# MIS SIKKIM SUBBA ASSOCIATES v. STATE OF SIKKIM

- **Citation:** [2001] 3 S.C.R. 261
- **Court:** Supreme Court of India
- **Decided:** 2001-05-01
- **Case number:** Civil Appeal Nos. 2789B 2790 of 1997
- **Bench:** Dr. A.S. Anand, R.C. Lahoti, Doraiswamy Raju
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/mis-sikkim-subba-associates-v-state-of-sikkim-17905
- **Pages:** 23

## Headnote

Sikkim High Court (Practice & Procedure) Rules, 1991-Rules 149
and 150-Deletion of Rules retrospectivelr-Difference of opinion between
A
B
two Judges-Order of reference to third Judge-Validity and effect of-Held, C
valid-Retrospective deletion could not per se have the effect of nullifying
or destroying orders passed or acts already performed-Sections 98(2) and
151-C.P.C.
Arbitration Act, 1940-Section 30-Misconduct of Arbitrator-Non- D
application of mind-Recording of findings which is absurd, unreasonable
and irrational-Held, amounts to misconduct of Arbitrator and the award is
vitiated on account of serious errors of law apparent on the face of it.
Respondent-State appointed appellant as organising agent for its
lotteries and later discontinued it due to disputes relating to settlement of E
amounts. The disputes were referred to an Arbitrator under the pro,isions of
the Arbitration Act, 1940. Arbitrator made an award determining the net
amount payable by the respondent to the appellant at Rs. 33.14 crores. Besides,
proportional costs and future interest were also granted to the appellant at
the rate of 12% p.a. on the amount. The damages awarded in favour of the F
appellant was Rs. 37. 75 crores. The State filed an application under Section
30 of the Act before Trial Court to set aside the award of the Arbitrator. The
Tr!al Comi made the award, a tule of Comi by passing a decree in terms of
the award An appeal was fded by the respondent before High Court. The matter
was heard by a Division Bench consisting of two Judges. One Judge set aside
the award of the Arbitrator and allowed the a1>peal of the respondent with costs. , G
Another Judge gave a dissenting judgment and remanded the matter back to
the Arbitrator for fresh determination of quantum of damages. Due to
difference of opinion, the matter was referred to a third Judge .. Before the
matter was heard by the third Judge, appellant filed an application before the
High Court invoking powers under sections 98 and 151 C.P.C. The respondent H
261
262
SUPREME COURT REPORTS
[2001] 3 S.C.R.
A also filed an application questioning the maintainability of the application filed
by the appellant The third Judge dismissed the application of the appellant
and allowed the application of the respondent
In ap11eals before this Com1, the appellant contended that due to
difference of opinion in the judgment of the High Court, the award of the
B Arbitrator should be confirmed under Section 98(2) C.P.C. since Rules 149
and 150 of the Sikkim High Court (Practice & Procedure) Rules, 1991
(Sikkim Rules) were deleted retrospectively with effect from the date of
l!nforcement of the original rules; and that the award of the Arbitrator cannot
be challenged under Section 30 of the Act since the award had been upheld
C by the Trial Court and did not disclose any misconduct of the Arbitrator.
The respondent contended that the proviso to sub-section (2) of Section
98 C.P.C. should be construed \\ith reference to the sanctioned strength alone,
which was only three Judges in Sikkim High Court; that the matter can be
referred to and heard by a third Judge; that Rules 149and150 of the Sikkim
D Rules apply to the case; that the Rule making authority cannot delete a
statutory rule retrospectively through a notification in the absence of a
statutory f>rovision conferring such power; that the Judge of the High Court,
who allowed the a11peal, enumerated in his judgement numerous errors, which
were apparent of the face of the award and substantiated with the materials
on record; and that the Judge of the High Court, who gave a dissenting
E judgment, also found serious infirmities relating to the quantum of damages
awarded by the Arbitrator.
Disposing of the appeals, the Court
HELD: 1.1. Rules 149 & 150 of the Sikkim High Court (Practice &
F Procedure) Rules, 1991 were in force on the date when the Division Bench
exercised their powers and, therefore, the order of reference passed is not
bad in law. Apart from

## Text

_Characters 0–39,959 of 59,404. This is a partial read: ask again with offset=39959 for what follows._

MIS SIKKIM SUBBA ASSOCIATES
v.
STATE OF SIKKIM
MAY 1, 2001
[DR. A.S. ANAND, CJ., R.C. LAHOTI AND
DORAISWAMY RAJU, JJ.]
Sikkim High Court (Practice & Procedure) Rules, 1991-Rules 149
and 150-Deletion of Rules retrospectivelr-Difference of opinion between
A
B
two Judges-Order of reference to third Judge-Validity and effect of-Held, C
valid-Retrospective deletion could not per se have the effect of nullifying
or destroying orders passed or acts already performed-Sections 98(2) and
151-C.P.C.
