# M/S. SOMA ISOLUX NH ONE TOLLWAY PRIVATE LIMITED v. HARISH KUMAR PURI & ORS

- **Citation:** [2014] 14 S.C.R. 617
- **Court:** Supreme Court of India
- **Decided:** 2014-04-17
- **Case number:** Civil Appeal No. 4611 of 2014
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/m-s-soma-isolux-nh-one-tollway-private-limited-v-harish-kumar-puri-ors-29759
- **Pages:** 60

## Headnote

[2014] 14 S.C.R. 617
M/S. SOMA ISOLUX NH ONE TOLLWAY
PRIVATE LIMITED
v.
HARISH KUMAR PURI & ORS.
(Civil Appeal No. 4611 of 2014)
APRIL 17, 2014
\[GYAN SUDHA MISRA AND
PINAKI CHANDRA GHOSE, JJ.]
A
Constitution of India :
C
Art. 226 -
Writ petition in public interest - National
. Highway (NH1) project -
Contract between appellantcompany and NHAI to construct certain portion of Highway
on built, operate, trade (BOT) mode- Investment to be made
by appellant by income generated from toll collection - In
D
other writ petitions the issue of shifting of Toll Plaza
adjudicated and attained finality- Matter again agitated and,
while deciding continuance or otherwise of an interim order
in a challenge to show cause notice, High Court in effect
cancelling the agreement and saddling the appellantE
contractor and its director with huge amounts of fine - Held:
When Division Bencf];of High Court had already settled the
dispute by a speaking judgment permitting the shifting of Toll
· Plaza, no legal authority was left with the Chairman, NHAI to
issue a letter questioning the shifting - High Court also by F
impugned order, ignored the fact that controversy regarding
shifting of Toll Plaza although had been set at rest by a
judicial verdict of High Court, NHAI still insisted that it cannot
permit the shifting when its I.E. (Independent Engineer) had
earlier approved of the same and accepted by NHAI in view G
of specific clause in the agreement to that effect- High Court
has further failed to visualise that the matter with which it was
seized was limited to the question as to whether the order by
which the show cause notice issued by the NHAI to appellant
concessionaire-company was ordered to be kept in abeyance H
617
..
' 618
SUPREME COURT REPORTS
[2014] 14S.C.R.
A
was fit to be vacated or not and went into the question whether .
the appellant-company was fit to continue with:th~ project
whichhad been handed over to it by NHAI by virtue ofa valid
agreement executed between the parties, primarily on the
ground of delay without really entering into the cause of delay
B and considering the plea at whose instance the contr13ctua/
obligations had been violated- Impugned directions of High
Court are set aside, and appellant is permitted to restore the
construction of the balance stretch/area of H/ghway project- ·
. NHAI is directed to permit the appellant to shift the Toll Plaza ·
· c as indicated in judgment - Directions .given to appellant to
·· complete entire construction of Highway and report the
. progress toNHAI.
Res judicata:
Constructive res-judicata -
Issue of shifting Toll Plaza
D decided by single Judge of High Court and decision affirmed
in Letters Patent appeal - Matter attained finality ·:C.. Issue
raised again - Held: A question or an issue which has been ·
raised earlier before High Court, adjudicated and on which a
final judgment/order was delivered, cannot be allowed to be
E raised for the second time as that would be clearly barred by
"the principle of constructive res judicata -
Therefore, the
issue of shifting of Toll Plaza which fi~lly was dismissed was
not permissible to be referred for arbitration once on the
judicial side permission to shift the Toll Plaza was permitted
F by High Court-Arbitration.
Contract:
Terms of contract- Held: In case of statutory contract,
the terms of the statute prevail over the terms of the contract
G - But, once the contract is signed by the contracting parties,
obviously the contract having assumed the legal authority of
a concluded contract would govern the terms and conditions
of the contract between the parties who have ~igned it and
thereafter it would be binding on the contracting partie~: .··.
-, ·_, ·.
H
•
MIS. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
619
HARISH KUMAR PURI
A writ petition was filed before the High Court as a A
Public Interest Litigation with the object of improving
management of traffic on G.T. Road (National Highway
No. 1) in the interest of the commuters and the public at
l

## Text

_Characters 0–39,673 of 126,522. This is a partial read: ask again with offset=39673 for what follows._

[2014] 14 S.C.R. 617
M/S. SOMA ISOLUX NH ONE TOLLWAY
PRIVATE LIMITED
v.
HARISH KUMAR PURI & ORS.
(Civil Appeal No. 4611 of 2014)
APRIL 17, 2014
\[GYAN SUDHA MISRA AND
PINAKI CHANDRA GHOSE, JJ.]
