# LOTUS LINE (P) LTD v. THE STATE OF MAHARASHTRA

- **Citation:** [1965] 2 S.C.R. 699
- **Court:** Supreme Court of India
- **Decided:** 1965-01-07
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/lotus-line-p-ltd-v-the-state-of-maharashtra-3435
- **Pages:** 6

## Headnote

A
LOTUS LINE (P) LTD.
v.
THE STATE OF MAHARASHTRA
January 7, 1965
699'
B [P. B. GAJENDRAGADKAR, C.J., K. N. WANCHOO, s. M. SIKRI, JJ.]
Damages-Measure of-whether party complaining of wrong to property entitled to restitution-<Jr to restoration of property damaged to
original condition.
A vessel owned by the appellant, caused damage to a jetty. The respondent state prepared an estimate of Rs. 16,400 as the cost of special
C
repain for the damage done.
Sometime thereafter,
emergent
repairr
costing Rs. 2783/ - were undertaken by the respondent state to make the
jetty workable and later some minor repairs costing about Rs. 1223/-
were further carried out.
The appellant having refused to pay for tho
damage done, the respondent state filed a suit claiming all the three above
mentioned amounts and interest thereon.
The trial court found that the damage done was attributable to tho
D
negligence of the appellant, but as regards the quantum of damages. it
came to !be conclusion that the claim for Rs. 16,400/- was really for
reconstruction of the whole damaged area, so that the respondent state
was in fact seeking restitution and not compensation for !be damage d~ne.
The trial court refused to give such restitution and held that the expenditure in respect of emergent and minor repairs had put the jetty in working
order and therefore gave a decree of Rs.
3671/ 12/ 6 which was
th<>
E
r
G
H
amount actually spent by the state in making these repairs.
In appeal, the High Court was of the view that the Wednesbury Corporation's Case, [1907] 1 K.B. 78, laid down the general rule in such cases,
which was, to require the party in the wrong to make compensation and
not restitution; but that this rule was subject to the exception that wher<>
the party complaining of a wrong to property was a corporation or a
trust<>e charged with the maintenance of a highway or other public work,
the wrong-doer was bound to make restitution. The High Court therefore
allowed the appeal modified the decree of tho trial court by awardLg a
aum of Rs. 19,038/ 8/ - plus interest.
HELD : The Wednesbury Corporation's case did not lay down the
proposition in the form •lated by the High Court. The true measur< of
compensation was held in that case to be the cost of restoration.
Th<>
p<>rsan to whom a wrong was done was entitled to full compensation for
restoring the thing damaged to its original condition, but this did not
mean complete reconstruction irrespective of the damage done. (702 l:l-D,
B-F, G]
The evidence in this case showed that the amount of Rs. 16,400/-
was needed to carry out necessary repairs to restore the jetty to i!' original
condition and not that the amount was for complete reconstruction of the
jetty i~pective of the damage done to it.
As this amount would ha e
restored the jetty to its original condition, there was no reason to al'ow
anything to the respondent state on accunt of emergent repairs or for
any other expenditure. (703 B-D, G]
CML APPELLATE JURISDICTION: Civil Appeal No. 810 of
1962.
700
SUPREME
COURT
REPORTS
(1965] 2 S.C.R.
Appeal from the judgment and decree dated October 1, 1959,
A
of the Bombay High Court in First Appeal No. 697 of 1955.
Purushottam Tricumdas, I. B. Dadachan;i, 0. C. Mathur and
Ravinder Narain, for the appellant.
T. V. R. Tatachari, and R. N. Sachthey, for the respondent.

## Text

A
LOTUS LINE (P) LTD.
v.
THE STATE OF MAHARASHTRA
January 7, 1965
699'
B [P. B. GAJENDRAGADKAR, C.J., K. N. WANCHOO, s. M. SIKRI, JJ.]
Damages-Measure of-whether party complaining of wrong to property entitled to restitution-<Jr to restoration of property damaged to
original condition.
A vessel owned by the appellant, caused damage to a jetty. The respondent state prepared an estimate of Rs. 16,400 as the cost of special
C
repain for the damage done.