Arbitration Act, 1940-Section 30-Misconduct of Arbitrator-Non- D
application of mind-Recording of findings which is absurd, unreasonable
and irrational-Held, amounts to misconduct of Arbitrator and the award is
vitiated on account of serious errors of law apparent on the face of it.
Respondent-State appointed appellant as organising agent for its
lotteries and later discontinued it due to disputes relating to settlement of E
amounts. The disputes were referred to an Arbitrator under the pro,isions of
the Arbitration Act, 1940. Arbitrator made an award determining the net
amount payable by the respondent to the appellant at Rs. 33.14 crores. Besides,
proportional costs and future interest were also granted to the appellant at
the rate of 12% p.a. on the amount. The damages awarded in favour of the F
appellant was Rs. 37. 75 crores. The State filed an application under Section
30 of the Act before Trial Court to set aside the award of the Arbitrator. The
Tr!al Comi made the award, a tule of Comi by passing a decree in terms of
the award An appeal was fded by the respondent before High Court. The matter
was heard by a Division Bench consisting of two Judges. One Judge set aside
the award of the Arbitrator and allowed the a1>peal of the respondent with costs. , G
Another Judge gave a dissenting judgment and remanded the matter back to
the Arbitrator for fresh determination of quantum of damages. Due to
difference of opinion, the matter was referred to a third Judge .. Before the
matter was heard by the third Judge, appellant filed an application before the
High Court invoking powers under sections 98 and 151 C.P.C. The respondent H
261
262
SUPREME COURT REPORTS
[2001] 3 S.C.R.
A also filed an application questioning the maintainability of the application filed
by the appellant The third Judge dismissed the application of the appellant
and allowed the application of the respondent
In ap11eals before this Com1, the appellant contended that due to
difference of opinion in the judgment of the High Court, the award of the
B Arbitrator should be confirmed under Section 98(2) C.P.C. since Rules 149
and 150 of the Sikkim High Court (Practice & Procedure) Rules, 1991
(Sikkim Rules) were deleted retrospectively with effect from the date of
l!nforcement of the original rules; and that the award of the Arbitrator cannot
be challenged under Section 30 of the Act since the award had been upheld
C by the Trial Court and did not disclose any misconduct of the Arbitrator.
The respondent contended that the proviso to sub-section (2) of Section
98 C.P.C. should be construed \\ith reference to the sanctioned strength alone,
which was only three Judges in Sikkim High Court; that the matter can be
referred to and heard by a third Judge; that Rules 149and150 of the Sikkim
D Rules apply to the case; that the Rule making authority cannot delete a
statutory rule retrospectively through a notification in the absence of a
statutory f>rovision conferring such power; that the Judge of the High Court,
who allowed the a11peal, enumerated in his judgement numerous errors, which
were apparent of the face of the award and substantiated with the materials
on record; and that the Judge of the High Court, who gave a dissenting
E judgment, also found serious infirmities relating to the quantum of damages
awarded by the Arbitrator.
Disposing of the appeals, the Court
HELD: 1.1. Rules 149 & 150 of the Sikkim High Court (Practice &
F Procedure) Rules, 1991 were in force on the date when the Division Bench
exercised their powers and, therefore, the order of reference passed is not
bad in law. Apart from the axiomatic principle of law that a subordinate
legislation in the form of Rules or Notification could not be made/unmade
retrospectively unless any power in that regard has been specifically
G conferred upon the Rule making Authority, a mere retrospective deletion
could not per se have the effect of nullifying or destroying orders passed or
acts already performed, when such powers were available in the absence of
any specific statutory provision enacted to destroy all such rights already
acquired or obligations and liabilities incurred. [270-C]
H
1.2. The words 'consisting of' in the proviso to sub-section (2) of Section
+
~ -
SIKKIM SUBBA ASSOCIATES v. STATE
263
98 C.P.C. have relevance only to the sanctioned strength. Therefore, taking A
-~
into account the fact that for the time being, there were only two Judges in
position and that the Judges, who constituted the Division Bench, expressed
different views and thought it fit to refer the matter to a third Judge, the matter
should await till the arrival of a third Judge. The amplitude of powers of this
Court under Articles 136 and 142 of the Constitution of India for doing B
complete justice in any cause or matter brought before it cannot be disputed.
[270-E-F]
Tej Kaur & Am: v. Kirpal Singh & Am:, [1995) 5 SCC 119 and Abdul
Latif v. Abdul Samad, AIR (1950) Assam 80, distinguished.
