# OIL & NATURAL GAS CORPORATION LTD v. SAW PIPES LTD

- **Citation:** [2003] 3 S.C.R. 691
- **Court:** Supreme Court of India
- **Decided:** 2003
- **Case number:** Civil Appeal No. 7419 of2001
- **Bench:** M.B. Shah, Arun Kumar
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/oil-natural-gas-corporation-ltd-v-saw-pipes-ltd-19126
- **Pages:** 51

## Headnote

Arbitration and Conciliation Act, 1966; Sections 23, 24, 25, 28, 31 and
34: Contract for supply of goods-Time is the essence of the contract-Delay
A
B
in supply of goods-Contractor's liability to purchaser-Award-Denial of C
compensation-Held: when liability to pay compensation in lieu of damages
for breach of any term of the contract by the other party is stipulated clearly
and unambiguously, and in the absence of evidence proving the compensation
claimed as unreasonable, arbitral tribunal could not ignore clear terms of the
agreement to determine liability of the defaulting party-It is not necessary
for the claimant to produce evidence proving damages/loss suffered by him- D
Burden is on the contending party to prove that claim is unreasonable-Since
contending party agrPed to pay damages, he cannot deny the same-Loss
actually suffered by the purchaser need not be proved-Indian Contract Act,-
Sections 73 and 74.
Claim-Deduction of compensation/claim by the purchaser from the bill
of the contractor in lieu of damages for breach of agreeme/1/-Nature ofHeld: such claim would be treated as disputed claim-Arbitrator to decide
it-Under the facts and circumstances of the case, Arbitrator holding the
claim as undisputed on the ground that goods were received and bill was no/
E
disputed-Such finding of the Arbitrator unjust and unreasonable. ·
F
Award by the arbitral tribzmal-lnterference with-Jurisdiction of the
Court-Ambit and scope of-Held: arbitral tribunal is empowered lo decide
the dispute referred to ii in accordance with the provisions of the Ac/-
Procedural law provides relief against the right-Award passed in
contravention of the provisions of substantive law/Act would be patently illegal G
and contrary to the basic concept of justice-Hence could be interfered with
by the Court.
Award in conflict with Public Policy of India-Power of the Court lo
inteifere with-Held: since the phrase 'Public Policy of India' is not defined H
591
692
SUPREME COURT REPORTS
(2003] 3 S.C.R.
A · under the Act, 1he Court requires to give contextual meaning in the light of
the principles underlying the Arbitralion Act/Contract Act/Constitutional
provisions-It could either be construed in a narrower or broader senseWhen award attains finality, jurisdiction of the Court to interfere with is
limited on the ground of public policy-It could be given wider meaning by
B !he Court in exercise of its appellatelrevisiona/jurisdiction-Award, in violation
of statutory provisions, can not be termed to be in public interest-Hence
against Public Policy of India and void-Interpretation of Statutes.
c
Domestic award and foreign award-Dist incl ion between-Discussed.
Words & Phrases:
'Arbitral Procedure', 'Substantive Law', 'Public Policy of India', 'Force
Majeure ', 'liquidated damages', 'wrtent illegality' and 'disputed claim'-
Meaning of in the context of Arbitration and Conciliation Act, 1996.
Respondent-foreign company, a contractor, had entered into an
D agreement with the appellant-company, a purchaser for supply of certain
goods on agreed terms. Timely delivery of the goods was the essence of
the agreement. As per terms of the agreement, any delay in supply of the
goods would entail liability on the contractor to liquidate damages for delay
in supply of goods. The respondent could not supply the goods in time due
E to strike of workers in that country and sought for extension of time. While
conveying extension, the appellant specifically mentioned that the liquidated
damages would be recovered from them. Accordingly it recovered the same
by making deductions from the payment due to the respondent. Since the
respondent considered the deduction as wrongful, it referred the dispute
F to the arbitral tribunal. The tribunal held the deduction made by the
appellant wrongful since it could not establish the actual monetary loss
suffered by it due to delay in supply of goods under the contract and the
tribunal passed an award accordingly. Appeal against the award was

## Text

_Characters 0–39,962 of 120,471. This is a partial read: ask again with offset=39962 for what follows._

OIL & NATURAL GAS CORPORATION LTD.
v.
SAW PIPES LTD.
APRIL I 7, 2003
[M.B. SHAH AND ARUN KUMAR, JJ.]
Arbitration and Conciliation Act, 1966; Sections 23, 24, 25, 28, 31 and
34: Contract for supply of goods-Time is the essence of the contract-Delay
A
B
in supply of goods-Contractor's liability to purchaser-Award-Denial of C
compensation-Held: when liability to pay compensation in lieu of damages
for breach of any term of the contract by the other party is stipulated clearly
and unambiguously, and in the absence of evidence proving the compensation
claimed as unreasonable, arbitral tribunal could not ignore clear terms of the
agreement to determine liability of the defaulting party-It is not necessary
for the claimant to produce evidence proving damages/loss suffered by him- D
Burden is on the contending party to prove that claim is unreasonable-Since
contending party agrPed to pay damages, he cannot deny the same-Loss
actually suffered by the purchaser need not be proved-Indian Contract Act,-
Sections 73 and 74.