A
Constitution of India :
C
Art. 226 -
Writ petition in public interest - National
. Highway (NH1) project -
Contract between appellantcompany and NHAI to construct certain portion of Highway
on built, operate, trade (BOT) mode- Investment to be made
by appellant by income generated from toll collection - In
D
other writ petitions the issue of shifting of Toll Plaza
adjudicated and attained finality- Matter again agitated and,
while deciding continuance or otherwise of an interim order
in a challenge to show cause notice, High Court in effect
cancelling the agreement and saddling the appellantE
contractor and its director with huge amounts of fine - Held:
When Division Bencf];of High Court had already settled the
dispute by a speaking judgment permitting the shifting of Toll
· Plaza, no legal authority was left with the Chairman, NHAI to
issue a letter questioning the shifting - High Court also by F
impugned order, ignored the fact that controversy regarding
shifting of Toll Plaza although had been set at rest by a
judicial verdict of High Court, NHAI still insisted that it cannot
permit the shifting when its I.E. (Independent Engineer) had
earlier approved of the same and accepted by NHAI in view G
of specific clause in the agreement to that effect- High Court
has further failed to visualise that the matter with which it was
seized was limited to the question as to whether the order by
which the show cause notice issued by the NHAI to appellant
concessionaire-company was ordered to be kept in abeyance H
617
..
' 618
SUPREME COURT REPORTS
[2014] 14S.C.R.
A
was fit to be vacated or not and went into the question whether .
the appellant-company was fit to continue with:th~ project
whichhad been handed over to it by NHAI by virtue ofa valid
agreement executed between the parties, primarily on the
ground of delay without really entering into the cause of delay
B and considering the plea at whose instance the contr13ctua/
obligations had been violated- Impugned directions of High
Court are set aside, and appellant is permitted to restore the
construction of the balance stretch/area of H/ghway project- ·
. NHAI is directed to permit the appellant to shift the Toll Plaza ·
· c as indicated in judgment - Directions .given to appellant to
·· complete entire construction of Highway and report the
. progress toNHAI.
Res judicata:
Constructive res-judicata -
Issue of shifting Toll Plaza
D decided by single Judge of High Court and decision affirmed
in Letters Patent appeal - Matter attained finality ·:C.. Issue
raised again - Held: A question or an issue which has been ·
raised earlier before High Court, adjudicated and on which a
final judgment/order was delivered, cannot be allowed to be
E raised for the second time as that would be clearly barred by
"the principle of constructive res judicata -
Therefore, the
issue of shifting of Toll Plaza which fi~lly was dismissed was
not permissible to be referred for arbitration once on the
judicial side permission to shift the Toll Plaza was permitted
F by High Court-Arbitration.
Contract:
Terms of contract- Held: In case of statutory contract,
the terms of the statute prevail over the terms of the contract
G - But, once the contract is signed by the contracting parties,
obviously the contract having assumed the legal authority of
a concluded contract would govern the terms and conditions
of the contract between the parties who have ~igned it and
thereafter it would be binding on the contracting partie~: .··.
-, ·_, ·.
H
•
MIS. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
619
HARISH KUMAR PURI
A writ petition was filed before the High Court as a A
Public Interest Litigation with the object of improving
management of traffic on G.T. Road (National Highway
No. 1) in the interest of the commuters and the public at
large. The writ petitioner had lost his son in a road
accident in 1996 on the said highway. During the B
. pendency of the writ petition, a concession agreement
was entered into between the appellant company and
respondent authorities to construct, operate and
maintain a project namely 6 laning of a part of NH 1 from
KM 96.00 to KM 387.100. As regards financing and C
investment to Highway Project, the agreement envisaged
that the project would be on the basis of build, operate,.
trade (BOT), mode, meaning thereby, all investment in
the project were to be made by the appellant-company
by the income generated from toll collection and no o
amount was to be invested/received from the National
Highway Authority of India (NHAI). On the contrary, the
. appellant-company as per the agreement offered to pay ·
to the respondent/NHAI premium equal to 20.14% of the
total collection of the toll for the first year and this E
premium was to be increased by 1% every subsequent
year. With regard to relocation of toll from KM 213 to
211.550 as approved by NHAI, CWP no. 21332/2011 was
dismissed by the High Courton 25.1.2012. Further CWP.
no. 23971/2011 challenging the relocation of toll plaza at F
211 KM - 212 KM was dismissed by the High Court on
1.5.2012. The Letters PatentAppeal was also dismissed
by the High Court on 6.12.2012.
However, despite the approval granted by the NHAI
and the order passed by the High Court, the appellant G
was prevented from commencing tolling at located Toll
Plaza at 211 KM and 110 KM and this, as claimed by the
appellant, resulted in loss of substantial fund that could
have been utilized for the construction of the project
H
62{)
SUPREME COURT REPORTS
[2014] 14 S.C.R.
A When .the appellant had competed 71% of the project
arid the matter of relocation of toll plaza was again
agitated before the High court in C.M no 3301/2013 arising
outofCWP no.13848/1998, the High Court saddled the
appellant-company with a fine of :Rs. 60 crores and Rs. 7
B crores to be paid by the appellant-company and its
director, respectively, by the impugned order and
directed respondent no. 6, NHAI, to proceed in the matter
'forthwith and take possession of the Highway Project
and ensure that collection of toll is deposited in a
c separate account. The.High Court further directed that
the entire matter relating to the contract, the completion
of the work of the Highway, collection of tolls without
existence of 6 lanes be enquired into and a report in that
regard be submitted. It was further directed that the
o Chairman, NHAI would be personally responsible for.
ensuring that the work of 6 laning of the Highway was
completed. Aggrieved, the concessionaire-company,
filed the appeal.