Sometime thereafter,
emergent
repairr
costing Rs. 2783/ - were undertaken by the respondent state to make the
jetty workable and later some minor repairs costing about Rs. 1223/-
were further carried out.
The appellant having refused to pay for tho
damage done, the respondent state filed a suit claiming all the three above
mentioned amounts and interest thereon.
The trial court found that the damage done was attributable to tho
D
negligence of the appellant, but as regards the quantum of damages. it
came to !be conclusion that the claim for Rs. 16,400/- was really for
reconstruction of the whole damaged area, so that the respondent state
was in fact seeking restitution and not compensation for !be damage d~ne.
The trial court refused to give such restitution and held that the expenditure in respect of emergent and minor repairs had put the jetty in working
order and therefore gave a decree of Rs.
3671/ 12/ 6 which was
th<>
E
r
G
H
amount actually spent by the state in making these repairs.
In appeal, the High Court was of the view that the Wednesbury Corporation's Case, [1907] 1 K.B. 78, laid down the general rule in such cases,
which was, to require the party in the wrong to make compensation and
not restitution; but that this rule was subject to the exception that wher<>
the party complaining of a wrong to property was a corporation or a
trust<>e charged with the maintenance of a highway or other public work,
the wrong-doer was bound to make restitution. The High Court therefore
allowed the appeal modified the decree of tho trial court by awardLg a
aum of Rs. 19,038/ 8/ - plus interest.
HELD : The Wednesbury Corporation's case did not lay down the
proposition in the form •lated by the High Court. The true measur< of
compensation was held in that case to be the cost of restoration.
Th<>
p<>rsan to whom a wrong was done was entitled to full compensation for
restoring the thing damaged to its original condition, but this did not
mean complete reconstruction irrespective of the damage done. (702 l:l-D,
B-F, G]
The evidence in this case showed that the amount of Rs. 16,400/-
was needed to carry out necessary repairs to restore the jetty to i!' original
condition and not that the amount was for complete reconstruction of the
jetty i~pective of the damage done to it.
As this amount would ha e
restored the jetty to its original condition, there was no reason to al'ow
anything to the respondent state on accunt of emergent repairs or for
any other expenditure. (703 B-D, G]
CML APPELLATE JURISDICTION: Civil Appeal No. 810 of
1962.
700
SUPREME
COURT
REPORTS
(1965] 2 S.C.R.
Appeal from the judgment and decree dated October 1, 1959,
A
of the Bombay High Court in First Appeal No. 697 of 1955.
Purushottam Tricumdas, I. B. Dadachan;i, 0. C. Mathur and
Ravinder Narain, for the appellant.
T. V. R. Tatachari, and R. N. Sachthey, for the respondent.
The Judgment of the Court was delivered by
B
Wanchoo, J.
This appeal on a certificate granted by the
Bombay High Court arises out of a suit brought by the State of
Bombay (respondent) against the appellant for recovery of
Rs. 24,979 /2/ 4. The facts which led to the filing of the suit
C
are not now in dispute as they have been concurrently found
by the two courts below and may be briefly narrated. On April
27, 1948, at about midday, the vessel Padam belonging to the
appellant arrived in the Dharamtar creek carrying a cargo of 3500
bags of manure )Veighing about 250 tons and laid anchor alongD
side Dharamtar jetty lying on the Pen side of the creek on the
Pen-Khopoli road.
The Dharamtar jetty is meant for small
vessels bringillg passengers and luggage crossing the creek and
so the peon on duty there requested the master of the ship to
remove the vessel into the creek and to unload the cargo with the
help of small boats.
The master of the ship agreed to do so. But
E
when he tried to move the vessel away from the jetty, she actually
came on top of it due to the force of the ebb tide and got stuck
there. The incident was reported by the peon to his superior
officer who directed the peon to inform the master to refloat the
vessel at night when there was high tide.
The master did so at
about 3 A.M.
The consequence of the ~essel getting on the jetty
F
and the attempt to take it off was serious damage to the jetty,
which was broken. This damage was found on the next day, i.e.,
April 28, 1948. An estimate for special repairs of the damage
done was prepared soon after and was submitted on May 12,
1948 to the Executive Engineer.
