agencies appointed by it. All the three studies that were
finally placed before the Expert Appraisal Committee and
which this Court has also taken into consideration, were
made at the behest of the project proponents and by
agencies of their choice. This Court would ~ave been c
more comfortable if the environment impact st4dies were
made by the MoEF or by any organization under it or at
least by agencies appointed and re~ommended by it.
[Paras 77 to 79] (846-B-H; 847-A]
Case Law Reference:
'
(1997) 2 sec 267
referred to .
Paras 1, 6, 18,
25
(2006) 5 sec 28
referred to
Paras 16
(1997) 8 sec 191
referred to
Paras 18
(2004) 12 sec 118
referred to
Paras 18, 29
(1985) 3 sec 643
referred to
f)aras 26
CIVIL ORIGINAL JURISDICTION: I.A. Nos.! 2609-2610 of
2009.
IN
I
Writ Petition (Civil) No, 202 of 199$.
Under Article 32 of the Constitution of India.
I
With
I.A. Nos. 2896, 2900 & 2928 of 2010.
D
E
.F
G
H
A
B
798
SUPREME COURT REPORTS [201 OJ 15 (ADDL I S C R
IN
I.A. Nos. 2609-2610 of 2009.
IN
Writ Petition (C) No. 202 of 1995.
H.P. Raval, ASG, Harish N. Salve, U.U. Lalit, Jayant
Bhushan, K.K. Venugopal, Raju Ramachandra, S.C. Mishra,
S.K. Dwivedi, AAG, Siddhartha Chowdhury, A.D.N. Rao, P.K.
C Manohar, Mihir Chatterjee, Har;Jh Beeran, Manish Kumar
Bishnoi, Gautam Talukdar, R.K. Gupta, Rajiv Kumar Dubey,
Ankur Talwar, Kamlendra Mishra for the appearing parties.
The Judgment of the Court was delivered by
o
AFT AB ALAM, J. 1. At the centre of the controversy is a
very large project of the Uttar Pradesh government at NOIDA.
Objecting to the project are the two app1icants who are
residents of Sector 15A, NOIDA, U.P. They claim to be public
spirited people, committed to the cause of environment.
E According to them, the project, undertaken at the instance of
Uttar Pradesh Government is a "huge unauthorized
construction". The applicants state that a very large number of
trees were cut down for clearing the ground for the project. The
trees that were felled down for the project formed a "forest" as
F the term was construed by this Court in its order dated
December 12, 1996 in Writ Petition (C) No.202 of 1995; T.N.
Godavarman Thirumulkpad v. Union of India & Ors., (1997)
2 SCC 267 and the action of the Uttar Pradesh Government in
cutting down a veritable forest without the prior permission of
the Central Government and this Court, was in gross violation
G of section 2(ii) of the Forest (Conservation) Act, 1980 (hereafter
"the FC Act"). The project involved massive constructions that
were m<ide without any prior environmental clearance from the
Central Government based on Environment Impact
Assessment. The constructions were, therefore, in complete
H
IN RE: CONSTRUCTION OF PARK AT NOIDAANANDARYA, 799
TN. GODAVA.RMAN THIRUMULPAD v. Li.OJ [AFTABALAM. J)
breach of the provisions of the Environment Protectio;i Act,
A
1986 (hereafter "the EP Act") and the notification issued under
the Act. More importantly, the project was causing great harm,
and was bound to further devastate the delicate and sensitive
ecological balance of the Okhla Bird Sanctuary to which the site
of the project lay adjacent. The project was, thus, in curnplete
B
disregard of this Court's directions concerning 'buffer zones'
2. The State of Uttar Pradesh, of course denies, equally
strongly, all the allegations made by the applicants. According
to the State, it was setting up a park that would develop and c·
beautify the area in a unique way. The park was conceived as
a fine blend of hard and soft landscaping with memorial
structures and commemoration pieces. The construction of the
park did not violate any law or the order of the Court. There was
no infringement of the provisions of the FC Act or the EP Act
or the notification made under it. Further, the setting up of the
D
park caused no harm to the bird sanctuary. The applicants'
objections to the construction of the park were fanciful and
imaginary and actuated by oblique motives.