2.1. Courts of Law have a duty and obligation in order to maintain purity c
of standards and preserve full faith and credit as well as to inspire confidence
in alternate dispute redressal method of Arbitration, when on the face of the
Award, it is ·shown to be-based upon a proposition of law which is unsound or
findings recorded which are absurd or so unreasonable and irrational that
no reasonable or right thinking person or authority could have reasonably D
come to such a conclusion on the basis of the materials on record or the
governing position of law to interlere. [274-E-F]
2.2. The award of the Arbi_trator is vitiated on account of several serious
errors of law, ap1>arent on the face of it and such infirmities go to substantiate
the claim of the respondent-State that the Arbitrator had acted arbitrarily :E
and irrationally on a perverse understanding or misreading of the materials
and found to have misdirected himself on the vital issues so as to render the
award to be one in utter disregard oflaw and precedents. Although the award
purports to determine the claims of parties, a careful scrutiny of the same
4.
discloses total non-application of mind to the actual, relevant and vital aspects
and issues in their proper perspectiye. The Arbitrator, who is obliged to apply F
law and adjudicate claims according to law, is found to have thrown to Winds
all such basic and fundamental principles and chosen to award an astronomical
sum as damages without any basis of concrete proof of such damages, as
required in law. The award of an Arbitrator cannot be opposed to law and what
is not permissible in law cannot be granted or approved by Courts merely G
because it was an Arbitrator who granted it The errors, which could be noticed
in the form of obvious and conspicuous mistake of facts vital and essential
aspects and misapplication of law, are found to so extensively and deeply pervade
........
the entire adjudicatory process undertaken by the Arbitrator as to render it
impossible to save the award except at the expense of rendering the ends of
justice as casualty. [281-D-H]
H
264
SUPREME COURT REPORTS
[2001] 3 S.C.R.
A
Champsey Bhara & Company v. Jivraj Ba/loo Spinning & Tfieaving
Company Ltd., AIR (1923) PC 66; Mis Alopi Parshad & Sons Ltd. v. Union of
India, AIR (1960) SC 588; KP Poulose v. State of Kera/a & Am'., AIR (1975)
SC 1259; Mis Chahal Engineering & Construction Company v. Irrigation
Department, Punjab, Sirsa, [1993] 4 SCC 186; Trustees of the Port of Madras
B v. Engineering Construction C01poration Ltd., [1995] 5 SCC 531; Raipur
Development Authority & Ors. v. Mis Chokhamal Contractors & Ors., [1989]
2 SCC 721 CB; The President, Union of India & Am: v. Kalinga Construction
Co. (P) Ltd., AIR (1971) SC 1646; Union of India v. Mis Jain Associates &
Am'., JT (1994) 3 SC 303; Rajasthan State Mines & Minerals Ltd. v. Eastern
Engineering Enterprises & Am:, [1999] 9 SCC 283; U.P. Hotels etc. v. U.P
C State Electricity Board, AIR (1989) SC 268; Puri Construction Pvt. Ltd. v.
D
Union of India, AIR {1989) SC 777 and Mis Sudarsan Trading Co. v. Govt. of
Kera/a, AIR (1989) SC 890, referred to.
Andrews v. Mitchell, {1904-7) All ER 599, referred to.
3.1. The award of the Arbitrator, as affi11ned by the 'Irial Comi is set
aside in so far as it purports to award damages to the tune of Rs. 37. 75 crores
in favour of the appellants, as wholly uncalled for and illegat [282-C-D]
3.2. The various facts adverted to show that, though the initial default
E was committed by the appellants, the respondent-State was also not adhering
strictly to the time schedule and other ~iipulations contained in the agreement
It is not also the case of the State that the appellants have made any undue·
profit or enriched themselves at the exi>ense of the State. Keeping in view all
these practicalities and realities of the situation, on the 1>eculiar facts and
· circumstances of this case, equities have to be properly worked out between
F parties to ensure that no one is allowed to have their pound of flesh un.iustly
against the other. Since this Court has chosen to take up for consideration
the merits of the claims of the respective parties in these appeals filed by the
appellants, in order to do substantial justice between parties in exercise of
its 1>owers under Article 142 of the Constitution of India, it is considered
G appropriate on an overall consideration of the matter, to reject the counterclaim made by the State. [282-F-H; 283-C)
3.3. The challenge to the order of the High Court dated 11.8.96 fails
and shall stand rejected. Consequently, the Award of the Arbitrator, ·as
affirmed by the Trial Court is set aside. The judgment of the High Court
H rendered on 29.9.1995 shall stand modified, accordingly. [283-D]
+
..
SIKKIM SUBBA ASSOCIATES v. STATE [RAJU, J.]
265
M Chelamayya v.M Venkatraman, AIR (1972) SC 1121; Upper Ganges A
·---1._
Valley Electricity Supp~y Co. Ltd. v. UP Electricity Board, [1973] 3 SCR 107
and Union of India v. Mis Jain Associates & Am:, JT (1994) 3 SC 303,
referred to.
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 2789B
2790 of 1997.
From the Judgment and Order dated 14.8. 96 of the Sikkim High Court
in CMA Nos. 11 & 15/96 in F.A. No. 2/94.
B. Sen, A.N. Parekh and Sushil Kumar Jain for the Appellants.
c
V.A. Bobde, N. Ganapathy, Brijender Chahar and Ashok Mathur for the
Respondent.
The Judgment of the Court was delivered by
D
RAJU, J. A skeletal reference to the facts, without much emphasis on
the details of merits of the case, would help to appreciate certain submissions,
at the time of actual consideration of the claims projected before us.