The appellant was asked by
telegram un May 5, 1948 to send a representative in order that
G
an estimate of the cost of special repairs for the damage done
might be prepared.
The appellant replied by telegran1 that a
representative would be sent but no one appeared on behalf of
the appellant when the estimate was prepared.
This estimate
was for Rs. 16,400/-. It appears that sometime tliereafter emergent repairs costing Rs. 2,783/- were undertaken to make the
H
jetty workable.
Later, some minor repairs costing about
Rs. 1,223/- were further
carried out.
In the meantime the
LOTUS LINE v. STATE (Wanchoo, /.)
701
A appellant was asked again and again to pay for the damage done.
The appellant refused to do so and therefore the State of Bombay
filed the suit claiming the three sums mentioned above for special
repairs, emergent repairs and minor repairs and also 6 per centum
per annum interest thereon.
B
The trial court found that the above facts had been established
by the evidence led before it and that the appellant was liable
to make go<id the loss as it arose on account of the negligence
of the master of the ship.
It then came to consider the quantum
of damages.
It came
to the conclusion
that the claim for
Rs. 16,400/- was really for reconstruction of the whole damaged
C area and this showed that the respondent-State wanted restitution
and not compensation for the damage done. ]t, however, refused
to give restitution on the ground that it had not been proved that
special repairs to the extent of Rs. 16,400/-
were
absolutely
necessary for the damaged portion of the jetty. The trial court
also inspected the jetty and was of the opinion that the emergent
D and minor repairs that had been made had put the jetty in order
and traffic was going on as usual. Further it took into account
the statement of a witness that a bridge was being constructed
over the Dharamtar creek and was likely to be completed within
two years. It, therefore, finally gave a decree for Rs. 3,671/12/6
which had been actually spent by the State in making the repairs.
J: The rest of the claim was dismissed.
This led to an .appeal by the State before the High Court, and
the only question which the High Court had to decide was the
quantum of damages.
In that connection the High Court relied
on The Mayor of Wednesbury Corporation v. The Lodge Holes
r
Colliery Co. Limited(') and held that that case laid down that the
general rule was to require the party in the wrong to make compensation and not restitution; but there was an exception to this rule
and that exception was where the party complaining of a wrong to
property was a corporation or a trustee charged with the mainti>-
nance of a highway or other public work. In such a case the wrongG
doer was bound to make restitution because a corporation or a
trustee who was charged with the maintenance of public works was
bound to restore the property in its or his possession to its original
condition. On this view, the High Court allowed the appeal and
modified the decree of the trial court by awarding Rs. 19,038/8/-
and interest at 6 per centum from the date of suit till realisation.
H
Th& present appeal on a certificate granted by . the High Court
challenges the principle laid down by the High Court, and it is
(1) [19,7] I K. B. 78.
L4Sup/6S-11
702
SUPREME
COURT
REPORTS
[1965] 2 s.c.R..
urged that no such principle has been laid in Wednesbury CorpoA
ration's case(1) and that that case was overruled in Lodge Holes
Colliery Co. Ltd. v. Mayor of Wednesbury( 2).
The only question that arises for decision before us therefore
is the quantum of damages in a· case like this. Apart from the
fact that the case relied upon by the High Court has been partly
overruled in the Lodge Holes Colliery Co. Limited's case(2 ), we
have been unable to find therein the principle which the High Court
has deduced from the case of Wednesbury Corporation(1 ). LearB
ned counsel for the respondent,State is also unable to point out any
passage in the judgment of Cozens-Hardy L.J. which lays down
C
the proposition in the form in which the High Court has stated
it. As we read that case it lays down that the rights of a corporation in such a case are at least as high as that of a private owner,
with this addition that a. trustee or corporation cannot renounce
those rights in the same way as a private owner could. The true
measure . of compensation was held in that case to be the cost · D
of restoration and compensation must give full restoration. l'n
that case the dispute really was whether the road which had subsided should be raised to the same level as it was before or whether
the purpose would be served even though it was not raised to the
same level and a dip was allowed therein. The Appeal Court held
that the Corporation was entitled to full compensation for restoring
E
the road to its original condition. It may be mentioned that this
view was not accepted in full by the House of Lords. It seems
to us however that the _yiew taken in Wednesbury Corporation'&
case(1 ) that a person to whom a wrong is done is entitled to full
compensation for restoring the thing damaged to its original condition may be accepted as the true measure of damages in a case of r
this kind. This applies equally to a private person as to a corpo-
. ration or trustee. Therefore, the respondent-State was entitled to
compensation to the extent necessary to restore· the jetty to its
·<>riginal condition. If this is to be called restitution, the corporation as well as a private person would be entitled to it. But if
by restitution, the High Court meant complete reconstruction irresG
pective of the damage done, then neither a private person nor a
corporation or a trustee is entitled to complete reconstruction
irrespective of the damage done.