Claim-Deduction of compensation/claim by the purchaser from the bill
of the contractor in lieu of damages for breach of agreeme/1/-Nature ofHeld: such claim would be treated as disputed claim-Arbitrator to decide
it-Under the facts and circumstances of the case, Arbitrator holding the
claim as undisputed on the ground that goods were received and bill was no/
E
disputed-Such finding of the Arbitrator unjust and unreasonable. ·
F
Award by the arbitral tribzmal-lnterference with-Jurisdiction of the
Court-Ambit and scope of-Held: arbitral tribunal is empowered lo decide
the dispute referred to ii in accordance with the provisions of the Ac/-
Procedural law provides relief against the right-Award passed in
contravention of the provisions of substantive law/Act would be patently illegal G
and contrary to the basic concept of justice-Hence could be interfered with
by the Court.
Award in conflict with Public Policy of India-Power of the Court lo
inteifere with-Held: since the phrase 'Public Policy of India' is not defined H
591
692
SUPREME COURT REPORTS
(2003] 3 S.C.R.
A · under the Act, 1he Court requires to give contextual meaning in the light of
the principles underlying the Arbitralion Act/Contract Act/Constitutional
provisions-It could either be construed in a narrower or broader senseWhen award attains finality, jurisdiction of the Court to interfere with is
limited on the ground of public policy-It could be given wider meaning by
B !he Court in exercise of its appellatelrevisiona/jurisdiction-Award, in violation
of statutory provisions, can not be termed to be in public interest-Hence
against Public Policy of India and void-Interpretation of Statutes.
c
Domestic award and foreign award-Dist incl ion between-Discussed.
Words & Phrases:
'Arbitral Procedure', 'Substantive Law', 'Public Policy of India', 'Force
Majeure ', 'liquidated damages', 'wrtent illegality' and 'disputed claim'-
Meaning of in the context of Arbitration and Conciliation Act, 1996.
Respondent-foreign company, a contractor, had entered into an
D agreement with the appellant-company, a purchaser for supply of certain
goods on agreed terms. Timely delivery of the goods was the essence of
the agreement. As per terms of the agreement, any delay in supply of the
goods would entail liability on the contractor to liquidate damages for delay
in supply of goods. The respondent could not supply the goods in time due
E to strike of workers in that country and sought for extension of time. While
conveying extension, the appellant specifically mentioned that the liquidated
damages would be recovered from them. Accordingly it recovered the same
by making deductions from the payment due to the respondent. Since the
respondent considered the deduction as wrongful, it referred the dispute
F to the arbitral tribunal. The tribunal held the deduction made by the
appellant wrongful since it could not establish the actual monetary loss
suffered by it due to delay in supply of goods under the contract and the
tribunal passed an award accordingly. Appeal against the award was
dismissed by the High Court. Hence the present appeal.
G
It was contended for the appellant that since the Award passed by
the arbitral tribunal was in violation of Sections 28 to 31 of the Arbitration
and Conciliation Act, it could be set aside by the Court as per provisions
under Section 34 of the Act; that since the impugned award was challenged
before a Forum prescribed under the Act and did not attain finality, wider
I
J"-
meaning could be assigned to the term 'Public Policy of India'; that the
r
H provisions of law for setting aside domestic award and foreign award are
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD.
693
different and the domestic award could be set aside under Section 34 of A
the Act; that since no time limit for passing the award has been prescribed
under the Act, impliedly legislature did not intend to give limited
jurisdiction to the Court, and the award passed by the tribunal could not
be said to have attained finality; that since the award was contrary to the
provisions of sub-section (3) of Section 28, it was vitiated and the appellant
was entitled to recover liquidated damages from the respondent; that the
award was illegal since appellant was required to prove the loss suffered
by it due to. delay in supply of goods in contradiction to the terms of the
agreement; and that the interest as granted in the award was unreasonable/
unjustified since it was against the specific terms of the agreement.
On behalf of the respondent, it was submitted that the phrase 'Public
Policy of India' could not be so interpreted to mean that the Court possesses
jurisdiction to set aside the award in violation of some provisions of law;
B
c
that Parliament did not intend to give wider jurisdiction to the Court to
challenge the arbitral award; otherwise it would have adopted similar
provisions of English Law on the subject; that limited jurisdiction is given D
to the Court under the provisions of the Act with the object of resolving
disputes at the earliest by giving finality to the award passed by the arbitral
tribunal; and that compensation/damages would be awarded for the breach
of contract only if loss was suffered and proved.