The respondent, State of Sikkim, and the appellant, Mis Sikkim Subba E
Associates (referred throughout as appellants), claimed to be a firm of
Partnership, entered into an agreement on 22.1.1991 under which the appellants
have been appointed as the "organising agents" for its lotteries enumerated
therein subject to the terms and conditions more fully set out therein regulatip.g
•
~
the rights and obligations of the parties. It needs to be kept in view that since F
running of private lotteries would constitute a criminal offence, some of the
States have allowed parties to put on the apparel of the State in return for
a stipulated fee to mobilise funds, in public interest to undertake public works.
Disputes and misunderstanding arose which led to the termination of· the
agreement resulting in the appellants seeking recourse to litigation by getting G
an Arbitrator appointed invoking the powers under Section 8 of the Arbitration
Act, 1940 (hereinafter referred to as the 'Act').
As against the order dated 24.10.1992 of the District Judge, Gangtok
(Sikkim), appointing the sole Arbitrator, the respondent challenged the same
before the High Court by filing an appeal which came to be dismissed on H
266
SUPREME COURT REPORTS
[2001] 3 S.C.R.
A 23.11.1992. The matter was pursued further before this Court in SLP (C) No.26
of 1993 and by a.."l order dated 26.4.1993 the same was, by the agreement of
parties, dismissed subject to the observation that the Arbitrator shall give a
speaking order and, therefore, there was no need to go into the controversy
raised. The appellants filed their statement of claim before the Arbitrator for
B
a sum of Rs. 81, 84, 679.45 with further relief for the refund ofRs.76 lacs, said
to have been realised by the State by encashing two bank guarantees, with
interest at 18% p.a. from 23.9.1992, the date of encashment. The respondent-
" State filed its reply opposing the claims made by the appellants and asserted
a counter claim against the appellants for a sum of Rs. 8,64,81,445 with future
interest and costs. Both parties marked documents and adduced oral evidence.
c Thereupon, the Arbitrator made an Award on 8.2.1994 determining the amount
payable by the State to the appellants at Rs. 37,75,00,000 and the amount
payable by the appellants to the State by way of counter claim at Rs. 4,61,35,242
and after adjusting the amounts due to the State towards its counter claim,
determined the net amount payable to the appellants by the State at Rs.
D
33,13,54,758. Proportionate costs were awarded and future interest was also
granted at the rate of 12% p.a. on the sum of Rs. 33,13,54,758.
Aggrieved, the State filed an application under Section 30 of the Act
to set aside the Award. The District Judge by his decision dated 27.10.94
overruled. tlie objections of the State and made the Award the rule of court
E by passing a decree in terms of the Award. The State challenged the same
before the High Court by filing an appeal under Section 39 of the Act. The
matter was heard in the High Court by a Division Bench consisting of the
learned Chief Justice (Justice S.N. Bhargava) and Justice R. bayal. In a
judgment dated 29.9.1995 the learned Chief Justice agreed with the contentions
•
rais~d on behalf of the State and sustained the challenge made to the Award
)-
F by setting aside the Award as well as the Judgement of the learne~ District
Judge, thereby allowing the appeal with costs. Dayal, J. rendered a separate
dissenting judgment by coming to the ultimate conclusion that the quantum
. of damages arrived at by the Arbitrator suffered an illegality apparent on its
face and, therefore, in his view the matter required to be remitted for
G reconsideration of the matter afresh to the Arbitrator. In view of the above,
the Court passed the following order :-
"There is a difference of opinion between us. Chief Justice has come
to the conclusion that the appeal should be allowed with costs whereas
Justice Dayal has come to the conclusion that the matter may be
H
remitted back to the Arbitrator for determining quantum of damages.
...
SIKKIM SUBBA ASSOCIATES v. STATE [RAJU, J.]
267
As such, the matter may be placed before the Hon'ble Chief Justice/ A
Judge as soon as he assumes charge.
Sd/-
(Ripusudan Dayal)
Judge
29/09/1995
Sd/-
(S.N. Bhargava)
Chief Justice
29/09/1995"
Thereafter, Dayal, J. ceased to be Judge of the Sikkim High Court and
was transferred to the Allahabad High Court and in his place Justice M.
Sengupta assumed office. Though the date for hearing of the matter was fixed
B
by the said learned Judge, on the said date it was mentioned that Sikkim
Subba Associates, the appellants, has filed an application in CMA No.11/96 C
invoking powers under Sections 98 and 151, CPC, opposing the hearing of the
appeal in view of Section 98(2). The State also filed CMA No.15/96 invoking
Sections 11, 98 and 151, CPC, questioning the very maintainability of the
application filed by Sikkim Subba Associates. The said applications though
initially were before Sengupta, J., due to inadvertence came to be listed before D
the new Chief Justice (Justice K.M. Agarwal) and when the learned Chief
Justice asked the counsel as to whether they wanted the case to be made over
to Sengupta, J., both sides "{anted the same to be heard by the Chief Justice
himself. The learned Chief Justice was of the view that the order of reference
made on the judicial side by the Division Bench cannot be upset either on
the administrative side or on the judicial side while hearing the appeal as a E
third Judge pursuant to the order of reference. Consequently, by an order
dated 14.8.96 the application filed by the appellants came to be dismissed and
the one filed by the State came to be allowed to the extent of challenge made
to the maintainability of the application filed by the appellants. These appeals
came to be filed in this Court challenging those orders.
