# HIND BUILDERS ETC v. UNION OF INDIA AND VICE-VERSA

- **Citation:** [1990] 2 S.C.R. 638
- **Court:** Supreme Court of India
- **Decided:** 1990-04-24
- **Case number:** Civil Appeal No. 1280 & 1281 of 1988
- **Bench:** S. Ranganathan, A.M. Ahmadi
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/hind-builders-etc-v-union-of-india-and-vice-versa-10746
- **Pages:** 21

## Headnote

Arbitration: A ward-Error on the face of the award-Clause in
the contract open to two equally plausible interpretations-Legitimate
for Arbitrators to accept one or the other of the available interpretations
and even if the court may think that the other view is preferrable, the
C court will not and should not interfere.
Award-Error on the face of award-Annexure setting out the
award as against various items of claim-Mere fact that statement of
claim refers to various items in the schedule to the contract does not
result in the contract itself being incorporated in the award-No error
D can be found in the award.
IE
Pendente Lite Interest: Power of Arbitrator-Not entitled to
grant pendente lite interest unless reference is made in the course of a
suit-Same powers to grant interest pendente lite as the courts when
matter is referred by the Court.
Certain disputes having arisen between the Union of India and tbe
Contractors in respect of the Contract awarded to the letter for the
execution of certain civil works pertaining to the Metro Railway Project
iu Calcutta, the same were referred for decision to two Arbitrators
appointed by the High Court of Calcutta. The Contractors filed their
f
itemised claim before the Arbitrators for a total sum ofRs.2,05.67.554.
The Arbitrators awarded a sum of Rs.57,47 ,198 to the contractors in_
full and final settlement of all their claims which included a sum of
Rs.6, 76,540 as interest vide item (1). They directed that the award shall
be complied with within sixty days of its publication failing which simple interest @ 11 percent per annum shall accrue thereon (excluding
(; interest amount of Rs.6,76,540) till the date of payment or decree upon
award which ever is earlier. On an application being made to the High
Court for making the Award a rule of the Court, the learned single
judge confirmed the award except that the principal sum awarded was
reduced by Rs.5.20.000 with the direction that the amount so awarded
will carry interest @ l l % per annum from the date of reference till the
H date of the award.
638
--
HIND BUILDERS v. U.0.1.
639
The l."nion of India preferred an appeal to the Division Bench.
which reduced the amount awarded under item (c)(xii) from
-
. Rs.23,96,000 to Rs.2,39,000. Thus the principal amount to be awarded
to the contractors was finally put at Rs.30, 70, 798 and this amount was
directed to carry interest @ 11 % per annum from the date of the reference till the date of the award.
Aggrieved by the order of the Division Bench reducing the
"'--·· amount awarded under item (c)(xii) from Rs.23,96,000 to 2,39,600 the
...,,-
contractors preferred an appeal to this Court. The Union of Indian on
the other hand preferred a cross-appeal praying (i) that interest should
___,-> not be payable on the amount of Rs.30, 70, 798 fixed by the High Court but
only on Rs.23,94,258 left after deducting therefrom the amount of
Rs.6, 76,540 awarded by the Arbitrators in respect of itein No. (LJ and
(ii) that. though the arbitrators had also awarded interest on the princi-
"'T-· - pal sum till the date of payment or decree on award in case payment was
not done within sixty days of the publication of the award. the
contractors should be held entitled to interest upto the date of the award
only and not beyond it because both the learned single judge and the
Division Bench have held so and the contractors have preferred no
appeal therefrom.
Taking up the contractor's appeal first, this Court carrie to the
conclusion that the Division Bench had exceeded its jurisdiction in
interfering with this part of the award and restored the amount
awarded by the arbitrators under item (c)(xii).
Dealing with the appeal of the Union oflndia this Court ruled that
there was really no dispute left about Union of India's first contention
as to what was the correct amount on which interest was payable to the
-;..- - contractors after its findings in the contractor's appeal and placed the
figure at Rs.45.50.658.
Dealing

## Text

_Characters 0–39,996 of 51,060. This is a partial read: ask again with offset=39996 for what follows._

A
B
HIND BUILDERS ETC.
v.
UNION OF INDIA AND VICE-VERSA
APRIL 24, 1990
[S. RANGANATHAN AND A.M. AHMADI, JJ.)
Arbitration: A ward-Error on the face of the award-Clause in
the contract open to two equally plausible interpretations-Legitimate
for Arbitrators to accept one or the other of the available interpretations
and even if the court may think that the other view is preferrable, the
C court will not and should not interfere.
Award-Error on the face of award-Annexure setting out the
award as against various items of claim-Mere fact that statement of
claim refers to various items in the schedule to the contract does not
result in the contract itself being incorporated in the award-No error
D can be found in the award.
IE
Pendente Lite Interest: Power of Arbitrator-Not entitled to
grant pendente lite interest unless reference is made in the course of a
suit-Same powers to grant interest pendente lite as the courts when
matter is referred by the Court.
Certain disputes having arisen between the Union of India and tbe
Contractors in respect of the Contract awarded to the letter for the
execution of certain civil works pertaining to the Metro Railway Project
iu Calcutta, the same were referred for decision to two Arbitrators
appointed by the High Court of Calcutta. The Contractors filed their
f
itemised claim before the Arbitrators for a total sum ofRs.2,05.67.554.