Allowing the appeal, the Court
HELD: I.I. The arbitral tribunal is empowered and is required to
decide the dispute in accordance with the provisions of the Arbitration and
Conciliation Act. Since the jurisdiction or the power of the arbitral tribunal
E
is prescribed under the Act, the award de hors the provisions, would be, F
on the face of it, illegal. The decision of the tribunal must be within the
bounds of its jurisdiction conferred under. the Act or the contract. In
exercising jurisdiction, the arbitral tribunal can not act in breach of some
provision of substantive law or the provisions of the Act. 1706-B, F, GJ
Harish Chandra Bajpai v. Triloki Singh, (19571SCR370, relied on.
1.2. In view of Section 34 and other provisions of the Act that the
legislative intent could not be that if the award is in contravention of the
provisions of the Act, still however, it couldn't be interfered and set aside
G
by the Court. If it is held that such award could not be interfered, it would H
694
SUPREME COURT REPORTS
(2003] 3 S.C.R.
A be contrary to basic concept of justice. If the arbitral tribunal has not
followed the mandatory procedure prescribed under the Act, it would mean
that it has acted beyond its jurisdiction and thereby the award would be
patently illegal which could be set aside under Section 34. Such
interpretation of clause (v) would be in conformity with the settled principle
B of law - there cannot be any wrong without a remedy - that procedural
law cannot fail to provide relief when substantive law gives the right.
(707-D-EJ
M V. Elisabeth and Ors v. Harwan Investment & Trading Pvt. Ltd, ( 1993)
Supp. 2 SCC 433 and Dhanna Lal v. Kalawatibai and Ors., (2002) 6 SCC
C 16, relied on.
2.1. The phrase 'Public Policy of India' is not defined under the Act.
Hence, the said term is re:;_;, ed to be given meaning in context and also
considering the purpose of the Section and scheme of the Act. It has been
D repeatedly stated by various authorities that the expression 'public policy'
does not admit of precise definition and may vary from generation to
generation and from time to time. Hence, the concept 'public policy' is
considered to be vague, susceptible to narrow or wider meaning depending
upon the context in which it is used. Lacking precedent the Court has to
give its meaning in the light of principles underlying the Arbitration Act,
E Contract Act and Constitutional provisions. (708-A, Bl
2.2. The term 'Public Policy of India' is required to be interpreted in
the context of the jurisdiction of the Court where the validity of award is
challenged before it becomes final and executable. The concept of
enforcement of the award after it becomes final is different and the
F jurisdiction of the Court at that stage could be limited. Similar is the
position with regard to the execution of a decree. It is settled law as well
as it is provided under Code of Civil Procedure that once the decree has
attained finality, in an execution proceeding, it may be challenged only on
limited grounds such as the decree being without jurisdiction or nullity.
G But in a case where the judgment and decree is challenged before the
Appellate Court or the Court exercising revisional jurisdiction, the
jurisdiction of such Court would be wider. Therefore, in a case where the
validity of award is challenged there is no necessity of giving a narrower
meaning to the term 'public policy of India'. On the contrary, a wider
meaning is required to be given so that the 'patently illegal award' passed
H by the arbitral tribunal could be set aside. It is for the Parliament to provide
•
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD.
695
for limited or wider jurisdiction to the Court in case where award is A
challenged. But in s.uch cases, there is no reason to give narrower meaning
to the term 'Public Policy of India'. Instead, wider meaning is required to
be given so as to prevent frustration of legislation and justice. The phrase
'Public Policy of India' used in Section 34 is required to be given a wider
meaning. It can be stated that the concept of public policy connotes some B
matter which concerns public good and the public interest. What is for
public good or in public interest or what would be injurious or harmful to
the public good or public interest has varied from time to time. The award
which is, on the face of it, patently in violation of statutory provisions
cannot be said to be in public interest. Such award/judgment/decision is
likely to adversely affect the administration of justice.
C
(713-C-E; 718-A-D; 716-GJ
Central Inland Water Transport Corporation Limited and Anr. v. Brojo
Nath Ganguly and Anr., (1986] 3 SCC 156; Murlidhar Agarwal and Anr. v.
State of U.P. and Ors., (1974) 2 SCC 472 and Rattan Chand Hira Chand v.
Askar Nawaz Jung (Dead) By Lrs. and Ors., (1991] 3 SCC 67 , referred to. D
Renusagar Power Co. ltd. v. General Electric Co., [1994) Supp. 1 SCC
644, distinguished.
'law of Arbitration and Conciliation' by Justice Dr. B.P. Saraf and E
Justice SM Jhunjhunwala, referred to.
2.3. If the award is patently against the statutory provisions of
substantive law which is in force in India or is passed without giving an
opportunity of hearing to the parties or without giving any reason in a case
where parties have not agreed that no reasons are to be recorded, it would
F
be against the statutory provisions. In such cases, the award is required to
be set aside on the ground of 'patent illegality'. (714-A, B]
2.4. It is true that under the Act, there is no provision which
specifically provides that the arbitrator shall pass award within reasonable G
time as fixed by the Court; that on occasions, arbitration proceedings are
delayed for one or the other reason, but it is for the parties to take
appropriate action in that regard. However, non-providing of time limit
for deciding the dispute by the arbitrators could have no bearing on
interpretation of Section 34 •. _Further, for achieving the object of speedier
disposal of dispute, justice in accordance with law can not be sacrificed. H
696
SUPREME COURT REPORTS
[2003] 3 S.C.R.