E
F
Allowing the appeal the court
HELD: 1.1 It is an admitted position that the
schedules and annexures to the Concession Agreement
form its integral part and would be in full force and effect
as expressly .set out in the body of the Concession
Agreement. [Para 36][651-G]
1.2 In Letters Patent Appeal No. 170/2012, the
Division Bench of the High Court had approved of the
orders of the single Judge permitting shifting of Toll
Plaza, and dismissed the LPA upholding the order of the
G single Judge allowing shifting the Toll Plaza in view of
the clause in the Concession Agreement and the opinion
of the Independent Engineer and the NHAI. Neither the
NHAI nor the PIL petitioners challenged the judgment
and order of the High Court permitting to shift the Toll
H
MIS. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
621
HARISH KUMAR PURI ·
Plaza. Thus, the controversy regarding shifting of Toll A
Plaza attained finality in view of final adjudication of the
dispute by the High Court. [Para 40][654-F-H; 655-A]
1.3 In fact, it is only on 18.3.2013, when a new
incumbent took over the charge as Chairman of the NHAI
that a letter dated 18.3.2013 was issued wherein the B
proposal of the appellant for relocation of Toll Plaza was
finally rejected stating therein that in principle, approval
dated 9.11.2010 by NHAI was only conditional in nature
and at the most was only recommendatory, ignoring that
the Independent Engineer, earlier had approved of the C
proposal for shifting the Toll Plaza. In fact, the NHAI
seems to be completely oblivious of the fact that when
the Division Bench of the High Court had already settled
the dispute by a speaking judgment and order in CWP
. No.21332/2011, CWP No.23971/2011 and LPA No.170/ D
2012 permitting the shifting, no legal authority was left
with the Chairman, NHAI to issue a letter questioning the
shifting. It is rather strange that NHAI defied the speaking
judgment and order of the High Court in contemptuous
disregard and it is equally strange that the High Court E
also by the impugned order, appears to have ignored
the fact that the controversy regarding shifting of Toll
Plaza although had been set at rest by a judicial verdict
of the High Court, the NHAI still insisted .that it cannot
permit the !?hitting when its Independent Engineer had F
earlier approved of the same and accepted by NHAI in
view of the specific clause in the agreement to that effect
[Para 41][655-E-H; 656-A-D]
2.1 In case of statutory contracts, the terms of the
statute prevail over the terms of the contract. But once G
the contract is signed by the contracting parties
obviously the contract having assumed th~ legal
authority of a concluded contract would govern the
terms and conditions of the contract between the parties
H
622
SUPREME COURT REPORTS
[2014) 14 S.C.R.
A who have signed and thereafter would be binding on
the contracting parties. [Para 43][658-B-D]
· 2.2 The Concession Agreement having been signed ..
by the appellaht-jointventure company and respondent·.
No,6-NHAl,'th~·r,ole of the Union of India to express its .
B view over and above the terms and conditions of the
contract in absence of any statutory violation will not be
allowed to prevail as after execution of the contract, it
c
.D
· can only issue the notification i.n this regard. [Para 44]
[658q-H]
2.3 Since it is the appellant-joint venture company
and respondent No.6-NHAI which alone are the parties
between whom the Concession Agreement has been
signed and the agreement is not even remotely alleged
to be'in violation of some statute ot central Act, the rol~
or the authority of the Union of India to intervene or
contest cannot be allowed as it at the most is a proforma
respondent in this appeal under the prevailing facts and
circumstances. [Para 44][659-8-C]
E
2.4Although the High Court has recorded that it did
not .intend to traverse the contractual obligations and
· liabiliti.es of parties and confined its considerations so
as to see whether public interest require that the interim
order be extended or vacated, it has indeed done. the
same when it directed the NHAI to forthwith take
· F possession of the Highway Project which in effect has.·
nullified the contract and has gone much further by .
directing the NHAI to ensure completion of the project·
which in effect meant that the NHAI would have to invite
fresh tender for construction of the balance 29% area of
G the Highway Project as admittedly NHAI itself cannot
undertake the construction. This clearly is nothing short
of cancellation of the Concession Agreement and it is a
misnomer when the High Court observed that it was not
H traversing the contractual obligation ignoring its
M/S. SOMAISOLUX NH ONE TOLLWAY PVT. LTD. v
623
HARISH KUMAR PURI
devastating effect on the contracting party who had A
completed 71% of the project arid had at least the right ·
to explain whether the delay in concluding the project
· . ·could entirely be attributed to the appellant or atleast ·
some of it could be fastened on the NHAI whi~h had gone
to the extent of not only backing out of its earlier opinion B · ·
but also· conveniently shut its eyes that it was vi9lating
.the order of the High Court which had earlier upheld the.
right of th~ appellant to shift the toll plaza. [Para 49l
·. [663-E-H; .664·A-B] .