The Arbitrators awarded a sum of Rs.57,47 ,198 to the contractors in_
full and final settlement of all their claims which included a sum of
Rs.6, 76,540 as interest vide item (1). They directed that the award shall
be complied with within sixty days of its publication failing which simple interest @ 11 percent per annum shall accrue thereon (excluding
(; interest amount of Rs.6,76,540) till the date of payment or decree upon
award which ever is earlier. On an application being made to the High
Court for making the Award a rule of the Court, the learned single
judge confirmed the award except that the principal sum awarded was
reduced by Rs.5.20.000 with the direction that the amount so awarded
will carry interest @ l l % per annum from the date of reference till the
H date of the award.
638
--
HIND BUILDERS v. U.0.1.
639
The l."nion of India preferred an appeal to the Division Bench.
which reduced the amount awarded under item (c)(xii) from
-
. Rs.23,96,000 to Rs.2,39,000. Thus the principal amount to be awarded
to the contractors was finally put at Rs.30, 70, 798 and this amount was
directed to carry interest @ 11 % per annum from the date of the reference till the date of the award.
Aggrieved by the order of the Division Bench reducing the
"'--·· amount awarded under item (c)(xii) from Rs.23,96,000 to 2,39,600 the
...,,-
contractors preferred an appeal to this Court. The Union of Indian on
the other hand preferred a cross-appeal praying (i) that interest should
___,-> not be payable on the amount of Rs.30, 70, 798 fixed by the High Court but
only on Rs.23,94,258 left after deducting therefrom the amount of
Rs.6, 76,540 awarded by the Arbitrators in respect of itein No. (LJ and
(ii) that. though the arbitrators had also awarded interest on the princi-
"'T-· - pal sum till the date of payment or decree on award in case payment was
not done within sixty days of the publication of the award. the
contractors should be held entitled to interest upto the date of the award
only and not beyond it because both the learned single judge and the
Division Bench have held so and the contractors have preferred no
appeal therefrom.
Taking up the contractor's appeal first, this Court carrie to the
conclusion that the Division Bench had exceeded its jurisdiction in
interfering with this part of the award and restored the amount
awarded by the arbitrators under item (c)(xii).
Dealing with the appeal of the Union oflndia this Court ruled that
there was really no dispute left about Union of India's first contention
as to what was the correct amount on which interest was payable to the
-;..- - contractors after its findings in the contractor's appeal and placed the
figure at Rs.45.50.658.
Dealing with the second contention as to what was the period with
reference to which interest would be payable to the contractors on the
above amount it was noticed that the arbitrators had allowed interest
from 5. J0.82 (date of termination of contract) to 26.3.84 (date of
award) ·under item (L) and had also allowed interest from the date of the
award. till the date of payment or decree whichever is earlier. The
learned single judge had deleted the interest for the period S. !0.82 to
•
I
6.5.8.' (date of reference) but held that the arbitrators had jurisdiction
to award interest from the date of the reference till the date of award
A
B
c
D
E
F
G
and also post-award interest. As the objection of the Union of India_
H
A
B
c
640
SUPREME COURT REPORTS
[1990) 2 S.C.R.
before the Division Bench in the LPA on the question of interest was only
that the arbitrators had erred in awarding interest from 6.5.1983 to
26.3.1984 the High Court had not decided that the contractors were not
entitled to interest beyond the date of award and therefore this contention of the L nion of India failed and was rejected. The Court.
HELD: The grant of pendente lite interest would be justified only
when reference to arbitration is made in the course of a suit. The
principle indicated is that since a court has, under S. 34 of C.P.C.
power to grant pendente lite interest in a suit, an arbitrator to whom a
reference to arbitration is made in the course of the suit would be
clothed with all the powers of the court including one to grant such
interest. Generally speaking, it would only seem reasonable that the
power to grant interest pendente lite should be treated as ancillary to
the award of damages or compensation which. but for the delay in the
litigation (whether in court or by way of arbitration). the claimant
should have received much earlier. However. though pendente lite
interest has been made available in court proceedings. its extension to
D arbitration law appears to have acquired some technical limitations
resulting in denial of pendente lite interest in most arbitration cases.
Pendent lite interest cannot still be awarded by an Arbitrator appointed
by the parties under a private agreement for which there may be no
justification in equity. Anomalies have arisen because f!'rmerly an
Arbitrator could not be treated as a court to which the code of civil
E procedure applied and because now the Interest act, 1978, while including arbitration proceedings within its ambit, has, apart from a reference to S. 34 omitted to provide specifically for pendente lite interest.
This has been clearly brought out by Chinnappa Reddy, J., in
Abhaduta Jena which outline the principle the learned judge had in
mind for permitting pendente lite interest by arbitrator. Abhaduta Jena
F
has been followed in later cases also and its scope bas been recently explained
in Shanna's Case (1988-4 SCC 353), and the Gujarat Water Supply case
(1989-1 SCC 532) where pendente lite interest was denied. [655H; 656A-F]
Gujarat Water Supply & Sewage Board v. Unique Erectors,
[1989] 1 S.C.C. 532; Finn Madan Lal Roshan Lal Mahajan v.