A Thus, giving limited jurisdiction to the Court for havi.ng finality to the
award by the arbitrator and resolving the dispute by speedier method
would be much more frustrated by permitting patently illegal award to
operate. Patently illegal award is required to be set at naught, otherwise it
would promote injustice. [717-E-H; 718-Al
B
2.5. An award could be set aside if it is contrary to:-
(a) fundamental policy of Indian law; or
(b) th:; interest of India; or
(c) justice or morality, or
C
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of
trivial nature it cannot be held that award is against the public policy.
Award could also be set aside if it is so unfair and unreasonable that it
shocks the conscience of the Court. Such award is opposed to public policy
D and is required to be adjudged void. [739-H; 740-A, Bl
3.1. lt is settled law that the intention of the parties is to be gathered
from the words used in the agreement. If words are unambiguous and are
used after full understanding of their meaning by experts, it would not be
E appropriate to gather their intention different from the language used in
the agreement. If upon a reading of the documents as a whole, it can fairly
be deduced from the words actually used therein that the parties had agreed
on a particular term, there ·is nothing in law which prevents them from
setting up that term. When parties have expressly agreed that recovery
from the contractor for breach of the contract is pre-estimated genuine
F liquidated damages and is not by way of penalty duly agreed by the parties,
there was no justifiable reason for the arbitral tribunal to arrive at a
conclusion that still the purchaser should prove loss suffered by it because
of delay in supply of goods. [723-B, C, El
Modi & Co. v. Union of India, [196812 SCR 565 and Provash Chandra
G Dalui andAnr. v. Biswanath Banerjee and Anr., [1989[ Supp 1SCC487, relied
on.
3.2. The arbitral tribunal is required to decide the dispute in
accordance with the terms of the contract. In the instant case, the agreement
H between the parties specifically provides that without prejudice to any other
..
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD.
697
right or remedy if the contractor fails to deliver the stores within the A
stipulated time, appellant will be entitled to recover from the contractor
liquidated damages on agreed terms.Further, when respondent sought
extension of time for supply of goods, time was extended with a specific
demand that the clause for liquidated damages would be invoked and
appellant would recover the same for such delay. Despite such specific B
indication by the appellant, respondent had supplied the goods which would
indicate that even at that stage, respondent was agreeable to pay liquidated
damages. 1723-F, G; 724-8, Cl
3.3. From the provisions of law under Sections 73 and 74 of Indian
Contract Act, it can be held that when a contract has been broken, the C
party who suffers by such breach is entitled to receive compensation for
any loss which naturally arise in the usual course of things from such
breach. And if parties knew when they made the contract that a particular
loss is likely to result from such breach, they can agree for payment of such
compensation. In such a case, there may not be any necessity of leading
evidence for proving damages, unless the Court arrives at the conclusion D
that no loss is likely to occur because of such breach. Further, in case where
Court arrLves at the conclusion that the term contemplating damages is
by way of penalty, the Court may grant reasonable compensation not
exceeding the amount so named iii the contract on proof of damages.
However, when the terms of the contract are clear and unambiguous then
its meaning is to be gathered only from the words used therein. In a case
where agreement is executed by experts in the field, it would be difficult
to hold that the intention of the parties was different from the language
used therein, and it is for the party who contends that stipulated amount
is not reasonable compensation, to prove the same. 1725-C-EI
Mazda Bux v. Union of India, 119691 2 SCC 554; H.M. Kamaluddin
Ansari & Co. v. Union of India and Ors., 119831 4 SCC 417 and Union of
India v. Rampur Distillery & Chemical Co. Ltd., 119731 I SCC 649, relied
on.
Fateh Chand v. Ba/kishan Das, 119641 I SCR 515, distinguished.
Union of India v. Raman Iron Foundry, 119741 2 SCC 231, held
inapplicable.
E
F
G
3.4. It is true that if the arbitral tribunal has committed mere error H
698
SUPREME COURT REPORTS
(2003) 3 S.C.R.