This being the principle, the respondent-State would be entitled
to such cost as would restore the jetty to its original condition. It H
is in that connection that an estimate was submitted for special
(!) (1907) I K. B. 78.
2. (1908] A. C. 323.
LOTUS LINB V. STATE (Wanchoo, /.)
703
A repairs to the jetty as early as May 12, 1948.
The appellant was
invited to send a representative to assess the cost of repairing the
damage done but it neglected to do so.
There is nothing dn the
record to show hat the special repairs to the tune of Rs. 16,400 fwere for complete reconstruction of the jetty irrespective of the
damage done to it.
Nothing has been brought out in the evidence
B of Patel who prepared the estimate and of the Sub Divisional
Officer who supervjsed it to show that the estimate of Rs. 16,400/-
was for complete reconstruction of the jetty irrespective of the
damage done.
The covering letter to the estimate shows that it
was an estimate for special repairs to the jetty. If the appellant
neglected to send a representative to be present to assess the
C
damage and the cost of repairing it, it cannot now come forward
and say that the amount of Rs. 16,400 /- would not be the proper
sllll) required for restoring the jetty to its original condition. All
that has been brought out in the evidence of the two witnesses
referred to above is that it could not be said whether any part of
D the dismantled material was fit for re-use; nor were the witnesses
able to say what the dismantled material would have fetched if
sold.
Barring these two matters all that the evidence shows is
that the amount of Rs. 16,400/- was ·needed to carry out the
special . repairs, which would have presumably restored the jetty
to its original condition.
Therefore the respondent-State would
E be entitled to this. sum of Rs. 16,400/-. But in view of the fact
that some of the material might have been fit for re-use and some
of the material might have been resold and thus fetched some price,
we would deduct the item of Rs. 1,600/ (from the total of
Rs. 16,400/-) which refers to "dismantling tlie damaged portion
and removing the debris outside including sorting materials and
F stacking the useful one to a suitable site etc." The rest of the
estimate amounting to Rs. 14,800/- is clearly for restoration of
the jetty to its original condition and the respondent-State would
be entitled to that amount.
We may add however that there is no reason to allow anything
G to the respondent-State in the shape of emergent repairs. It has
been shown that Rs. 14,800/- would have restored the jetty to its
originlil condition and that is all that the State is entitled to have.
How it decided to spend that sum, whether at one time or at
different times in the shape of emergent repairs or minor repairs,
has no bearing on ·the quantum of compensation necessary for
H
restoring the jetty to its original condition. For the same reason
the fact that the State might not have "spent the whole amount by
the time the trial court came to give its judgment or the fact that
704
SUPRBMB COURT REPORTS
[1965] 2 S.C.R.
a bridge was going up and the jetty might not thereafter be required
A.
has no relevance on the question of damage done on April 27,
1948, though the former may affect the date from which interest
may be awarded. We are therefore of opinion that the respondent-State is entitled to Rs. 14,800/- as compensation for the
damage done to the jetty to put it back in its original condition. 1l
We therefore partly allow the appeal and reduce the amount
decreed to Rs. 14,800/-. This sum will carry interest at the rate
of Rs. 6/- per centum from the date of decree of the trial court
till realisation as ordered by the High Court. The appellant will
pay proportionate costs throughout to. the respondent-State.
Appeal partly allowed.