G Hukumchand Mills Ltd., Indore, [1967) l S.C.R. 105; Allen Berry &
Co. Pvt. Ltd v. Union of India, [1971) 3 S.C.R. 287; N. Chellappan v.
Secretary, Kera/a State Electricity Board & Anr., [1975) l S.C.C. 289;
Hindustan Tea Co. v. K. Shashi Kant Co. & Anr., [1986) Suppl.
S.C.C. 506; Hindustan Steel Works Construction Ltd. v. C. Rajasekhar
Rao, [1987) 4 S.C.C. 93; Sudarsan Trading Co. v. Government of
H Kera/a & Anr .. [1989] 2 S.C.C. 38: M/s. A/ppi Prashad & Sons, Ltd. v.
··-r
HIND BUILDERS v. U.0.1. IRANGANATHAN, J.]
641
Union of India, [1960] 2 S.C.R. 793; Bhagat Trading Co. v. Union of
India, AIR 1984 Delhi 358; Union-of India v, Bakshi Ram, [1957] LIX
P.L.R. 572; Executive Engineer v. Abhaduta Jena, [1988] 1 S.C.C. 418;
Nachiappa v. Subramaniam, [1960] 2 S.C.R. 290; Satinder v. Amrao,
]1961] 3 S.C.R. 676; Union v. Bungo Steel Furniture P. Ltd., [1967] I
S.C.R. 324; Ashok Construction Co. Ltd. v. Union, [1971] 3 S.C.C. 66;
State v. Saith & Skelton P. Ltd., [1972] 3 S.C.R. 233; Food Corpora·
tion of India v. Surendra, Devendra & Mohendra Transport Co.,
[1988] 1 S.C.C. 547 and State of Rajasthan v. Sharma & Co., [1988] 4
S.C.C. 353, referred to.
-~--
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1280
& 1281 of 1988.
From the Judgment and Order dated 21.4.1987 of the Calcutta
~
_ High Court in Appeal from Original Order No. 128 of 1985, Award
r
Case No. 151of1987.
A
B
c
A.K. Sen, Dr. Shankar Ghosh, Ajay K. Jain, Praveen Kumar
D
and Pramod Dayal for the Appellant.
M.K. Banerjee and G.S. Chatterjee for the Respondent.
The Judgment of the Court was delivered by
RANGANATHAN, J. These are cross appeals by Mis. Hind
Builders (hereinafter referred to as 'the contractors') and the Union of
India. from an order of Division Bench of the Calcutta High Court in
an arbitration matter.
E
)--·
The contractors had been awarded a contract for the execution
F
1 of certain civil works in connection with the Metro Railway Project in
t--Calcutta. Certain disputes arose between the Union and the con·
tractors. These disputes were referred for decision to two arbitrators
appointed by the High Court of Calcutta. The arbitrators entered upon
the reference on 27th June. 1983. The contractors had filed a claim
before the arbitrators for a sum of Rs.2,05,67,554. Un 26.3.1984 the
G
arbitrators awarded-a-sum of Rs.57,47,198 to the contractors.
~ The claim of the contractors filed before the arbitrators was an
·
itemised claim in respect of various items of works executed by them.
The body of the award made by the arbitrators reads as follows:
H
"We ..... make and publish our Award, as below:
A
B
c
D
E
F
G
1--1
642
SUPREME COURT REPORTS
[1990) 2 S.C.R.
(i) That the Respondent .......... shall pay ..... the
Contractors a sum of Rs.57,47,198 ..... only in full and
final settlement of all their claims and dues under the
abovementioned contract
agreem~nt. In addition, . the
three Bank Guarantees .......... issued by Vijaya Bank,
Cuttack, on behalf of the contractors, in favour of Metro
Railway, Cuttack, shall be released by the Respondent
Railway, as detailed in the Annexure to this Award.
xxx
xxx
xxx
The Award shall be complied with within 60 (Sixty) days
from the date of publication of this Award, failing which
simple interest @ 11 per cent per annum on the amount of
the Award (excluding interest vide item (1) of the Anne·
xure i.e. Rs.6,76,540) shall accrue till the date of payment
or decree upon Award whichever is earlier."
In the annexure to the award, the arbitrators tabulated the various
items of the claim before them, the amount claimed against each item
and the amount awarded against each item. Ut\der item ( 1) in the
annexure, the arbitrators had awarded an interest of Rs.6,76,540 and
that is why the direction regarding interest by the arbitrators excluded
this amount from the principal amount which was to bear interest. As
stated earlier, the total amount awarded was Rs.57,47, 198 in respect
of items (a) to (q) of the award as against the claim of Rs.2,05,67,554
made by the contractors.
On an application being made to the High Court of Calcutta on
the Original Side for making the award a rule of court, the learned
single Judge sitting on the Original Side confirmed the award except to
the extent of Rs.5,20,000. This is no longer in issue. The learned
Judge. however, concluded his judgment with the following words:
"The principal sum awarded stands reduced by Rs.5,20,000
as mentioned above. The respondent will be entitled to
interest at the rate of 11 per cent per annum from the date
of reference till the date of the award."
The Union of India preferred an appeal from the order of the
learned single Judge. The Division Bench was of the opinion that the
arbitrators were not justified in awarding a sum of Rs.23,96,000 to the
contractors (as against a claim of Rs.42,65,957 made by them) in
respect of item (c)(xii) viz. "cost towards consolidation of earth by
ramming and rolling" and that they could have awarded under the
---
~
~-
-("-
).:: ' '
'"""'
-~
~
..