A of fact or law in reaching its conclusion on the disputed question submitted
to it for adjudication then the Court would have no jurisdiction to interfere
with the award. But, this would depend upon reference made to the
arbitrator; (a) If there is a general reference for deciding the contractual
dispute between the parties and if the award is based on erroneous legal
B proposition, the Court could interfere; (b) It is also settled law that in a
case of reasoned award, the Court can set aside the same if it is, on the
face of it, erroneous on the proposition of law or its application; (c) If a
specific question of law is submitted to the arbitrator, erroneous decision
in point of law does. not make the award bad, so as to permit of its being
set aside, unless the Court is satisfied that the arbitrator had proceeded
C illegally. (729-D, El
3.5. In the facts of the instant case, if contractual term, as it is, is to
be taken into consideration, the award is, on the face of it, erroneous and
in violation of the terms of the contract and thereby it violatPs Section 28(3)
D of the Act. The reference to the arbitral tribunal was · Jt with regard to
interpretation of question of law. It was only a general reference with
regard to claim of respondent. Hence, if the award is erroneous on the basis
of record with regard to proposition of law or its application, the Court
will have jurisdiction to interfere with the same. 1729-F, GI
E
Mis. Alopi Parshad & Sons Ltd. v. Union of India, 11960] 2 SCR 793;
Maharashtra State Electricity Board v. Sterilite Industries (India) and Anr.,
120011 8 SCC 482; Union of India v. A.L. Ra/lia Ram, [1964] 3 SCR 164;
Seth Thawardas Pherumal v. Union of India, [ 1955] 2 SCR 48; Rajasthan State
Mines & Minerals Ltd v. Eastern Engineering Enterprises and Anr., [199919
F sec 283; Sikkim Subba Associates v. State of Sikkim, [200115sec629 and
G.M Northern Railway and Anr. v. Sarvesh Chopra, [200214 SCC 45, referred
to.
G
F.R. Absalom Ltd. v. Great Western (London) Garden Village Society
Ltd., (1993) AC 592, referred to.
4:1. The arbitral tribunal failed to consider Sections 73 and 74 of the
Indian Contract Act and the ratio laid down in *Fateh Chandv. Balkishan
Das wherein.it is specifically held that jurisdiction of the Court to award
compensation in case of breach of contract is unqualified except as to the
maximum stipulated; and compensation has to be reasonable. The emphasis
H is on reasonable compensation. If the compensation named in the contract
I
;A
·-
--
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD.
699
is by way of penalty, consideration would be different and the party is only A
entitled to reasonable compensation for the loss suffered. But if the
compensation named in the contract for such breach is genuine pre-estimate
of loss which the parties knew when they made the contract to be likely to
result from the breach of it, there is no question of proving such loss or such
party is not required to lead evidence to prove actual loss suffered by him.
Burden is on the other party to lead evidence for proving that no loss is likely B
to occur bv such breach. (734-C-GI
*Fateh Chand v. Balkishan Das, (196411 SCR 515, followed.
Mau/a Bux v. Union of India, (196912 SCC 554, relied on.
4.2. In the instant case, no evidence is led by the claimant to establish
that stipulated condition was by way of penalty or the compensation contemplated
was, in any way, unreasonable. There was no reason for the tribunal not to
rely upon the clear and unambiguous terms of agreement stipulating prec
estimate damages because of delay in supply of goods. [736-EI
D
4.3. When the agreed amount is deducted and thereafter contractor
claims it back on the ground that the appellant was not entitled to deduct the
same as it has failed to prove loss suffered by it, such claim undoubtedly would
be a 'disputed claim'. The arbitrators were-required to decide the undisputed E
claim by considering the facts and the law applicable. The reason recorded by
the arbitrators that as the goods were received and bills are not disputed,
therefore, the claim for recovering the amount of bills cannot be held to be
'disputed claim' is, on the face of it, unjust, unreasonable, unsustainable and
patently illegal as well as against the expressed terms of the contract. It is the
primary duty of the arbitrators to enforce a promise which the ,parties have F
made and to uphold the sanctity of the contract which forms the basis of the
civilized society and also the jurisdiction of the arbitrators. Hence, that part
of the award passed by the arbitral tribunal granting interest on the amount
deducted by the appellant from the bills payable to the respondent is against
the terms of the contract and is, therefore, violative of Section 28(3) of the G
Act. (738-A-C-F(
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7419 of2001.
From the Judgment an(l Order dated 21.6.2000 of the Mumbai High
Court in A. No. 256 of 2000.
H
700
SUPREME COURT REPORTS
[2003] 3 S.C.R.
A
Ashok H. Desai, Dushyant A. Dave, Sunil Gupta, Ashwani Kumar, Ms.
B
Anuradha Bindra, Kashi Vishweshwaran, Ms. Padmalakshmi Nigam, Vikram
Mehta, K.R. Sasiprabhu, A.M. Khattawala, Mahesh Agarwal, Rishi Agarwal,
E.C. Agarwala, Prabhjit Jauhar and S.S. Jauhar for the Appearing parties.
The Judgment of the Court was delivered by
SHAH, J. Court's Jurisdiction Under Section 34 of the Arbitration and
Conciliation Act. 1966
Before dealing with the issues involved in this appeal, we would first
decide the main point in controversy, namely-the ambit and scope of Court's
C jurisdiction in case where award passed by the Arbitral Tribunal is challenged
under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as "the Act") as the decision in this appeal would depend upon
the said finding. In other words-whether the Court would have jurisdiction
under Section 34 of the Act to set aside an award passed by the Arbitral
D Tribunal which is patently illegal or in contravention of the provisions of the
Act or any other substantive law governing the parties or is against the terms
of the contract?
