# SETH THAW ARDAS PHERUMAL v. THE UNION OF INDIA

- **Citation:** [1955] 2 S.C.R. 48
- **Court:** Supreme Court of India
- **Decided:** 1955
- **Bench:** Vivian Bose, JAGANNADllAOAS, Sinha
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/seth-thaw-ardas-pherumal-v-the-union-of-india-1505
- **Pages:** 19

## Headnote

Arbitratio11 Act, 1940, (Act Xvi 1940), .-. l6t /)(c)-Arbitratio11
-Award-Legality thereof-\Flwn ca" be challenged-Arbitratvr·-
Condition precedent for his jurisdiction-Award-\\i'hen Jinal-Both
parties specifically referring a qut?stiun of law for the decision 11/
aTbitrator-Cases where question of law specifically referred aud
cases where decision incidentally tnaterial (however necessary) in
order to decide the question actually ref~rred-Distinction between
-w·rong
construction
of
contract-Error
of
law-Iuterest
awarded-Contract not providing for it-Require1nents of Interest
Act, 1839 !Act XXXII of 1839) not fulfilled--Specific type of loss
actually contemplated by the partie.--Expres.- stipulatio" that
no
damage will be payab~e-Parties bound down to the agreementAgreement on which s:;,it based no1 found in tlie written
contract
but implied under s. 9 of the fodian Contract Act, 1872-Matter
not covered by the arbitration clause---Error of law apparent au the
face of the award.
'The appellan;, a contractor, entered into a contract with the
Dominion of India for the supply of bricks. A clause in the contract required all disputes arising out of or relating to the contract
tq be referrt:d to arbitration. Disputes arose and the matter was duly
referred. The arbitrator gave an award in the contractor's favour.
The Union Government, which by thc'Il had displaced the Dominion
of India, contested the a\vard on a nunibcr of grounds.
Held: (1) that it is not enough for the contract to provide for
arbitration; more is necessary.
An arbitrator only gets jurisdiction
when either, both the parties specifically agree to refer specified
matters or, failing that, the court compels them to do so under the
arbitration clause if the dispute is covered by it;
(2) the legality of an award cannot be challenged on facts, but
it can be challenged on questions of law provided the illegality is
apparent on the face of the award: s. 16'l)!c) of the Arbitration
Act;
(3) the only exception is when both parties specifically refer a
question of law for the decision of the arbitrator. In that event
they are hound by his decision on that particular question as well as
by his decision on the facts.
But a distinction must be drawn between cases in which a question of law is specifically referred and
those in which a deci,.ion is incidentally material (however necessary) in order to decide the question actually referred. The law
about this is the sallll' in India as in England. 1923 A.C. 395 and
1933 A.C. 592, followed. 54 C.W.N. 74 at 79, 50 I.A. 324 at 330 &
•
r
2 s.c.R.
SUPREME COURT REPORTS
49
331, 54 I.A. 427 at 430, 29 I.A. 51 at 60, 1942 A.C. 356 at 368 l'eferred to and 1950 S.C.R. 7.92 at 798, explained;
1955
Seth Thawa•das
Quaere: -Whether the courts will interfere when a question of
Phe~imal
law is specifically referred if the arbitrator acts illegally in deciding The Unioi; of India
it, such as deciding on inadmissible evidence or on principles of
construction which the la\Y· does not countenance. 1923 A.C. 395 at
409, refen:.ed to;
( 4) a wrong construction of the contract is an error of law and
can be challenged provided the error appears on the face of the
award;
(5) so is the awarding of interest when the <:ontract does not
provide for interest and the requirements of the Interest Act are not
fulfilled: 65 I.A. 66, referred to.
Quaere: whether the Interest Act applies to arbitrations~
(6) when a specific type of loss is directly contemplated by the
parties to a contract and they expressly stipulate that no damages
will. be payable in respect of it they must be bound down to their
agreement and any claim for damages in respect of such loss must
be dismissed;
(7) when the agreement on which the suit is based is not to be
found in a contract which has been reduced to writing but has to be
implied under s. 9 of the Contract Act then the matter is not covered
by an arbitration clause of the kind referred to above because the
dispute in such a case ari

## Text

_Characters 0–39,912 of 40,782. This is a partial read: ask again with offset=39912 for what follows._

1955
March 24
48
SUPREME COURT REPORTS
SETH THAW ARDAS PHERUMAL
v.