HIND BUILDERS v. U.0.1. [RANGANATHAN, J.]
643
contract only a sum of Rs.2,39,600 in respect of this item. The amount
awarded to the contractors was thus further reduced by the Division
Bench by a sum of Rs.21,56,400 (Rs.23,96,000-Rs.2.39,600). The
Bench then observed that the principal sum to be awarded to the
'contractors would now stand at Rs.30,70,798 and directed that the
respondent contractor should be entitled to interest at the rate of 11
per cent per annum on the said amount from the date of the reference
till the date of the award.
The contractors have appealed from the order of the Division
Bench being aggrieved by the reduction of the amount awarded under
item lc)(xii) to Rs.2,39,600 from Rs.23,96,000. The Union of India
has preferred an appeal contending principally that, since the principal amount on which the arbitrator awarded interest was not
Rs.57,47,198 but only Rs.50,70,658 (i.e. Rs.57,47,198-Rs.6,76,540),
the contractors would be entitled to interest, after the judgment of the
Division Bench, not on Rs.30,70,798 as held by the Division Bench but
only on Rs.23,94,258. In addition, at the tune of the hearing before us,
counsel for the Union of India raised two further points:
( I) that the Division Bench erred in awarding interest to
the contractors from the date of the reference till the date of the
award.
(2) That though the arbitrators had also awarded interest
on the principal sum till the date of payment, the contractors
should now be held entitled to interest only upto the date of the
award because the learned single Judge and the Division Bench
have he Id so and the contractors have preferred no appeal
therefrom.
Taking up the contractor's appeal first, the point raised falls
within a very narrow compass and turns on the interpretation of item
No. - . 09 of the annexure to the contract containing the schedule of
rates. This item reads as follows.
Item Brief description
l"o. of work
2
Approximate
Qty.
3
Unit of
payment
4
Rate of
payment in
"words" &
"figures"
Rs.
P.
5
A
B
c
D
E
F
G
H
644
.. ". '
- '.A
4.09
\\ '
\
B
c
)
D' ..
E
- - "-
,_
F
G
,_,_ . .--- ';.,,
" .
:, \
'
/
; .
, · .• ',
. ·' ·, i-.
·.
I
·,
,
\-
', ·' '
· SUPREME COURT REPORTS
\ .
[ 1990] 2 S.C.R.
(~) Earthwork in open excava-2,35,000
10
tion for forming garbage
Cubic
Cubic
tanks in all kinds and
metres • . metres ·
conditions of soils upto -
depths varying from 0 to 3
3 metreli from the existing
ground level and disposing
of the spoils so as to
raise land_ required for
- piling work, to fill up the
existing low lying areas
and ponds, to form embankments for roads,'ett::of the
Car Depot complex includ-
. - ing spreading in layers,
·breaking clods, levelling,
- dressing, all lifts/descents
ahd all leads etc. complete -
Note:
No extra payments Wu! be
made if wet excavation is
met with or for baling/
pumping out of water of all
- · -sorts includiilg ralli water.
(b) Extraoveritein (a) abo~e, l,3s;ooo -10
for consolidation of the ' Cubic
Cubic
filled up areas or some of metres - - metres
the top layers of the filled
·up areas or road embank-
. · ment portions by watering
. - and ramming/rolling as
directed.
Rs.180
(Rupees one
hundred
_>Jeighty
n:·ly).
Rs.20
(Rupees
Twenty
only).
In respect of these items the statement of claim filed on behalf of the
- · • contractonvas in the following terms:
-
H
_-- ---
(b) Eanhwork in excavation measured but not paid in full:
. That unde( agreement item No. 4.09 (a) the claimants as -
rer instructions, specifications and agreement excavated
..
-
-·•
-,,,,,
~-
t
--·
t
HIND BUILDERS .v. U.0.1. [RANGANATHAN, J.]
645
earthwork in open excavation for forming garbage tanks in
all kinds of soil for a quantity of 2, 15,000 Cum and thereafter the contract was rescinded against which reduced
quantity has been measured provisionally upto 17th CC bill
for 2,09,523 Cum measured on 24.5.82 and as per the said
measurements the claimants are yet to be paid for a
quantity of 5,477 Cum over and above the payments
already made upto 17th CC. The claimants claim payment
for 5,477 Cum of excavation @ Rs.18 per each Cum.
amounting to Rs.98,586.UO.
CLAIM AMOUNT ... Rs.98,586.00
(c)(xii) Cost towards consolidation of earth by ramming
and rolling:
That as per agreement item No. 4.09(b) the claimants are
required to fill up the low lying areas etc., as specified
under General Conditions of the Contract at para 3.05 with
the excavated spoils obtained out of earthwork in excavation under agreement item No. 4.09(a). The payment for
earthwork in open excavation for work executed under
agreement item No. 4.09(a) is to be made on sectional
_measurements calculated by level sections. The excavated
earth obtained from garbage excavation, a quantity of
2, 15,000 Cum as per provisions made in agreement item
No. 4.09(b) was consolidated in different areas as per
instructions and approved plan. The claimants claim payment for this quantity of consolidation at Rs.20 per·cum
i.e. Rs.2 extra over Rs.18 per Cum as specified in agreement item No. 4.09(a) & (b), amounting to Rs.43,00,000.oO
against which payment has been made in CC bills for
reduced quantity and amount of Rs.34,043.00. The claimants claim payment for the balance amount of
Rs.42,65,957.00 not paid for.