THE PROJECT:
3. Before proceeding to examine the arguments of the two
sides in greater detail it would be useful to take a look at the
project and to put at one place the basic facts concerning it that
are admitted or at any rate undeniable.
i.
The project is sited at sector 95, Naida. According
E
F
to the applicants, at the site of the project previously
there used to be five parks on the Yamuna front,
namely, Mansarovar, Nandan Kanan, Children's
Park, Smriti Van and Navagraha, opposite Sectors
G
14A, 15A and 16A, Naida.
ii.
The project site, on its western side, lies in very
close proximity to the Okhla Bird Sanctuary. The bird
sanctuary was formed as a large water body with
H
800
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R.
A
the adjoining land-mass of the embankment as a
result of the construction of the Okhla Barrage. It falls
partly in Delhi and partly (400 hectares in area) in
the district of Gautam Budh Nagar, U.P. The
administrative control of the area of the Sanctuary
B
is under the Uttar Pradesh Irrigation Department
and its management is with the Uttar Pradesh
Forest Department. The Sanctuary is home to
about 302 species of birds. Accor.ding lo the
Bombay Natural History Society, out of the bird
c
species found here, 2 are critically endangeted, 11
are vulnerable and 7 are nearly threatened. About
50 species are migratory in nature and come here
mainly during the winter months. The annual
population/visit is estimated as under:
D
2006- 2007
24166
2007-2008
17111
2008-2009
21272
This haven for birds was declared a bird sanctuary ("the
Okhla Bird Sanctuary") vide notification dated May 8, 1990
E
issued by the State of Uttar Pradesh under section 18 of
· the Wildlife (Protection) Act, 1972. The project, subject of
the present controversy, is sited in very close proximity to
the Okhla Bird Sanctuary on its eastern side. The
applicants refer to it as adjoining the left afflux bund of the
F
Okhla Bird Sanctuary but to be accurate it lies about 3550 metres away from the outer limit of the Sanctuary.
According to the applicants, the boundary of the project
site is as under:
G
H
NorthSouthEastWestDelhi-UP ONO Toll Road
Not clearly stated
Dadri Road
Okhla Bird Sanctuary, left afflux bund
iii.
The project is spread over an area of 33.43
hectares, equal to 334334.00 square metres of land
I
IN RE: CONSTRUCTION OF PARK AT NOi DA ANAND ARYA, 8'0;1'1
·.!:··,,
TN. GODAVARMAN THIRUMULPAD v. U.0.1. [AFTAB ALAM, J.]
"
surrounded by a boundary wall made of stone., .~
A
· metres in height and 0.3 metres in thiqkness. TJ1'¢
estimated cost of the project is Rupees 685 crores.
iv.
At the site of the project there used to be a tree
cover, thin to high- moderate in density and for
B
clearing the ground for the project six thousand one
hundred and eighty six (6186) trees were cut down
and one hundred ·and seventy nine (179) were ·
"shifted". These trees were of Subabul, Bottle
Brush, Bottle Palm, Morepankhi, Ficus benjamina,
Cassia siamia, Eucalyptus, Fishtail palm, Rubber
Qi
plant, Silver oak, etc.
v.
The project, though insisted upon by the Uttar
Pradesh Government is nothing but a 'recreational
park', involves the construction of dedicatory
D
columns, commemorative plaza, national memorial,
plinth with sculptures, larger than life-size statues on
tall pedestals, large stone tablets with tributary
engravings, pedestrian pathways, service block,
boundary wall, hard landscape, soft landscape, etc.
E .
As initially planned the breakup of the area under
different uses was as under:
802
SUPREME COURT REPORT t, [201 OJ 15 (ADDL ) S C R
A 4
Total area under Soft
Landscape
B
c
D
E
F
G
H
(a)
Area under grass & ·
plantation
(i))
Arce Jnder pl: r1ters
built within paved areas
5 Total area for vehicular
movement with grass pavers
(maintenances, fire path etc.)