On 3.3.1997 when SLP (C) Nos. 3232-3233 of 1997 came up for hearing, .
this Court (Hon'ble the Chief Justice and Hon'ble Mrs. Justice Sujata V
Manohar) passed the following order, after briefly noticing the circumstances
in which the appeals have been filed :-
"Against the said order of 14.8.96 made by Agarwal Chief Justice, the
F
G
petitioners filed the present Special Leave Petitions. When these
petitions were came up for hearing on the last occasion a technical
objection was raised that the per Court order of 29.9.95 had net been.
challenged by the petitioners and, therefore, the petitions were not
maintainable. To overcome this technical objection by way of abundant H
268
A
B
c
SUPREME COURT REPORTS
[2001] 3 S.C.R.
caution the petitioners have sought amendment of the petition with
a view to challenging the said per Court order of 29.9.95. The
amendment is opposed on the ground that it is barred by 400 days.
However, in the aforementioned circumstances, we conclude that there
was no deliberate delay on the part of the petitioners, but it was only
because they thought that it was not necessary to challenge the order
of29.9.95 as they had challenged the subsequent order of 14.8.96. We,
therefore, condone the delay and allow the amendment.
We would also like to make it clear that we do not propose to go
into the merits of the matter except to consider whether in the aforesaid
factual background was it permissible to the learned Chief Justice to
hear and pass the order of 14.8.96. In other words, was the learned
Chief Justice entitled to hear the matter in view of the per Court order
passed on 29.9.95. If yes, the question is whether the per Court order
of 29.9.95 itself was a correct order. Ifno, what order this Court should
pass in the matter. This is the limited question which we may be
D
required to consider at the initial stage unless we find it necessary to
enter into the merits of the matter.
·
We direct the learned counsel appearing for the contesting parties
to file their brief written submissions within two weeks from today.
The matters may thereafter be fixed for final disposal. Permitted to
E
mention before the learned Chief Justice."
F
G
H
On 11.4 .1997 when the SLPs came up once again before the very Bench
of this Court, it was ordered as follows :-
"In order to avoid multiplicity of the proceedings which may be the
consequence if this Court first decides only the legality of the order
dated 14.8.1996 passed by the learned third Judge in the High Court,
we consider it appropriate to treat these special leave petitions as
ones against the judgment of the High Court even on merits.
Irrespective of the view taken by this Court on the question of the
legality of the order of the learned third Judge, these matters would
be heard as appeals even on merits of the case. This is clarified in
view of the earlier order dated 3.3.1997 which had indicated that this
Court did not propo~e then to go into the merits of these matters.
Learned counsel for both sides agree that this would be the more
appropriate course to avoid any further delay in the decision of the
matters on merits and it would also avoid multiplicity of proceedings
J ..
..
SIKKIM SUBBA ASSOCIATES v. STATE [RAJU, J.]
269
because in either view taken on the question of legality of the learned A
••
~
third Judge's order, the aggrieved party would be required to then
challenge the decision on merits. It is clarified accordingly.
Leave granted.
No stay.
B
Shri B. Sen, learned senior counsel for the appellants, submitted that
having regard to the fact that the Sikkim High Court, at the relevant point of
time, had only two judges, inclusive of the Chief Justice, and they have
chosen to differ from each other - the learned Chief Justice taking the view c
that the appeal of the State has to be allowed and the Award of damages in
favour of the appellants was unwarranted as well as unsustainable in law and
the other learned Judge (R. Dayal J.,) expressing the view that the award
suffered from an error of law apparent only in the manner of determination
of the quantum of damages and that for purposes of re-determination afresh
of the quantum of damages alone, the matter has to be remitted to the D
Arbitrator, the Award ought to have been confirmed under Section 98 (2)
+
C.P.C., particularly when rules 149 & 150 of the Sikkim High Court (Practice
& Procedure) Rules, 1991 came to be deleted with effect from 12.3.92, the date
"
of enforcement of the original rules. Reliance has been placed in this regard
on the decision of this Court reported in Tej Kaur & another v. Kirpal Singh E
& Another, [1995] 5 SCC 119 and that of the Assam High Court in Abdul Latif
v. Abdul Samad, AIR (1950) Assam 80. In traversing the said claim, Shri VA.
Bobde, learned senior counsel for the Sikkim State, contended that the words
...
"Court consisting of' in juxtaposition to the words "Constituting the Bench",
in proviso to sub-Section (2) of Section 98 will only have relevance and has
to be construed with reference to the sanctioned strength alone - 'which at F
all relevant points of time was only three so far as Sikkim High Court is
concerned and whenever there is a third judge, even on the vacancy being
filled up on such vacancy arising for any reason in respect of any one of the
two, the matter should be referred to and heard by the third judge and neither
any exception could be taken for the same nor could it be claimed that the G
,.,.
judgement under appeal before the High Court should only be confirmed.