A
B
c
D
E
F
CLAIM AMOUNT Rs.42,65,957.00
G
In other words, the contractors claimed payment at the rate of Rs.18
-
Iii'' -!?er cubic metre in respect of the excavation work done by them under
item No. 4.09(a). Again, in respect of the same quantity.of 2,15,000
cubic metres, the contractors made a claim at Rs.20 per cubic metre as
the amount payable to them in respect of the consolidation of H
A
B
c
646
SUPREME COURT REPOR"S
[ 1990] 2 S.C.R.
excavated earth by ramming and rolling. The Division Bench was of . ._
the view.that under item No. 4.09(b), the contractors were entitled to
an additional payment of Rs.2 only, since the contractors had already
been paid at the rate of Rs.18 per cubic metre in respect of the excavation done by them. The extra charges for ramming and rolling were
payable only at the rate of Rs.2 per cubic metre instead of Rs.20 per
cubic metre. The Division Bench accordingly scaled down the amount
awarded by the arbitrator m this regard to !/10th of the amount
awarded by him.
It is submitted on behalf of the contractors that the rate payable
for the work under item 4.09(b) of the contract was not at all in <;l}spute ~.
between the parties at any stage. The Union had not raised any plea in
this regard in its reply to the contractors' claim, in the objections to the
award filed in the High Court or in the arguments before the learned
Single Judge. Clearly, the Division Bench travelled beyond the limits· 47
permissible for the interference with an award by a court of law in
reducing the amount awarded on this account. It is pointed out that the
D award itself is a non-speaking award. The award does not refer to the
terms of the contract or incorporate the details of the claims made by
the contractors. Though it is true that the arbitrators awarded a sum of
Rs.23,96,000 against item (c)(xii), they have not given reasons therefore. The award neither shows that the amount has been worked out at
'
...
the rate of Rs.20 per cubic metre nor does it show the quantity in );_. ~
E respect of which the amount has been worked out. There is no reference to the terms of the contract or to item No. 4.09, clause (a) or (b).
No reasons have been given by the arbitrators for determining that a
sum of Rs.23,96,000 has to be paid to the contractors under item
(c)(xii). It is therefore submitted that there was no error app.arent on
the face of the record. Learned counsel vehemently contended that it ~
F
is now settled law that an award cannot be said to suffer from a manifest error unless the error appears on the face of the award or of some -{-
document incorporated in the award. Reference is made to the decisions of this Court in the following cases: Firm Madan/a/ Roshan/al
Mahajan v. Hukumchand Mills Ltd:, Indore, [1967) 1 SCR 105; Allen
Berry & Co. Pvt. Ltd. v. Union of India, [1971) 3 SCR 287; N. ChellapG pan v. Secretary, Kera/a State Electricity Board & Anr., [1975) 1 SCC
289; Hindustan Tea Co. v. K. Shashi Kant Co. & Anr., [1986) Suppl. ·
SCC 506; Hindustan Steel Works Construction Ltd. v. C. Rajasekhar 1..........,
Rao, [1987] 4 SCC 93 and Sudarsan Trading Co. v. Government of---
Kerala & Anr., [1989) 2 SCC 38. According to the contractors, what
the Division Bench has done is to give its own interpretation to item
H Nos. 4.09(a) & (b) of the contract, to read an erroneous interpretation
HIND BUILDERS v. U.0.1. {RANGANATHAN, J.]
647
/
of the said item into the award made by the arbitrators and to substitute its opinfon in the place of that given by the arbitrators. Thus, it is
~-submitted, runs quite contrary to the principles enunciated in the
above decisions and should, therefore, be set aside.
-
On the other hand, Shri Milon Banerjee, learned counsel for the
Union of India submitted that the award is really a speaking award in
so far as it does specify the amount granted in respect of each item of
,-t-' daim. He submitted that the present case falls within the principle
·
enunciated in Mis Alopi Prashad & Sons, Ltd. v. Union of India,
[1960] 2 S.C.R. 793, which has been taken note of in the case of "4./s
-r Sudarsan Trading Co. v. Government of Kera/a & Anr., [1989] 2 SCC
38 at p. 54 that an award which overlooks or ignores the terms of the
contract is bad. He also made a reference to the decision of the Delhi
High Court in Bhagat Trading Co. v. Union, AIR 1984 Delhi 358 in
·'""r~ this context. He also referred to a decision of the Punjab High Court in
Union of India v. Bakshi Ram, [ 1957] LIX P .L.R. 572, holding that
"when there are pleadings in an arbitration and they are specifically
referred to in the award so that it cannot be understood without reference to them, then those pleadings are incorporated in the award and
they must be included in the consideration whether there is any error
apparent on the face of the award" and that "if a lump sum is awarded
by an arbitrator and it appears on the face of the award or is proved by
• ~'extrinsic evidence that in arriving at the lump sum matters were taken
~ ·
into account which the arbitrator had no jurisdiction to consider, the
award is bad." The contention of Shri Banerjee is that the annexure to
the award clearly incorporates the statement of claim made by the
contractors. Since in turn the statement of claim refers to the clauses of
~
the contract, the contract should also have been treated as incor-
·~ porated in the award. It is also apparent on the face of the award,
insofar as it relates to item (c)(xii), that the arbitrators have awarded
payment at Rs.20 per cubic metres under item 4.09(b) whereas it must
1 obviously be at Rs.2 per cubic metre. According to the learned
counsel, the decisions relied upon by him clearly show that an award
which ignores or overlooks the express terms of a contract suffers from
an error apparent on the face of the record and can be set aside by this
Court. He submitted that the award, read with the annexure, brings
out the reasoning of the arbitrators and that an error therein can be
rectified by the court. The arbitrators had no power to travel beyond
-
~the authority of the contract and, in order to determine whether they
had exceeded lheir authority, the contract can be looked into by the
court. In support of this contention, the learned counsel also referred
to a passage at p. 421 in the Law of Arbitration by Bachawat (Second
Edition).