Learned senior counsel Mr. Ashok Desai appearing for the appellant
submitted that in case where there is clear violation of Section 28 to 31 of the
E Act or the terms of the Contract between the parties, the said award can be
and is required to be set aside by the Court while exercising jurisdiction
under Section 34 of the Act.
Mr. Dushyant Dave, learned senior counsel appearing on behalf of
respondent-company submitted to the contrary and contended that the Court's
F jurisdiction under Section 34 is limited and the award could be set aside
mainly on the ground that the same is in conflict with the 'Public Policy of
India'. According to his submission, the phrase 'Public Policy of India'
cannot be interpreted to mean that in case of violation of some provisions
of law, the Court can set aside the award.
G
H
For deciding this controversy, we would refer to the relevant part of
Section 34 which reads as under:-
"34. Application for setting aside arbitra/ award-{!) Recourse to a
court against an arbitral award may be made only by an application
for setting aside such award in accordance with sub-section (2) and
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD. [SHAH, J.]
701
sub-section (3).
(2)
An arbitral award may be set aside by the court only if-
(a)
the party making the application furnishes proof that-
(i)
a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the law to which
the parties have subjected it or, failing any indication thereon,
under the law for the time being in force; or
(iii) the party making the application was not given proper notice
A
B
of the appointment of an arbitrator or of the arbitral C
proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by
or not falling within the terms of the submission to arbitration,
or it contains decisions on matters beyond the scope of the
submission to arbitration;
Provided that, if the decisions on matters submitted to arbitration
can be separated from those not so submitted, only that part of the
arbitral award which contains decisions on matters not submitted to
arbitration may be set aside; or
D
(v) the composition of the arbitra/ tribunal or the arbitral E
procedure was not in accordance with the agreement of the
parties, unless such agreement was in conflict with a provision
of this Part from which the parties cannot derogate, or, failing
such agreement, was not in accordance with this Part; or
(b) the court finds that-
(i)
the subject-matter of the dispute is not capable of settlement
by arbitration under the law for the time being in force, or
(ii) arbitral award is in conflict with the public policy of India.
Explanation-Without prejudice to the generality of sub-clause
(ii), it is hereby declared, for the avoidance of any doubt, that an
award is in conflict with the public policy of India if the making of
the award was induced or affected by ji·aud or corruption or was in
violation of Section 75 or Section 81."
F
G
H
702
SUPREME COURT REPORTS
[2003] 3 S.C.R.
A
For our purpose, it is not necessary to refer to the scope of self
explanatory Clauses (i) to (iv) of sub-section (2)(a) of Section 34 of the Act
and it does not require elaborate discussion. However, clause (v) of subsection 2(a) and clause (ii) of sub-section 2(b) require consideration. For
proper adjudication of the question of jurisdiction, we shall first consider
B what meaning could be assigned to the tenn 'Arbitral Procedure.'
c
'Arbitral Procedure.'
The ingredients of clause (v) are as under:-
(I) The Court may set aside the award:-
(i) (a) ifthe composition of the arbitral Tribunal was not in accordance
with the agreement of the parties.
(b) failing such agreement, the composition of the arbitral tribunal
was not in accordance with Part-I of the Act.
D
(ii)
if the arbitral procedure was not in accordance with:-
( a) the agreement of the parties, or
(b) failing such agreement, the arbitral procedure was not in
accordance with Part-I of the Act.
E
However, exception for setting aside the award on the ground of
composition of arbitral tribunal or illegality of arbitral procedure is that the
agreement should not be in conflict with the provisions of Part-I of the Act
from which parties cannot derogate.
In the aforesaid sub-clause (v), the emphasis is on the agreement and
F the provisions of Part-I of the Act from which parties cannot derogate. It
means that the composition of arbitral tribunal should be in accordance with
the agreement. Similarly, the procedure which is required to be followed by
the arbitrators should also be in accordance with the agreement of the parties.
If there is no such agreement then it should be in accordance with the
G procedure prescribed in the Part-I of the Act i.e. Section 2 to 43. At the same
time, agreement for composition of arbitral tribunal or arbitral procedure should
not be in conflict with the provisions of the Act from which parties cannot
derogate. Chapter V of Part-I of the Act provides for conduct of arbitral
proceedings. Section 18 mandates that parties to the arbitral proceedings shall
be treated with equality and each party shall be given full opportunity to
H present his case, Section 19 specifically provides that arbitral tribunal is not
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD. [SHAH, J.]