THE UNION OF INDIA
(and connected <lppeal)
[1955] •
[VIVIAN BOSE, JAGANNADllAOAS and SINHA, J.J .J
Arbitratio11 Act, 1940, (Act Xvi 1940), .-. l6t /)(c)-Arbitratio11
-Award-Legality thereof-\Flwn ca" be challenged-Arbitratvr·-
Condition precedent for his jurisdiction-Award-\\i'hen Jinal-Both
parties specifically referring a qut?stiun of law for the decision 11/
aTbitrator-Cases where question of law specifically referred aud
cases where decision incidentally tnaterial (however necessary) in
order to decide the question actually ref~rred-Distinction between
-w·rong
construction
of
contract-Error
of
law-Iuterest
awarded-Contract not providing for it-Require1nents of Interest
Act, 1839 !Act XXXII of 1839) not fulfilled--Specific type of loss
actually contemplated by the partie.--Expres.- stipulatio" that
no
damage will be payab~e-Parties bound down to the agreementAgreement on which s:;,it based no1 found in tlie written
contract
but implied under s. 9 of the fodian Contract Act, 1872-Matter
not covered by the arbitration clause---Error of law apparent au the
face of the award.
'The appellan;, a contractor, entered into a contract with the
Dominion of India for the supply of bricks. A clause in the contract required all disputes arising out of or relating to the contract
tq be referrt:d to arbitration. Disputes arose and the matter was duly
referred. The arbitrator gave an award in the contractor's favour.
The Union Government, which by thc'Il had displaced the Dominion
of India, contested the a\vard on a nunibcr of grounds.
Held: (1) that it is not enough for the contract to provide for
arbitration; more is necessary.
An arbitrator only gets jurisdiction
when either, both the parties specifically agree to refer specified
matters or, failing that, the court compels them to do so under the
arbitration clause if the dispute is covered by it;
(2) the legality of an award cannot be challenged on facts, but
it can be challenged on questions of law provided the illegality is
apparent on the face of the award: s. 16'l)!c) of the Arbitration
Act;
(3) the only exception is when both parties specifically refer a
question of law for the decision of the arbitrator. In that event
they are hound by his decision on that particular question as well as
by his decision on the facts.
But a distinction must be drawn between cases in which a question of law is specifically referred and
those in which a deci,.ion is incidentally material (however necessary) in order to decide the question actually referred. The law
about this is the sallll' in India as in England. 1923 A.C. 395 and
1933 A.C. 592, followed. 54 C.W.N. 74 at 79, 50 I.A. 324 at 330 &
•
r
2 s.c.R.
SUPREME COURT REPORTS
49
331, 54 I.A. 427 at 430, 29 I.A. 51 at 60, 1942 A.C. 356 at 368 l'eferred to and 1950 S.C.R. 7.92 at 798, explained;
1955
Seth Thawa•das
Quaere: -Whether the courts will interfere when a question of
Phe~imal
law is specifically referred if the arbitrator acts illegally in deciding The Unioi; of India
it, such as deciding on inadmissible evidence or on principles of
construction which the la\Y· does not countenance. 1923 A.C. 395 at
409, refen:.ed to;
( 4) a wrong construction of the contract is an error of law and
can be challenged provided the error appears on the face of the
award;
(5) so is the awarding of interest when the <:ontract does not
provide for interest and the requirements of the Interest Act are not
fulfilled: 65 I.A. 66, referred to.