A
B
c
D,
E
F
G
H
A
B
648
SUPREME COURT REPORTS
[ 1990) 2 S.C.R.
We have considered the respective contentions of the parties and
we are of the opinion that the Division Bench erred in setting aside the
award insofar as it relate to the sum of Rs.25,96,000. Though the
annexure sets out the award of the arbitrators as against various items
of claims, the mere enumeration of the heads of claims cannot be
equated to an incorporation of the statement of claim by the contractors into the award. At any rate, the award does not relate the
claims to the various clauses of the contract and the mere fact that the
statement of claim refers to various items in the schedule to the contract does not result in the contract itself being incorporated as part
of the award. No error can be found in the award unless one reads into
it first the statement of claim and then the relevant clauses of the
contract. But this cannot be done unless these documents are treated
-
C as incorporated in the award. This cannot be done. That apart even if
the contract can be read into the award, we doubt whether this case
can be treated as one of an error on the face of the award. All that the
-~
award has st~ted is that for the extra work involved in ramming and
rolling, the contractors were to be paid a sum of Rs.23,96,000. The
o award does not mention how this amount is arrived at. There is no
mention of the quantity in respect of which this is awarded nor the rate
at which the payment has been calculated. It is, however, pointed out
that contractors had claimed payment at the rate of Rs.20 per cubic
metres in respect of 2,15,000 cubic metres and that, even if it is
assumed that the ramming and rolling had been done in respect of the
):__ •
E entire volume of 2, 15,000 cubic metres, the contractors could have, on
a proper construction of the contract, been awarded only a sum of
Rs.4,30,000 and nothing more. Obviously, the award is calculated at
Rs.20 per cubic metres in respect of 1,19,800 cubic metre. It is clear,
says counsel for the Union, that the volume of the item for which
payment has to be made has been cut down but the amount has been
~
F calculated at Rs.20 per cubic metre which exceeds the amount of Rs.2
stipulated in the contract and this is erroneous on the face of it.
-{-
We are afraid that, in putting forward this contention, the
respondents are really trying to analyse the reasons of the arbitrator
for-making the award under this head when no such reasons have been
G stated in this award. In fact, it does not necessarily follow that the
payment has been directed at the rate of Rs .20 per cubic metre in
respect of 1,19,800 cubic metre. Theoretically, it could have been
awarded, in respect of the entire volume of 2,15,000 cubic metre, at
the rate of Rs.11 and odd per cubic metre. It is, howevr, clear that the
payment has been granted at a rate in excess of Rs.2 per cubic metre.
H We shall, however, take it that the arbitrators have awarded at the rate
_,,.__ -
-
HIND BUILDERS v. U.0.1. [RANGANATI!AN, J.]
649
of Rs.20 per cubic metre in respect of this item of work for, as pointed
out by Dr. Ghosh, the Union of India had never put forward the case
either before the arbitrator or before the learned single Judge that the
contractors were not entitled to payment at the rate of Rs.20 per cubic
metre as claimed and it was before the Division Bench for the first time
that a question arose that the payment for the item should be at Rs.2
and not Rs.20 per cubic metre. Whether the payment should be made
at the rate of Rs.20 per cubic metre or at Rs.2 per cubic metre will
depend upon a proper interpretation of the contract. It is argued that
the main item of work viz. excavation and distribution of the
excavated work has been paid for under item No. 4.09(a) and that item
4.09{b) envisages an additional payment of Rs.2 per cubic metre if the
excavated soil, instead of being loosely distributed, is rammed and
rolled by applying some pressure. This seems, prima facie, a plausible
interpretation of clause 4.09{b ). But we cannot assume, in the absence
of any evidence or expert knowledge, that the ramming and rolling was
not an independent, heavy or cumbersome piece of work and merely
involved a minor addition to the work under item 4.09(a). On the
other hand, in the grounds of appeal filed by the contractors it is
contended:
"The High Court failed to appreciate that the process of
ramming and rolling is a very expensive specialised process
as it has to be done layer by layer not exceeding six inches
A
B
c
D
at a time and requires watering, breaking of clods and use
E
of specialised road rollers, bulldozers and other equipment. The work of ramming and rolling is much more
expensive than that of earth excavation provided for in
item 4.09 (a). The High Court further failed to appreciate
tha_t in its reply to the statement of claim of the petitioner,
the respondent No. 1 had not disputed that the rate applicF
able for ramming and rolling was Rs.20 per cubic metre.