703
bound by the Code of Civil Procedure, 1903 or the Indian Evidence Act, 1872 A
and parties are free to agree on the procedure to be followed by the arbitral
tribunal in conducting its proceedings. Failing any agreement between the
parties subject to other provisions of Part-I, the arbitral tribunal is to conduct
the proceedings in the manner it considers appropriate. This power includes
the power to determine the admissibility, relevance the materially and weight B
of any evidence. Sections 20, 21 and 22 deal with place of arbitration,
commencement of arbitral proceedings and language respectively. Thereafter,
Section, 23 24 and 25 deal with statements of claim and defence, hearings and
written proceedings and procedure to be followed in case of default of a party.
At this stage, we would refer to Section 24 which is as under:-
C
"24. Hearings and written proceedings-( I) Unless otherwise agreed
by the parties, the arbitral tribunal shall decide whether to hold
oral hearings for the presentation of evidence or for oral argument,
or whether the proceedings shall be conducted on the basis of
documents and other materials:
Provided that the arbitral tribunal shall hold oral hearings, at
an appropriate stage of the proceedings, on a request by a party,
unless the parties have agreed that no oral hearing shall be held.
D
(2) The parties shall be given sufficient advance notice of any hearing E
and of any meeting of the arbitral tribunal for the purposes of
inspection of documents, goods or other property.
(3) All statements, documents or other information supplied to, or
applications made to the arbitral tribunal by one party shall be
communicated to the other party, and any expert report or evidentiary F
document on which the arbitral tribunal may rely in making its decision
shall be communicated to the parties."
Thereafter, Chapter VI deals with making of arbitral award and termination
of proceedings. Relevant Sections which require consideration are Sections
28 and 31. Section 28 and 31 read as under:-
G
"28. Rules applicable to substance of dispute-
(1)
Where the place of arbitration is situate in India-
(a) in an arbitration other than an international commercial
arbitration, the arbitral tribunal shall decide the dispute H
704
A
B
c
SUPREME COURT REPORTS
(2003] 3 S.C.R.
submitted to arbitration in accordance with the substantive
law of the time being in force in India.
(b)
in international commercial arbitration,-
(i) the arbitral tribunal shall decide the dispute in accordance
with the rules of law designated by the partie~ as applicable
to the substance of the dispute;
(iO any designation by the parties of the law or legal system of
a given country shall be construed, unless otherwise
expressed, as directly referring to the substantive law of that
country and not to its conflict of law rules;
(iiO failing any designation of the law under clause (a) by the
parties, the arbitral tribunal shall apply the rules of law it
considers to be appropriate given all the circumstances
surrounding the dispute.
D
(2) The arbitral tribunal shall decide ex aequo et bona or as.
E
amiable compositeur only if the parties have expressly authorised it
to do so.
(3) In all cases, the arbitral tribunal shall decide in accordance
with the terms of the contract and shall take into account the usages
of the trade applicable to the transaction.
31. Form and contents of arbitral award-(!) An arbitral award shall
be made in writing and shall be signed by the members of the arbitral
tribunal.
F
(2) For the purposes of sub-section (I), in arbitral proceedings
with more than one arbitrator, the signatures of the majority of all the
members of the arbitral tribunal shall be sufficient so long as the
reason for any omitted signature is stated.
(3) The arbitral award shall state the reasons upon which it is
G
based, unless-
(a)
the parties have agreed that no reasons are to be given, or
(b) the award is an arbitral award on agreed tern1s under section 30.
(4) The arbitral award shall state is date and the place ofarbitratinn
H
as determined in accordance with section 20 and the award shall be
,,
OIL & NATURAL GAS CORPORATION LTD. v. SAW PIPES LTD. [SHAH, J.] 705
deemed to have been made at that plare.
(5) After the arbitral award is made, a signed copy shall be delivered
to each party.
A
(6) The arbitral tribunal may, at any time during the arbitral
proceedings, make an interim arbitral award on any matter with respect B
to which it may make a final arbitral award.
(7)(a) Unless otherwise agreed by the parties, where and in so far
as an arbitral award is for the payment of money, the arbitral tribunal
may include in the sum for which the award is made interest, at such
rate as it deems reasonable, on the whole or any part of the money, C
for the whole or any part of the period between the date on which the
cause of action arose and the date on which the award is made.
(b) A sum directed to be paid by an arbitral award shall unless
the award otherwise directs carry interest at the rate of eighteen per
centum per annum from the date of the award to the date of payment. D
(8) Unless otherwise agreed by the parties,
(a) the costs of an arbitration shall be fixed by the arbitral
tribunal:
(b) the arbitral tribunal shall specify,-
(i)
the party entitled to costs.
(ii) the party who shall pay the costs,
E
(iii) the amount of costs or method of determining that F
amount, and
(iv) the manner in which the costs shall be paid.
Explanation: For the purpose of clause (a), "costs" means reasonable
costs relating to,-
(0
the fees and expenses of the arbitrators and witnesses.
(ii)· legal fees and expenses,
(iii) any administration fees of the institution supervising the
arbitration, and
G
H
706
SUPREME COURT REPORTS
(2003) 3 S.C.R.