Quaere: whether the Interest Act applies to arbitrations~
(6) when a specific type of loss is directly contemplated by the
parties to a contract and they expressly stipulate that no damages
will. be payable in respect of it they must be bound down to their
agreement and any claim for damages in respect of such loss must
be dismissed;
(7) when the agreement on which the suit is based is not to be
found in a contract which has been reduced to writing but has to be
implied under s. 9 of the Contract Act then the matter is not covered
by an arbitration clause of the kind referred to above because the
dispute in such a case arises out of and relates to the implied agreement and not to the written contract; 1942 A.C. 356 at 371, referred
to.
CIVIL APPELLATE J!JRISDICTION:
Civil Appeal
No. 260 of 1953 and connected appeal (C.A. No. l2 of
1954).
Appeals from the Judgment and Decree
dated
the 11th day of May 1951 of the High Court of Judicature at Patna in Miscellaneous Appeal No. 253 of
1950 and in appeal from Original Order No. 252 of
1950 arising out of the order dated the 11th day of
May 1951 of the Court of Subordinate Judge, Dhanbad
in Suit No. 34 of 1949 and in Title Suit No. 27 of 1949
respectively.
Mahabir Prasad, Advocate-General for the State
of Bihar (S. P. Varma and M. M. Sinha, with him). for
the appellant (In Civil Appeal No. 260 of 1953).
Mahabir PrasaZ dvocate-General for the State of
Rihar (M. M. Sinha for R. C. Pmsad. with himl for
the appellant (Jn Civil Appeal No. 12 of 1954).
'
•
1955
Sith Tha-.JJardas
l'hcrlunal
50
SUPREME COURT REPORTS
[1955]
· G. K._ Daphtary, Solicito}-General fo~>lndia (Porus
A •. ~JJfehta and P. G. Gokhale, with him), for the respondent (In both the Appeals). -
·-
J
TllcUnio:·o/ lnd;a
- - 1955. l\Iar6h 24.
The Judgment of the CourtWas delivered by
_ BosE J.-_ This appeal and Civil Appeal No. 12 of
l!J54, which will also be governed by this judgment,
raise the same points though there are some differences
in the facts.
\Ve_ will deal with Civil Appeal No. 260
of 1953 first.
_.
The suit there related to an arbitration matter.
The appellant before us, whom- it will be convenient
to call the contractor, entered into a contract with
the Dominion of -India through an Additional Chief
Engineer of the C.P. \V.D. on l-ll-1945 for the supply
of bricks to the C.P.\V.D., a department of the Dominion Government. Disputes arose about a number of
matters. -Clause 14 of the agreement provided that
all disputes arising out of or relating to the contract
should be referred to the Superintending Engineer of
the Circle for the time being. Accordingly, there was
a reference on 21-1-1949 and an award followed on
8-5-l!l49. It was filed in the Court of the Subordinate
Judge, Dhanbad, and the contractor prayed that it be
accepted and that a decree be passed in terms of it.
The Dominion of India filed objections under section
30 of the Arbitration Act, 1940 and prayed that the
award be set aside and alternatively that it be modi-
' "4
fied or corrected.
The contractor's application was
registered as a suit under section 20(2) of the Act and
a decree was passed in terms of the award on
18-3-1950.
-
By that time the Constitution had come into force
and the Union of India replaced the Dominion of India
as a defendant.
The Union of India filed an appeal
to the High Court.
The appeal was allowed in part.
The contractor thereupon appealed to this Court.
·
The dispute that was referred to the arbitrator consisted of 17 heads of claim but only three of them are
t
contested here, namely items 5, 8 and 17.
2 S.C.R.
SUPREME COURT REPORTS
51
In the 5th head of claim the contractor claimed Rs.
JYSj
75,900 as the price of 88 lacs of katcha bricks that
Serh Thall'arda.1·
h
k
h
Pher111nal
were destroyed by rain.
T ese bric s were not t e
v.
subject-matter of the contract but the contractor put The Union of India
his claim in this way.
no.e.t.
The contract was for the supply of 2} crores of
pucca bricks which had to be delivered according to
the followil)g schedule30 lacs by 25-1-46
50 lacs by 25-2-46
55 lacs by 25-3-46
55 lacs by 25-4-46
60 la'cs by 25-5-46.