1,57.161.79 sq.m 47.01%
6, 181.91 sq.m.
34,850.00 sq.m.
10.42%
vi.
According to the State Government, the work on the
project commenced in January 2008. The
app1:..:;ants filed IA no.1179 before +.he Central
Empowered Committee (l1ereaftei "CEC")
constituted by this Court on March 5, 2009. They
filed IA nos. 2609-2610 of 2010 (presently in hand)
before this Court on April 22, 2009. According to
the State Government, by that time 50% of the
construction work of the project was complete. The
report from the CEC was received in this Court on
September 4, 2009 and on October 9, 2009, this
Court by an interim order restrained the State
Government from carrying on any further
const1·uctions till further orders. By that time,
according to the government, 70-75% of the
construction w0rk of the project was completed.
vii.
In course of hearing of the matter, on a suggestion
made by the Court, the State Government modified
the layout plan increasing the soft/green area from
47% to 65.28% of the total area of the project. The
revised layout plan is as under:
S. No.
DESCRIPTION
EXISTING
MODIFIED
(in sq.
(in sq.
metres + %)
metres + %)
1.
Green Area
157161. 79
218246.51
IN RE: CONSTRUCTION OF PARK AT NOIDAANANDARYA, 893
TN. GODAVARMAN THIRUMULPAD v. U.OJ [AFTABALAM, J]
(47%)
(65.28%)
A
2.
Hard Landscape
129140.80
98544.99
(38.6%)
(29.48%)
a
Boundary Wall
2700.79
2700.79
(0.81%)
(0.81 %)
B
b
Platforms, Plinths,
126440.00
95844.99
Sculpture &
(37.79%)
(29.48%)
Surrounding
Paved Areas
3.
Area for vehicular
34850.00
0.00 (NIL)
c
movement
(10.42~ 11)
4.
Area under ornamental
0.00 (NIL)
6302.00
water feature (may be
(1.88%)
considered part of the
D
Eco Frien.dly Area)
5.
Area under parking with
0.00 (NIL)
4241.00
grass pavers (may be
(1.27%)
considered part of the
Eco Friendly Area)
E
6.
Utilities and Facilities
3500.00
3500.00
(1.05%)
(1.05%)
7.
Memorial Building and
3499.50
3499.50
Toilets
(1.05%)
(1.05%)
'F
8.
Total Area
334334.00
334334.00
(100%)
(100%)
Under the amended plan, around 7300 trees, more than 4
years of age and measuring 8-12 feet in height, belonging to
G
the native species such as Neem, Peepal, Pilkhan, Maulsari,
lmli, Shisham, Mango, Litchi and Belpatra will be planted in the
project area.
4. According to the State Government, the revised plan
that includes planting of trees in such large numbers would not
H
804
SUPREME COURT REPORTS [2010] 15 (ADDL.) S.C.R.
A only restore the tree cover that was in existence at the site
earlier but would make the whole area far better, more beautiful
and environment friendly. The applicants however, would have
none of it. On their behalf it is contended that the whole project
is bad and illegal from every conceivable point of vie'«; .its
s construction was started and sought to be completed at a
breakneck speed in flagrant violation of the laws. According to
the applicants therefore, all the structures at the project site,
complete, semi-complete or under construction must be pulled
down and the project site be restored to its original state.
C THE PROJECT AND SECTION 2 OF THE FC ACT:
5. Mr. Jayant Bhushan, learned senior counsel appearing
for the applicants submitted that over six thousand trees were
admittedly cut down for clearing the area for the construction
D of the project and it was, thus, clearly a case of forest land
being put to use for non-forest purpose in complete violation
of section 2 (ii) of the FC Act.
Section 2 of the FC Act, in so far as relevant for the present,
E provides as follows:
"2.