. · 2.5 Tile High Court was not justified in recording C · ·· ·
. that the delay had been caused merely at the instanc.e .. ·
of t],11La·~.P~llant,130 as. to pass a blanket order for
.
trahsferting tile execution ofthe projectto NHAI contrary
t9 JiW'. ·~ai:eementwherein it was permissible. {or the
appe)l~ntt9 ~hift th~ Tol(Plazas and the sanie had also D ·.·
. !),en approved by the High Court. [Para 50][664-C-D]
. , .... 2.6 The High Court has further Jailed to visualise
that the matter.with which it was seized was limited to
ttie·question as t9 w'hether the.order by which the show .
cause notice issued by the NHAI to the appellant E
concessionaire"company was ordered to be. kept in
abeyance was fit to be vacated or not as the High Court .
was essentially adjudicating the question.whether the
NHAI could at all issue a show cause notice to the
appellant~company to terminate the contract and while · F
the High Court did.not enter into the question whether .
the said order was fit to be continued or was fit to be
vacated, went into the question wheth~r the appellantcompany was fit to .:ontinue with'the project which had
been han<:(ed over to the appellant by the NHAI by virtue G
of a valid agreement executed between the parties
primarily on the ground of delay without really entering
into the cause of delay and considering the plea at whose
instance the contractual obligations had been violated.
[Para 50][664-D-G]
H
624
SUPREME COURT REPORTS
[2014] 14 S.C.R.
A
2. 7 In fact, even at this stage before this Court, the
respondent NHAI has merely contended that the Toll
Point/Toll Plaza should not be allowed to be shifted from
the point determined earlier and has been asserting that
the Toll Plaza should not be shifted from 146 KM to 110
B KM. In fact, NHAI neither before the High Court nor before
·this C~urt even remotely has contended that the contract
should be nullified. (Para 51](664-G-H; 665-A].
3.1 In any event, the question of termination of the
Concession Agreement without adjudication could not
C arise at all when the High Court was merely considering
the application seeking vacation of the stay order to the
show cause notice issued by the NHAI. In case, it had·
rejected the application, the show cause notice issued
by the.NHAI to the appellant could have proceeded. But
D the High Court terminated the contract itself for all
practical purposes without expr-essly using the
expression "termination" when it directed the NHAI to
take over the project from the appellant- company and
continue with the project and complete it, nullifying the
E contra.ct in its entirety. [Para 52](665-F-H; 666-A]
3.2 It is significant to note that the appellant
admittedly. has completed 71 per cent of the 291 KM
stretch and barely 29 per cent is yet to be construc.ted
which is enmeshed in litigation over the question as to
F whether the Toll Plaza should be permitted to·be shifted
or not. This aspect had not been gone into by the High
Court clearly missing that this question had been raised
in the PIL before the High Court wherein the NHAI and
others were a party wherein the appellant had been
G permitted to shift the toll plaza. In spite of the dispute
having been settled NHAI did not permit the appellantcompany to shift the Toll Plazas, although it had failed
to prefer any appeal against the judgment and order
H
M/S. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
625
HARISH KUMAR PURI
passed by the High Court in CWP No.21332/2011 and A
LPA No.170/2012 challenging such permission.
{Para 54]{666-E-F; 667-B-C]
3.3 However, while nullifying the contract on the
ground of delay, the dispute regarding shifting of Toll
Plaza, which was clearly the only contentious issue for B
not completing the project, could not have been given a
go bye or ignored in any manner by the High Court while
taking an undertaking from the appellant and thereafter
cancelling the Concession Agreement itself when it
admittedly did not traverse the terms and conditions of C
the Agreement. [Para 56][667-G-H; 668-A-B]
3.4 Besides, a question or an issue which had been
raised earlier before the High Court, adjudicated and on
which a final judpment/order was delivered, cannot be 0
allowed to be raised for the second time as that would
be clearly barred by the principle of constructive res
judicata. Therefore, the issue of shifting of Toll Plaza
which finally was dismissed was not permissible to be
referred for arbitration once on the judicial side
permission to shift the Toll Plaza was permitted by the E
High Court by its judgment and order passed in CWP
No.21332/2011 and LPA No.170/2012 which had settled
the issue regarding shifting of Toll Plaza. [Para 57]
{668-B-C; E-F]
F
3.5 In fact, it needs to be highlighted that in terms
of Article 48.1 of the Concession.Agreement, liberty has
1
been granted to the appellant to decide the locations of
Toll Plaza in consultation with the I.E. and the same was
finally approved by the I.E. who conveyed his approval G
to the change of location as proposed by the appellant
and, therefore, the same cannot be allowed. to be rea9itated despite confirmation of the same by the High
Court by its judgment and order passed in the writ
H
626
SUPREME COURT REPORTS
(2014] 14 S.C.R.
A petitions and the LPA against ,Which no appeal was
preferred either by the NHAI or the PIL petitioner or any
other res.pondent. [Para 58][669-B-D]
·
3.6 Thus, the stand of the NHAI appears to be clearly
illegal and arbitrary and a clear case of an afterthought
B taken in the instant proceedings before this Court, as
the N.HAI ad idem was in complete agreement with the .
appellant as regards its right for relocation of Toll Plazas.