A
(iv) any other expenses incurred in connection with the arbitral
proceedings and the arbitral award."
The aforesaid provisions prescribe the procedure to be followed by the
arbitral tribunal coupled with its powers. Power and procedure are synonymous
in the present case. By prescribing the procedure, the arbitral tribunal is
B empowered and is required to decide the dispute in accordance with the
provisions of the Act, that is to say, the jurisdiction of the tribunal to decide
the dispute is prescribed. In these sections there is no distinction between
the jurisdiction/power and the procedure. In Harish Chandra Bajpai v. Triloki
Singh, (1957] SCR 370, while dealing with Sections 90 and 92 of the
C Representation of the !'eople Act, 1951 (as it stood), this Court observed
thus:-
D
E
"It is then argued that S.92 confers powers on the Tribunal in
respect of certain matters, While S. 90(2) applies the CPC in resoect
of matters relating to procedure that there is a distinction between
power and procedure, and that the granting of amendment being a
power and not a matter of procedure, it can be claimed only under
section 92 and not under S. 90(2). We do not see any antithesis
between 'procedure' in S. 90(2) and 'powers' under S.92. When the
respondent applied to the Tribunal for amendment, he took a procedural
step, and that he was clearly entitled to do under S. 90(2). The
question of power arises only with reference to the order to be passed
on the petition by the Tribunal. Is it to be held that the presentation
of a petition is competent, but the passing of any order thereon is
not? We are of opinion that there is no substance in the contention
either."
F
Hence, the jurisdiction or the power of the arbitral tribunal is prescribed
under the Act and if the award is do hors the said provisions, it would be,
on the face of it, illegal. The decision of the Tribunal must be within the
bounds of its jurisdiction conferred under the Act or the contract. In exercising
jurisdiction, the arbitral tribunal can not act in breach of some provision of
G substantive law or the provision of the Act.
The question, therefore, which requires consideration is-whether the
award could be set aside, ifthe arbitral tribunal has not followed the mandatory
procedure prescribed uhder Section 24, 28 or 31(3), which affects the rights
of the parties? Under sub-section (I )(a) of Section 28 there is a mandate to
H the arbitral tribunal to decide the dispute in accordance with the substanuve
,..
OIL & NATURAL GAS CORPORATION LTD. '"SAW PIPES LTD. [SHAH, J ] 707
law of the time being in force in India. Admittedly, substantive law would A
include the Indian Contract Act, the Transfer of Property Act and other such
laws in force. Suppose, if the award is passed in violation of the provisions
of the Transfer of Property Act or in violation of the Indian Contract Act, the
question would be-whether such award could be set aside? Similarly, under
sub-section (3), arbitral tribunal is directed to decide the dispute in accordance B
with the terms of the contract and also after taking into account the usage
of the trade applicable to the transaction. If arbitral ignores the terms of the
contract or usage of the trade applicable to the transaction, whether the said
award could be interfered? Similarly, if the award is non-speaking one and is
in violation of Section 31(3), can such award be set aside? In our view, reading
Section 34 conjointly with other provisions of the Act, it appears that the C
legislative intent could not be that if the award is in contravention of the
provisions of the Act, still however, it couldn't be set aside by the Court. If
it is held that such award could not be interfered, it would be contrary to basic
concept of justice. If the arbitral tribunal has not followed the mandatory
procedure prescribed under the Act, it would mean that it has acted beyond
its jurisdiction and thereby the award would be patently illegal which could D
be set aside ~nder Section 34.
The aforesaid interpreta<ion of the clause (v) would be in conformity
with the settled principle of law that the procedural law cannot fail to provide
relief when substantive law gives the right. Principle is there cannot be any E
wrong without a remedy. In M V. Elisabeth and Ors. v. Harwan Investment
& Trading Pvt. ltd, (1993] Supp. 2 SCC 433 this Court observed that where
substantive law demands justice for the party aggrieved and the statute has
not provided the remedy, it is the duty of the Court to devise procedure by
drawing analogy from other systems of law and practice. Similarly, in Dhanna
Lal v. Kalawatibai and Ors., [2002] 6 SCC 16 this Comi observed that wrong F
must not be left unredeemed and right not left unenforced.
Result is if the award is contrary to the substantive provisions of law
or the provisions of the Act or against the terms of the contract, it would be
patently illegal, which could be interfered under Section 34. However, such
failure of procedure should be patent affecting the rights of the parties.
G
What Meaning Could be assigned to 1he phrase 'Public Policy of
India'?
The next clause which requires interpretation is clause (ii) of subsection 2(b) of Section 34 which inter alia provides that the Court may set H
708
SUPREME COURT REPORTS
[2003] 3 S.C.R'.
A aside arbitral if it is in conflict with the 'Public Policy oflndia'. The phrase
'Public Policy of India' is not defined under the Act. Hence, the said term is
required to be given meaning in context and also considering the purpose of
the section and scheme of the Act.