The respondent No. 1 had only raised a dispute with regard
to the quantity of the ramming and rolling done by the
petitioner. The High Court misinterpreted the contract and
erred in reducing the award for ramming and rolling by
erroneously applying the rate of Rs.2 per cubic metre."
G
This may be right or wrong but this is also a plausible view. Unfortu-
-
-.i.._ nately, this was an aspect not urged before, or considered by, the
arbitrators. There was no evidence before the arbitrators or material
adduced before the Court as' to the nature of these operations. It is
difficult to say, by merely reading the terms of contract that the
H
A
B
c
650
SUPREME COURT REPORTS
[1990) 2 S.C.R.
arbitrators have erroneously interpreted the tenns of the contract. It is
not without significance that the departmental officers did not dispute
the rate of the claim. Equally, the arbitrators were experienced
engineers and would not have passed, what is now said to be, an
astounding claim without thought. It is difficult to assume that all these
persons have overlooked that the contractor had already been paid at
Rs.18 under item 4.09(a) especiallv when it is so stated on the face of
the claim. This, therefore, is not a case where the arbitrators can be said
to have ignored or overlooked a tenn of the contract; on the contrary,
they have acted upon a particular interpretation of certain clauses of
the contract on which two views are possible. This case certainly cannot be brought under the principle that the arbitrators have ex facie
exceeded the authority or jurisdiction conferred on them by the contract. At worst, what can be said is that they may have committed an
error in deciding the issue referred to them but the error is not apparent on the face of the award even if the contract is read as part of it
both because the arbitrators have not given their reasoning and
because the view taken by them of the relevant tenns of the contract
D cannot be said to be clearly erroneous. In a matter on which the
contract is open to two eqully plausible interpretations, it is legitimate
for the arbitrators to accepr one or the other of the available interpretations and, even if the Court may think that the other view is preferable, the Court will not and should not interfere. This view is too well
E
settled to need any reference to any precedent other than Sudershan
Trading Co's case referred to earlier. That is why we think that this
case does not fall within the principle referred to by Shri Banerjee and
that Dr. Ghosh is right in his submission that the Division Bench
exceeded its jurisdiction in interfering with this part of the award.
Turning now to the appeal of the Union of India, there is really
F
no dispute about the first contention regarding the amount on which
-/..
G
'H
interest is payable to the contractors. The correct computation should
stand as follows in the light of our findings in the contractors' appeal:
-I_Compensation awarded
by arbitrator
Less : Interest element
therein [item ( 1) I
Net principal amount
awarded
Rs.
57,47, 198
6,76,540
50,70,658
-
' j
HIND BUILDERS v. U.0.1. [RANGANATI!AN, J.]
651
Less : Amount deleted
by learned Single Judge
5,20,000
45,50,650
The contractors will be entitled to interest on this amount.
A
B
What is the period with reference to which interest would be
payable on the above amount? The arbitrators had allowed interest on
the amount awarded by them from 5.10.82 to 26.3.84 under item (1)
and had also allowed interest from the date of the award till the date of C
payment or decree, whichever is earlier. Of this, the learned Single
Judge had deleted the interest for the period 5.10.82 to 6.5.83 and
whaf<remains is the award of interest from 6.5.83 till the date of payment. There are two disputes as to this._ The first objection raised on
behalf of the Union is that the contractors will not be entitled to any
D
interest for the period from the date of reference to arbitration
(6.5.1983) till the date of the award (26.3.1984). On behalf of the
contractors, Dr Ghosh refutes this contention. He relies upon the
decision of this Court in Executive Engineer v. Abhaduta Jena .. [1988]
1 sec 418 and contends that, in all cases where, as in this case,
arbitrators are appointed by Court and disputes referred to them for
E
arbitration, pendente lite interest can and should be awarded by the
arbitrator. He points out that, though initially in Seth Thawardas' case
[ 1955] 2 SCR 48 some doubts were raised abl'ut-the competence of the
arbitrator to award interest, this Court has subsequently consistently
held that an arbitrator can do this: vide, Nachiappa v. Subramaniam,
[ 1960] 2 SCR 209; Satinder v. Amrao, [1961] 3 SCR 676; Firm MadanF
Jal v. Hukamchand Mills Ltd., [1967] 1SCR105; Union v. Bungo Steel
Furniture P. Ltd., [ 1967] 1 SCR 324; Ashok Constructon Co. Ltd. v.
Union, [ 1971] 3 SCC 66 and State v. Saith & Skelton P. Ltd., [ 1972] 3
SCR 233. After referring to these and other cases, Chinnappa Reddy,
J. in Abhadutalena, (supra) summed up the position thus:
"15. As a result of the discussion of the various cases, we
see that Bengal Nagpur Railway Co. Ltd. v. Ruttanji Ranjit,
65 IA 66; Union of India v. West Punjab Factories, [ 1966] 1
SCR 580 and Union of India v. Watkins & Co., AIR 1966
SC 275 were cases of award of interest not by an arbitrator,
G.
but by the court. It was laid down in those three cases that
H
652
A
B
c
D
E
F
G
H
SUPREME COURT REPORTS
[ 1990] 2 S.C.R.
interest could not be awarded for the period prior to the
suit in the absence oi an agreement for the payment of
interest or any usage of trade having the force of law or any
provision of the substantive law entitling the plaintiff to
recover interest. Interest could ·also be awarded by the
court under the Interest Act if the amount claimed was a
sum certain payable at a certain time by virtue of a written
instrument. In regard to pendente lite interest, the provisions of the Civil Procedure Code governed the same.