The same is recorded and clearly reflected in. the
correspondence of various officers of NHAI, minutes of
C meeting, stand of Independent Engineer including its
stand before the High Court and, therefore, the NHAI
cannot be permitted to resile from its stand atthis distant
point of time as the affidavits were filed as early as 2011
which finally upheld the location of the Toll Plazas.
D (Para 59][669-D-F]
.
•
3.7 Moreover, based on, in principle, approvals·
granted by NHAI and its stand, the lenders continued to
di.sburse funds and the appellant continued to invest in
the project on the plea that the implementation of the
E decision to relocate the Toll Plazas would be done after
tht;! decision of the High Cpurt upholding the relocation
of Toll Plazas. It is, therefore;. too late in the day for the
NHAI to take such specious and uritenable plea with a·
view t6 wriggle out of its obligation which cannot be
F permitted by this Court. [Para 59][670-A-C]
.G
H
3.8 It is ·rather chaotic as also jurisdictional error
that in spite of several orders passed by three different.
·co-ordinate Benches of the High.Court on the judicial
side permitting relocation of the Toll Plazas, the dispute ·
did not set at rest and the High Court while dealing with
the Pll has not even taken note of the fact that it w'as
nullifying the Concession Agreement on the ground <if
delay of the project witl:tout entering into the rights and
'
{,
M/S. SOMA ISOLUX NH ONE TOLLWAY PVT LTD. v
627
HARISH KUMAR PURI
obligations of the Concessionaire-appellant and A
respondentNo;6 NHAI ignoring that the NHAI could not
have been permitted to get away from the onus of
delaying the project when it failed to honour its.
contractual obligation. [Para 61][670-F-H; 671cA]
·
3.9 Besides, NHAI is not funding the project in any· B,
manner as the agreement is in the nature of BOT mode
and the appellant cannot generate profit without
undertaking the construction further. It is, therefore,
pertinent to take note of the fact that the project being ill"
BOT mode, all investment in the project has to be made C.
by the appellant and no amount is received from NHAI.
It may further be noted that the agreement between the
appellant and respondent No. 6 NHAI acknowledges and
confirms the role of lending institutions, mainly
nationalized banks as a major significant holder in project D
implementation. All the financing agreement dealing with
the administration occurred between lending institutions
and the petitioner as well as the financial model for the.
project has been submitted with their reven!Je and
approval prior to th~ con:imence~e~t of.the P..':~~cJ:_JJ:ie.J:. ~- .
appellant-Conces51ona1re, -thef-efore;slates lhatlns
committed to the completion of the project asserting that
its endeavour is to complete the six laning works,atthe
earliest since it is not a gainer in any manner ifthe project
is at a standstill and the appellant also would gain only if F
the project is started. [Para 63][671-E-H; 672-A-B] · '
3. fo In course of oral argument before this Court,
NHAI had yielded and did not seriously dis'pute th.e
shifting of Toll Plaza from KM 212 to KM 211 and rig_htly
so as the shifting is hardly at a distance of 1 KM which is G
negligible and the shifting has already taken place.
[Para 64][672-G-H]
· ·
H
628
SUPREME COURT REPORTS
[2014) 14 S.C.R.
A
4.1 The impugned directions of the High Court are
set aside, and the appellant is permitted to restore the
construction of the balance stretch/area of the highway
project. The NHAI is directed to permit the appellant to
shift the Toll Plaza from KM 146 to any point between
B KMs 110 and KMs 117 with concurrence of the NHAI. The
exact point of construction of Toll Plaza between KMs
110 to KMs 117 shall thus be decided by the NHAI
holding mutual consultation with the appellant/
concessionaire in the light of the approval already
c granted by the Independent Engineer in terms of the
Agreement which also had been approved by the High
Court earlier. [Para 66][674-H; 675-A-B]
.
4.2 However, the High Court although by its order
permitted shifting of the Toll•Plaza in dispute to point
D KM 11 o, the distance between KMs 96 where Toll Plaza
of L & T is existing and the proposed toll plaza at-KMs
110 would be at a distance of only 14 KMs which may
not .be in the interest of the commuting public and,
therefore, it is directed that the shifting although may
E not be permitted at KMs 110, it may be allowed to
be shifted at any point
between KMs 110 ·and KMs
117 in consultation and with concurrence of the NHAI. · ·
[Para 66][675-B-D]
--=~4.3 Therefore;"in"order to facilitate and expedite- .. '
F completion of the Highway Project, this Court directs the
respondent NHAI to permit shifting of Toll Plaza from 146
to anywhere between KMs 110 and KMs 117
expeditiously. The appellant thereafter shall forthwith
restart the construction including setting up of Toll Plaza
G at the agreed point and continue with construction of
the remaining area of the Highway Project and shall
complete the entire construction .of the Highway on or
before
31.3.2015 failing which the appellant/
H
0
M/S. SOMA ISO LUX NH ONE TOLLWAY PVT. LTD. v
629
HARISH KUMAR PURI
concessionaire company shall be liable for penal A
consequences to be determined by the NHAI in terms of
the Concession Agreement. [Para 67][675-F-H; 676-A] ·
4.4 The appellant/concessionaire company is
further directed to report/update the progress/
development of the construction to the NHAI referred to B
in the Concession Agreement after every three months
from the date of compliance of the required statutory
notification for shifting of Toll Plaza at the instance of
the NHAI and the Ministry of Road Transport and
Highways/any other competent authority.