Since retrospective deletion of a statutory rule could not have been legitimately
""-.\._
made by a notification by the rule-making authority in the absence of a
,,,-
specific statutory provision conferring any such power in this case, it is
contended that the deletion could be only of prospective effect and the case
before us would be governed by those rules, as if it existed.
H
270
SUPREME COURT REPORTS
[2001] 3 S.C.R.
A
In our view, the decision in AIR 1950 Assam 80 (Supra) has no application
to this case where unlike the Assam Case, the very Division Bench, as part
·~
of their judicial order also made a consequential order of reference to a third
judge and inasmuch as there was no appeal challenging the same. We are of
the view that rules 149 & 150 of the Sikkim High Court (Practice & Procedure)
B
Rules, 1991, which governed the situation, were very much in force on the
date when the Division Bench exercised their power and the order of reference
passed in this case could not therefore be said to be bad in law. Apart from
the a..-xiomatic principle of law that a subordinate legislation in the form of Rule
or Notification could not be made/unmade retrospectively unless any power
in that regard has been specifically conferred upon the Rule-making Authority,
c a mere retrospective deletion could not per se have the effect of nullifying
or destroying orders passed or acts already performed, when such powers
were available in the absence of any specific statutory provision enacted to
destroy all such rights already acquired or obligations and liabilities incurred.
The decision in [ 1995] 5 SCC 119 (supra) will have no ~pplication to this case,
D
in view of rules 149 & 150 noticed above and also for the reason that unlike
in the present case, the case considered therein, concedingly involved only
a question of fact over which the dissenting views came to be expressed. That
+
apart, the words "Consisting of' shall mean and also considered to have
relevance only to the sanctioned strength. Therefore, taking into account the
~,
fact that for the time being, there were only two Judges in position and that
E the learned judges, who constituted the Division Bench, expressed different
views and at the same time thought fit to refer the matter to the opinion of
a third judge, the matter should await till the arrival of a third judge. Not only
such a contingency also fructified in this case but the matter also came to
be actually posted before the third judge for hearing. The amplitude of powers
_J.
F
of this Court under Articles 136 and 142 of the Constitution oflndia for doing
complete justice in any cause or matter brought before it, cannot also be
otherwise disputed. As a matter of fact, in the teeth of the Orders passed by
this Court on 11.4.97 to treat the appeals as having been filed even on the
merits of the case and be heard as such, and that too, on the agreement
e::iq>ressed by the counsel on both sides, to be also the appropriate course,
,.
~
G in these matters, it is not permissible for the appellants to take a stand to the
contrary to avoid or stall a hearing and disposal of these appeals on the
merits of the matters involved therein.
The respondent-State, though at some point of time, seems to have
,.L ,..~
pressed into service Article 299 of the Constitution of India, to contend that
H no valid contract between parties came into existence as envisaged therein
)-
SIKKIM SUBBA ASSOCIATES v. STATE [RAJU, J.]
271
and consequently neither the Arbitrator could have entered upon reference A
nor can the State be held bound by such an agreement, the same was not
~
pursued before us realising the futility of the same, having regard to the
....
peculiar facts of this case. We are not called upon, in such circumstances, to
decide this issue and the parties have also proceeded on the footing that
there was a valid and binding contract between the appellants and the State, B
in this case, without prejudice to their contentions in respect of their rights
under the agreement.
On behalf of the appellants, it has been strenuously contended that the
1
Arbitrator's award cannot be challenged in proceedings under Section 30 of
the Act, as if on an appeal and that the Award in this case has been rightly c
upheld by the District Judge, since it did not disclose any 'misconduct' on
the part of the Arbitrator and no other ground for any such interference
within the parameters of Section 30, having also been substantiated by the
respondent-State. It is, therefore, contended that the decision of Chief Justice
Bhargava, for the same reason, could not be sustained and that the learned D
Chief Justice committed an error in directing the Award, as affirmed by the
District Judge, to be set aside for ariy one or other of the reasons assigned
by him." At the same time, while strongly defending the decision of the learned
Chief Justice, it was urged for the respondent-State that the numerous errors
apparent ex facie on the Award have been not only meticulously enumerated
E
but found to have been substantiated succinctly, by adverting to the materials
in support thereof for justifying Court's interference. It was also submitted for
the respondents that Dayal J., having found the Award to suffer from serious
infirmities in awarding damages, erred in directing a remand to the very
Arbitrator for consideration afresh, to re-determinate the damages and instead
~
there should have been only a suppression of the arbitration agreement itself F
under Section 19 read with Section 16 (c) of the Act. The learned senior
counsel on either side invited our attention to voluminous case law on the
scope and ambit of powers of Courts exercising jurisdiction under Section 30
as well as Section 39 of the Act for interference with the award of an
Arbitrator, which, on a closer scrutiny, would disclose that the observations G
I'll'
in each of such cases came to be made, invariably and ultimately in the
context of the peculiar facts and circumstances of the cases dealt with therein
and having regard to the particular class or category of mistakes or nature
of errors found highlighted in those cases. It is appropriate, before undertaking
..,;.._.__
an adjudication on the merits of the claims of parties, to advert to the salient
and overall peripheral parameters, repeatedly re- emphasised by this Court, in H
272
SUPREME COURT REPORTS
[2001] 3 S.C.R.