16. The question of award of interest by an arbitrator was
considered in the remaining cases to which we have referred earlier. Nachiappa Chettiar v. Subramaniam Chettiar,
[1960] 2 SCR 209; Satinder Singh v. Amrao Singh, [196 ll 3
SCR 676; Firm Madan/a/ Roshanlal Mahajan v. Hukumchand Mills Ltd., [ 1967] 1 SCR 105; Union of India v.
Bungo Steel Furniture Pvt. Ltd., I 1967] I SCR 324; Ashok
Construction Co. v. Union of India, [1971] 3 S.C.C. 66 and
State of Madhya Pradesh v. Mis. Saith & Skelton Pvt. Ltd.,
[ 1972] 3 SCR 233 were all cases in which the reference to
arbitration was made by the court, of all the disputes in the
suit. It was held that the arbitrator must be assumed in
those circumstances to have the same power to award
interest as the court. It was on that basis that the award of
pendente lite interest was made on the principle of Section
34 Civil Procedure Code in Nachiappa Chettiar v. Subramaniam Mills Ltd., (>upra); Firm Madan/a/ Roshanla/
Mahajan v. Hukumchand Mills Ltd., (supra); Union of
India v. Bungo Furniture Pvt. Lid., (supra) and State of
Madhya Pradesh v. Mis Saith & Skelton Pvt. Ltd., (supra).
In regard to interest prior to the suit, it was held in these
cases that since the Interest Act, 1839, was not applicable,
interest could be awarded if there was an agreement to pay
interest or a usage of trade having the force of law or any
other provision of substantive law entitling the claimant to
recover interest. Illustrations of the provisions of substantive law under which the arbitrator could award interest
were also given in some of the cases. It was said, for
instance, where an owner was deprived of his property, the
right to receive interest took the place of the right to retain
possession, and the owner of immovable property who lost
possession of it was, therefore, entitled to claim interest in
the place of right to retain possession. It was further said
(
_.,. __
-
HIND BUILDERS v. U.0.1. [RANGANATHAN, l.]
653
that it would be so whether possession of immovable property was taken away by private treaty or by compulsory
acquisition. Another instance where interest could be
awarded was under. Section 61(2) of the Sale of Goods Act
which provided for the award of interest to the seller or the
buyer, as the case may be, under the circumstances
specified in that section.
xxx
xxx
xxx
18. While this is the position in cases which arose prior to
the coming into force of the Interest Act, 1978, in cases
arising after the coming into force of the Act, the position
now is that though the award of pendente lite interest is still
governed by the same principles, the award of interest
prior to the suit is now governed by the Interest Act, 1978.
Under the Interest Act, 1978, an arbitrator is by definition,
a court and may now award interest· in all the cases to which
the Interest Act applies."
Sri Milon Banerjee, appearing for the Union of India, however,
contends that the above principle is applicable only in cases where an
arbitrator is appointed on intervention of comt as contemplated in
Chapter IV of the Arbitration Act. It is only in these cases that the
arbitration proceedings can be considered to be a continuation of the
court proceedings, empowering the arbitrator to do all that the court
could do. For, even in cases arising after the Interest Act, 1978, the
award of pendente lite interest can only be in terms of the provisions of
s. 34 of the Code of Civil Procedure and this cannot be invoked. in
cases of arbitration except in cases falling under Chapter IV merely on
the ground that the appointment of the arbitrator is made under S. 8,
12 or 20 of the said Act. Counsel submits that Chinnappa Reddy, J.
has pointed out in Abhadhuta Jena's case [ [1988] 1 SCC at pp. 434-5 I
that in all cases whether arising before or after the Interest Act, the
claimants would not be entitled to interest from the date of reference
to the date of the award for the simple reason that "the arbitrator is
A
B
c
D
E
F
not a court nor were the references to arbitration made in the course of
G
suits". It is this principle that has been reiterated in Food Corporation
of India v. Surendra, Devendra & Mohendra Transport Co., [1988] 1
3
. ...._ SCC 547 (at pp. 554 et seq) and Gujarat Water Supply & Sewage Board
v. Unique Erectors, [1989] 1SCC532.
There is force in the contention urged by Sri Banerjee. There are
H
A
B
c
D
E
F .
G
H
654
SUPREME COURT REPORTS
(1990] 2 S.C.R.
passages ih Abhaduta Jena which indicate that the grant of pendente
lite interest would be justified only when the reference to arbitration is
made in the course of a suit: vide, the last sentence on p. 428, the first
sentence on p. 429, the emphasis added in the extracts from earlier
judgments on pp. 430-1, and the summings up at p. 433 and 435. The
principle indicated in these passages apparently is that since a Court
has, under s. 34, of the C.P.C., power to grant pendente lite interest in
a suit, an arbitrator to whom a reference to arbitration is made in the
course of the suit would be clothed with all the powers of the Court
including the one to grant such interest.