However, it C
is made explicitly clear that no dispute shall be allowed
to be raised further by any of the parties before any court
which may impede or slow down the progress of
completion of the Highway Project as this measure most
certainly would not be in the' interest of the Highway D
Project and consequently not in public interest in any
manner. However, the main contesting parties i.e. the
appellant-Concessionaire Company and the NHAI would
be at liberty to seek such other or further direction from
this Court in case there is bona fide heed to resort to E
such an eventuality in regard to the Highway Project
referred to in the Agreement. [Para 68][676-B-E]
Monarch Infrastructure (P) Ltd. v. Commissioner,
Ulhasnagar Municipal Corporation, 2000 (3)
SCR 1159: (2000) 5 SCC 287 - cited.
CASE LAW REERENCE
2000 (3) SCR 1159
cited
para 37 .
CIVILAPPELLATE JURISDICTION: Civil Appeal No(s).
4611 of2014.
From the Judgment and Order dated 27.05.2013 of the
High Court of Punjab & Haryana at Chandigarhin C. W. P. No.
13848 of 1998.
F
G
H
•
630
' SUPREME COURT REPORTS
(2014] 14 S.C.R.
A
Dr.Al;Jhishek Manu Singhvi, Sr.Adv.,Arunabh Chowdhury,
Sumeet Goel, Parthiv K. Goswami, Amit Bhandari, Rahul
Pratap, Vaibhav Tomar, Prashant Kumar, Mis. Ap & J
Chambers, Advs.for the Appellant..
Ms. lndu Malhotra, P. S. Patwalia, Narender Hooda, Sr .. ···
B Advs., Manjit Singh AAG, T. S. Sidhu, Sumit Gupta, Ashish
Suman, Ms. Pallavi Mohan, Ganesh Karnath, Mukesh Kumar,
Ms:Meenakshi Sood, Ms. Tanu Priya Gupta, Prateek Khanna,
Mis. M. V. Kini &Associates, Tushar Bakshi, S. Ranjith Kumar,
Ms. Nupur Chaudhry, Tarjit Singh, Vinay Kuhar, Dr. Monika
C Gusain, Kamal Mohan Gupta, ShadmanAli, Ms. Madhurima
· Mridal,D. S. Mahra; Advs. forthe Respondents.
·
The Judgment of the Court was delivered by
. GYAN SUDHA MISRA, J. 1. Leave granted.
D
2: This appeal by special leave has been filed assailing
the order dated 27.5.2013 passed by the High Court of Punjab
and Haryana at Chandigarh in C.M.No. 330112013 arising out
of CWP No. 1384811998 whereby certain advers.e directions
to be related hereinafter were issued having grave implication
E on the contractual rights of the appellant- Mis. Soma lso.lux NH
One Tollway Pvt. Ltd. (hereinafter referred to as 'the
Concessionaire company') as it was saddled with.a fine of
Rs.60 .crores and Rs.7 crores to be paid by the appellant-·
· Concessionaire Company and its Director respectively which
F were to be deposited with the Registrar General of the High ·
Court within one mon!h of the date of the order. The respondent
No.6 National Highways Authority of India (shortly referred to
as 'the NHAI') was further directed to proceed in the matter
forthwith and take possession of the Highway project and
. G ensure that collection of toll is deposited in a separate account
·and the work of rep.airs of the highway commenced within a
week and the work of construction of highway commenced
and completed within a month thereafter. The High Court further
issued direction that the entire matter relating to the contract,
H the completion of the work of the highway, collection from tolls
M/S. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
631
HARISH KUMAR PURI [GYAN SUDHA MISRA, J.]
without existence of six-lanes be enquired into and a report in A
that regard be placed before the High Court within three
months. It was also made clear that the enquiry shall not be
construed to be an excuse to delay the construction of the
highway. It was further observed that the Chairman, NHAI shall
be personally responsible for ensuring that the work of six~ B
laning of the highway between Panipat and Jullunder. is .·
completed within six months failing which the Chairman, NHAI
would be held personally liable to pay fine similar to the terms
imposed on the Concessionaire Company-respondent No. 7.
The appellant-Concessionaire Company has, therefore, come c
up to this Court challenging the impugned .order passed by ·.
the High Court.
3: The substantial questions of.law of general and public
· ·.. • .·
· imp,ortance that emerge for consideration iri this appeal inter
alia may be crystallised as follows:
.. ~.
·
·
D
Whether: the directions issued by the High.Court
··
.. whiCh ha\/e far reaching consequences against the
petitioner/appellant and which directions by a judicial
fiat, has the effect of nullifying the terms of the.
Concession Agreement dated 09.05.2008 defeating
E
the rights and obligations arising therefrom in a
Public Interest Litigation while exercisingjurisdiction
•
under Article 226 of the Constitution of India is an
act of judicial overreach under the garb of public
interest?.· · ·
·
· ·
. .