A justification of interference with an Award of the Arbitrator by different
Courts at various levels exercising powers under the Act as well as by this
Court, without unnecessarily multiplying the number of authorities by making
reference to only some relevant out of the same, for our purpose.
B
Relying upon the ratio in Champsey Bhara & Company v. jivraj Ba/loo
Spinning & Weaving Company Ltd., AIR (1923) P.C. 66 this Court in Mis
Alopi Parshad & Sons Ltd. v. Union of India, AIR (1960) SC 588 observed
that the award may be set aside on the ground of an error on the face thereof,
when in the award or in any document incorporated with it, as for instance,
a note appended by the Arbitrator(s) stating the reasons for the decision
C wherein the legal propositions which are the basis of the award are found to
be erroneous. A specific question submitted to the Arbitrator for his decision,
even if found answered wrongly involving an erroneous decision in point of
law also, was considered not to make the award bad on its face so as to call
for interference. While emphasising the position that 'misconduct' in Section
D 30 (a) of the Act comprises legal misconduct, this Court held it to be complete
in itself ·when the Arbitrator was found to have, on the face of the a1vard,
arrived at a decision by ignoring very material and relevant documents which
throw abundant light on the controversy to help a just and fair decision or
arrived at an inconsistent conclusion on his own finding K.P Poulose v. State
of Kera/a & Am:, AIR (1975) SC 1259. In Mis Chahal Engineering and
E Construction Company v. Irrigation Deptartment., Punjab, Sirsa, [1993] 4
SCC 186, this Court held that the words "is otherwise invalid" in clause (c)
of Section 30 of the Act would include an error apparent on the face of the
record. In Trustees of the Port of lvfadras v. Engineering Constructions
Corporation Ltd., [1995] 5 SCC 531 after adverting to the ratio of the
F
Constitution Bench of this Court in Raipur Development Authority & Ors. v.
Mis Chokhamal Contractors & others, [1989] 2 SCC 721, this Court held that
the error apparent on the face of the award contemplated by Section 16 (1)
(t;) and Section 30 (c) of the Act is "an error of law" apparerit on the face
of the award and not an error of fact and that the Arbitrator cannot ignore
the law or misapply it in order to do what he thinks is just and reasonable.
G In The President, Union of India & Another v. Kalinga Construciion Co. (P)
Ltd., AIR (1971) SC 1646, it was held that the Court, in a proceeding to set
aside the award cannot exercise jurisdiction, as if ori an appeal by re-examining
and re-appraising the evidence considered by the Arbitrator and come to the
decision that the Arbitrator was wrong (See also AIR 1989 SC 268; 1989 _SC
H 777 and 1989 SC 890).
)·
SIKKIM SUBBA ASSOCIATES v. STATE [RAJU, J.]
273
In Union of India v. Mis Jain Associates & Another, IT (1994) 3 SC 303, A
this Court held as follows:
"7. In K.P Poulose v. Mis Jain Associates & Am:, [1975] Supp. SCR
214, this Court held that misconduct under Section 30(a) does not
connote a moral lapse. It comprises of legal misconduct which is
complete if the arbitrator, on the face of the award, arrives at an B
inconsistent conclusion even on his own finding, by ignoring material
documents which would throw abundant light on the controversy and
help in arriving at a just and fair decision. It is in this sense that the
arbitrator has misconducted the proceedings in the case. In that case
the omission to consider the material documents. to resolve the C
controversy was held to suffer from manifest error apparent ex facie.
The award was accordingly quashed. In Dandasi Sahu v. State of
Orissa, [1990] 1 SCC 214, this Court held that the arbitrator need not
give any reasons. The award could be impeached only in limited
circumstances as provided under Section 16 and 30 of the Act. If the
award is disproportionately high having regard to the original claim D
made and the totality of the circumstances it would certainly be a case
of non application of mind amounting to legal misconduct and it is not
possible to set aside only invalid party while retaining the valid part.
In other words the doctrine of severability was held inapplicable in
such a situation. It is, therefore, clear that the word misconduct in E
Section 30(a) does not necessarily comprehend or include misconduct
of fraudulent or improper conduct or moral lapse but does comprehend
and include actions on the part of the arbitrator, which on the face of
the award, are opposed to all rational and reasonable principles
resulting in excessive award or unjust result or the like circumstances
which tend to show non application of the mind to the material facts F
placed before the arbitrator or umpire. In truth it points to fact that
the arbitrator or umpire had not applied his mind and not adjudicated
upon the matter, although the award professes to determine them.