F ·
ii
Whether the terms and conditions ofa concluded'
·contract can be nullified by the High Court by issuing
sweeping directions in an ongoing Public lnteresf
Litigation Petition which renders the terrhs and
. ·conditions of the Concession Agreement between G
. the contracting parties redundant, aHhe instan6eand .
initiative of the Court itself when stich directiorishas
· · ' not even been sought by any of the parties•tc:ithe
Public 1.nterei>tPetition?
H
. .
632
SUPREME COURT REPORTS
(2014] 14 S.C.R.
A
iii
Whether a Bench of the High Court which is seized
of a particular dispute would be justified in not taking
note of the final judgment and order passed earlier·
by a co"ordinate Bench settling the said Controversy
in view of which no direction could be issued by the
B
High Court nullifying the contractual rights of the
affected party?
4. In order to appreciate and adjudicate the controversy
involved and to put the matter in proper perspective certain
factual background may be related which disclose that this
C appeal by way of special leave petition has its genesis in a
writ petition bearing CWP No. 13848/1998 which came to be
filed in the High Court of Punjab and Haryana at Chandigarh
as a public interest litigation on 25. 7.1998 by the respondent
No.1 herein Harish Kumar Puri whose son had died in a road
D accident on 14.5.1996 at Pipli Chowk, Kurukshetra due to the
criminal negligence alleged on the part of the traffic police
posted on the said chowk. In the PIL, the respondent No.1 Mr.
Puri prayed for issuance of a writ in the nature of mandamus
directing for enforcement of traffic rules and to maintain the
E
signal system, rumble strips on crossing, first aid units, control
over speeding on G. T. Road National Highway No.1 and a
further writ or direction holding the State functionaries liable
for the criminal negligence on the part of its employees and
saddle it with monetary liability.
F
5. Interestingly, this writ petition which was filed as a PIL
with the laudable object of improving management of traffic
on the highway in the interest of the comr:nuters and the public
at large over the years metamorphosed into a long drawn
litigation alleging breach of contractual obligations between
G the appellant-concessionaire company and the r'espondent
No. 7 NHAI wherein the respondent Union of India as also the
respondent/PIL petitioner in the High Court have jumped into
the fray giving rise to several rounds of litigation. In the process
it affected the very purpose and object for which the writ petition
H
MIS. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
633
HARISH KUMAR PURI [GYAN SUDHA MISRA, J.]
had been filed as also the construction of the Highway for which
A
a concession agreement had been executed between the
· appellant-concessionaire comp.any and the respondent No.6
NHAI by way of a competitive bidding process during pendency
of the PIL as a step towards resolving the issue of management
of traffic.
B
6. While tracing out the background of the matter, bereft
of not so essential factual details, it may be sufficient to state
thatthe Division Bench of the High Court issued notice of motion
on 1.9.1998 in the writ petition (PIL) which came up before the
High Court for consideration from time to time spanning over.· C
several years and finally on 11.4.2002, an order was passed
by the High Court on 11.4.2002 for impleading the Secretary
to the Government of India, Ministry of Road Transport and
Highways, New Delhi when the issue camp up regarding nonopening of the railway bridge near Dera Bassi for the general D
public. Several years thereafter, notice was also issued to the
National Highways Authority of India (NHAI) to appear before
the High Court through its authorized representative as on
9.5.2008 a Concession Agreement had been executed
between NHAI and the appellant-company since the appellant E
succeeded in a competitive bidding process by which it was
granted exclusive rights, license and authority to construct,
operate and maintain its project namely, six-laning of a part of
NH 1 from KM 96.00 to KM 387.100 (approximately 291.10
KM) from Panipat to Jullundur for a period of 15 years. While
F
awarding the contract, the credentials and track record of the
appellant was taken note of which indicated that the appellant
Mis Soma lsolux NH One Tollway Pvt. Ltd. is a joint venture
company with lsolux Corsan Group which is a multinational
company having vast experience of Infrastructure Development G
in various part of the world including Europe, South America,
Nort.h America and Asia and has successfully developed
Highway Projects in various countries including Spain, Mexico,
Brazil, India etc. lsolux Corsan Group is the leading European
Investor in infrastructure in India 'and Mis Soma Enterprise Ltd.
H
634
SUPREME COURT REPORTS
[2014] 14 S.C.R.
A
is a renowned Development Construction firm.and has several
Natiqnal Highway Projects in the past.13 years and have
completed projects ahead of schedule. It has also undertaken
.. and completed projects in other infrastructure sectors like
Irrigation Hydro Power and Railways.
B
7. The Concession Agreement envisaged reciprocal
obligations from various parties including NHAI, the State of
Haryana and the State of Punjab. Under Clause 4.1.2 (a) NHAI
is/was required to provide right of way and the appellantcompany is/was entitled to demand and collect appropriate
C fee commonly known as toll fee from vehicles and persons
liable to pay toll fee for using the national highway. The
. Concession Agreement was drafted as per the model
approved by the Planning Commission of India and the draft
concession was in fact circulated with the RFP (Tender ·
D Document) and, therefore, ne_itherthe appellant-company nor·
the NHAI could have changed the contents of the agreement
·pursuant to the award of contract.
8. In so far as the financing and investment to the Highway
Project is concerned the agreement envisaged that the
E appellantccompany and the NHAI would be on the basis of
Build, Operate, Trade (BOT) mode which enumerated that the
project being in BOT mode, all investment in the project will
have to be made by the appellant-company by the income
generated from toll collection and no amount was to be
F
invested/received from the NHAI. On the contrary, the
appellant-company as per the Agreement, offered to pay to
the respondent/NHAI premium equal to 20.14 per cent of the
total collection of toll for the first year and this premium was to
be increased by one per cent every subsequent year. Based
G on a detailed analysis of the Concession Agreement. the NHAI
thus is not only notfunding any part of the project development
cost. it is receiving a significant portion of the revenue collected
. as premium by way of collection of toll. However allthe amount
collected by way of toll were to be deposited in the ESCROW
H
.
.
M/S, SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
635
HARISH KUMAR PURI [GYAN SUDHAMISRA, J.)
account as a result of which any amount from this account · A
cannotbe withdrawn by the appellant without signature from
the other contracting party i.e. NHAI. It may further be noted
· .. that the agreement between the appellant and respondent/NHAI
. acknowledges and confirms the role of lending institutions,
. mainly nationalised banks as a major significant holder in
B
project implementation. All the financial agreement dealing in
the administration occurred between lending institutions and
the appellant and the financial model for the project had been
submitted regarding revenue and approval prior to the
commencement of the project. Agreement entered into c
between the appellant/company and the NHAI also envisages
·continuous support and co-operation from the respective State
Governments of Punjab and Haryana and the Concession
Agreement as per Article 47.3 requires the execution of
.Tripartite State Support Agreement between NHAI, D
Concessionaire and respective State Governments for which
support agreements were signed by the State of Punjab on
11.9.2009 and the State of Haryana on 16.9.2009. Asper the
agreement six laning was to be retrofitted on the existing fourlane as per standards and specifications which temporarily
E
· was to put the travelling public to some inconvenience. On
8.9.2008, the Division Bench of the High Court which was
seized of the matter passed an order impleading M/s.
Himalayan Expressway Limited as respondent No.7 herein
and on 11.9.2009 the State Support Agreement mentioned
F
hereinbefore was executed between the Governor of the State
of Punjab, NHAI and the appellant-company regarding the
obligations of the Government of Punjab and its continued
support. for grant of certain rights and aut.horities for
mobilization of resources by the appellant-company. The G
agreement visualizes continuous support and co-operation of .
the Government of Punjab.
9. In the meantime, the writ petition/Public Interest
Litigation which was pending in the High Court during pendency
of which the Concession Agreement was executed, continued H
535·.
SUPREME COURT REPORTS
[2014] 14 S.C.R.
A
to be taken up by the High Court and various directions came
to be passed from time to time by the High Court in course of
hearing of the Pl L.
·
10. The High Court thereafter vide order dated 2.1.2012
on an oral request impleaded the appellant-company as a party
B
respondent and issued notice to it on 2.1.2012 to ascertain
the progress of the Highway Project. The appellant-company
responded to the notice and sought time to file its reply.
Thereafter, on 28.1.2012, an affidavit was filed by the Project
Chairman, NHAI, Ambala before the Hig~ Court in the pending
C PIL info[ming the status of Panipat- Juilundur Section of NH 1
stretch from KM 96.000 to KM 387.100 wherein it was stated
that the Concessionaire-appellant company could not achieve
the milestone -II on the specified date due to delay in various
clearance, tree cutting, utility shifting etc. and further stated
D that the scheduled six laning date has been extended to
15.6.2012. In the meantime and in response to the notice, the
appellant also had filed affidavit on 12.3.2012 giving details
of the progress of the construction on the highway as also the
· difficulties and impediments encountered in the construction.
E
11. rhe High Court however refused to consider even
remotely the reasons for the delay in the progress of the
Highway Construction, much less scrutinized it and further failed
to examine or even visualise as to why the .appellant/
concessionaire company, which within a period of three years
F had constructed 71 % of the highway project had suddenly
slowed down for the rest 29% of the project. In the process it
further refused to consider whether there were bonafide
reasons for the delay on the part of the appellant/
concessionaire com pa fl¥ or the delay was on account of the
G impediments created by the NHAI violating the terms and
conditions of the Agreement as also ignored even the reasoned
judicial orders passed earlier by a co-ordinate Bench of the
Punjab and Haryana High Court itself which had permitted the
appellant to shift the toll plaza in view of the terms and conditions
H · in the Agreement which were conveniently ignored by the NHAI
MIS. SOMA ISOLUX NH ONE TOLLWAY PVT. LTD. v
637
HARISH KUMAR PURI [GYAN SUDHArvilSRA, J.]
contrary to the opinion of its own Independent Engineer whose A
opinion in terms of the Agreement was binding on the NHAI
and the same has been upheld by the High Court by several
judgments and orders settling the controversy.