Such situation would arnount to misconduct. In other words, if the
arbitrator or umpire is found to have not applied his mind to the G
matters in controversy and yet, has adjudicated upon those matters
in law, there can be no adjudication made on them. The arbitrator/
umpire may not be guilty of any act which can possibly be construed
as indicative or partiality or unfairness. Misconduct is often used, in
a technical sense denoting irregularity and not guilt of any moral
turpitude, that is, in the sense of non-application of the mind to the H
274
A
B
SUPREME COURT REPORTS
[2001] 3 S.C.R.
relevant aspects of the dispute in its adjudication. In K. V George v.
Secretary to Government, Water & Power Department, Trivandrum &
Am:, [1989] 4 SCC 595, this Court held that the arbitrator had committed
misconduct in the proceedings by making an award without
adjudicating the counter claim made by the respondent. In Indian Oil
Corporation Ltd. v. Amritsar Gas Service and Ors., [1991] 1 SCC 533
& 544, the counter claim was rejected on the ground of delay and non
consideration of the claim, it was held, constituted an error on the face
of the award."
It is also, by now, well settled that an Arbitrator is not a conciliator and
C his duty is to decide the disputes submitted to him according to the legal
rights of the parties and not according to what he may consider it to be fair
and reasonable. Arbitrator was held not entitled to ignore the law or misapply
it and cannot also act arbitrarily, irrationally, capriciously or independently of
the contract (See {l 999] 9 SCC 283 : Rajasthan State Mines and Minerals Ltd.
v. Eastern Engineering Enterprises & Am~) If there are two equally possible
D or plausible views or interpretations, it was considered to be legitimate for the
Arbitrator to accept one or the other of the available interpretations. It would.
be difficult for the Courts to either exhaustively define the word 'misconduct'
or likewise enumerate the line of cases in which alone interference either could
or could not be made. Courts of Law have a duty and obligation in order to
E maintain purity of standards and preserve full faith and credit as well as to
inspire confidence in alternate dispute redressal method of Arbitration, when
on the face of the Award it is sho"vn to be based upon a proposition of law
which is unsound or findings recorded which are absurd or so unreasonable
and irrational that no reasonable or right thinking person or authority could
have reasonably come to such a conclusion on the basis of the m~terials on
F record or the governing position of law to interfere. So far as the case before
us is concerned, the reference to the Arbitrator is found to be a general
reference to adjudicate upon the disputes relating to the alleged termination
of the agreement by the State and not a specific reference on any particular
question anci consequently, if it is shown or substantiated to be erroneous
G on the face of it, the award must be set aside.
The Award under challenge, in our view, stands vitiated on account of
several serious errors of law, apparent on the face of it and such infirn1ities
go to substantiate the claim of the State that not only the Arbitrator acted
--(
..
arbitrarily and irrationally on a perverse understanding or misreading of the
J.- ~
H materials but also found to have misdirected himself on the vital issues before
SIKKIM SUBBA ASSOCIATES v. STATE [RAJU, J.]
275
him so as to render the award to be one in utter disregard of law and the A
, precedents. Although the award purports to determine the claims of parties,
a careful scrutiny ofthe same discloses total non-application of mind to the
actual, relevant and vital aspects and issues in their proper perspective. Had
there been such a prudent and judicious approach, the Arbitrator could not
have awarded any damage whatsoever and, at any rate, such a fabulous a(ld
astronomical sum on mere conjectures and pure hypothetical exercises, B
absolutely divorced from rationality and realities, inevitably making law, equity
and justice, in the process, a casualty. The Arbitrator has acknowledged when
recording a finding on the basis of indisputable facts that except for the first
set of draws in respect of eight lotteries in groups A & B, the prize money
obliged to be deposited seven days before the draw (since the winners have C
to be paid only out of such deposits, after draw) as well as the agency fee
running to crores was not deposited/remitted in time constraining thereby the
State to mobilise funds to distribute prize money from State funds in orde*
to preserve and protect the fair name and reputation of the State, the lotteries
being run as that of and for and on behalf of the State. Even, as late as 8. 2. 94'
when the award came to be passed the appellants were in arrears, due to non- D
deposit of prize money within the stipulated time, a sum of Rs.1,37,47,026
besides non-remittance of agency fee of Rs. 3,72,87,884. Despite this, the
Arbitrator tried to find an alibi for the defaulter appellants in the fact that the
State, in spite of warnings and threats, did not actually stop either those ·
draws or the further subsequent draws and allowed the lotteries to go on E
without any break. From the above, the Arbitrator as well as the learned ·
District Judge chose to infer that the respondent-State had condoned or
waived the lapses and defaults completely overlooking the vital fact that the
Arbitrator is not dealing with any claim for damages from the respondentState against the appellants who defaulted in respect of such defaults but on
the other hand a claim from the defaulter appellants itself for damages against F
the State for not willing to put up any longer with a recurrent and recalcitrant
defaulter. The Arbitrator, grossly omitted to give due weight to such defaults
committed by the appellants and further misdirected himself in not drawing
the legal inferences necessarily flowing from them.