Delivery was to be at the kiln site. In order to keep
to this schedule the· contractor had to think
ahead
and work to a particular time table. First, he had to
prepare katcha or unbaked bricks and place them in
his kilns for baking. While this lot was baking he
had to prepare and stock another lot of katcha bricks
ready to take the place of the baked bricks as soon as
they were removed, It was the duty of the C.P.W.D.
to remove these bricks as soon as they were ready for
delivery, that is to say, as soon as they were fully
baked. At a certain stage of the contract the C.P.W.D ..
failed to remove the backed bricks which were ready ·
for delivery and removal. This caused a jam in the
kilns and prevented the contractor from placing afresh
stock of unburnt bricks in the kilns, and in the meanwhile his stock pile of katcha bricks ready for baking
kept on mounting up: Had everything been done to
time the n crores of bricks would have been delivered
before the- rains set in.
But owing to the default
of the C.P.W.D. in not removing the burnt bricks··
which were ready for removal, delay occurred in the
time table and the rains set in with the result that 88
lacs of katcha bricks were destroyed by the
rains.
As this loss was occasioned by the default of the
C.P.W.D. the contractor claimed that he should be paid
their price.
The reply of the Union Government was two-fold.
First it contended that the katcha bricks formed· no
part of the contract and even if it w:1s at fault in not
52
SUPREME COURT" REPORTS
[1955]
/955
taking delivery of the burnt bricks in time all that it
Setlr T!rawarda; could be held liable for would be for breach of that
Plrer:_mat
contract; and said that the Joss that was occasioned by
The Union 'If· India the damage caused to the katcha bricks which formed
B7'seJ.
no part of the contract was too remote. Secondly,
that compensation for this Joss could not in any event
be claimed because this kind of situation was envisaged by the parties when the contract was made and
they expressly stipulated that the Dominion Government would not be responsible. The Union Government relied on additional clause 6 of the agreement
which is in these terms:
"The department will not entertain any claim for
idle Jabour or for damage to unburnt bricks due to any
c,ause whatsoever".
The arbitrator held that this clause was not meant "to
absolve the department from carrying out their part
of the contract" and so he awarded the contractor Rs_
64,075 under tliis head.
We are clear that the arbitrator went wrong in law.
Government departments have their difficulties no less
than contractors. There is trouble with labour, there
is the likelihood of machinery breaking down in out
of the way places and so forth; there was also the
danger of thunder sto.rms and heavy showers of rain
in the month .of May: it will be remembered that the
last date of delivery was 25-5-46.
If, with that in
view, Government expressly stipulated, and the contractor expressly agreed, that Government was
not
to be liable for any loss occasioned by a consequence
as remote. as this, then that is an express term of the
contract and the contractor must be tied down to it.
If he chase to contract in absolute terms
that was
his affair. But having contracted he cannot go back
on his agreement simply because it does not suit him
to abide by it. This is not to say that Government
is absolved froni all liability, but all it can be held
responsible for is for damages occasioned by the breach
of its contract to remove the pucca bricks which it
had undertaken to remove·. But what would such a
breach entail?
2 S.C.R.
SUPREME COURT REPORTS
53
The contractor had a duty under section 73 of the
l955
Contract Act to minimise the loss, accordingly he would
Seth Thawardas
have had the right to remove the bricks himself and
Pherumat
stack them elsewhere and claim compensation for the The Unio~· of India
loss so occasioned; and indeed two of his heads of claim
(not in dispute here) relate to that.
He has
been
awarded Rs. 11,744-11-0 under claim No. 4 for the
extra load in connection with the stacking of 1 crore
7 lacs of bricks due to the accumulation at the kiln
site owing to the department's failure to work to its
part of the time table, and in addition, he has been
given Rs. 15,500 under claim 13 for the cost of levelling and dressing land to enable him to stack these
extra bricks.
Alternatively, he could have sold the bricks in the
market and claimed the difference in price, but ordinarily he could not have cl;;timed compensation for
damage done to the katcha bricks unless he could have
shown that that kind of damage, ordinarily too remote,
was expressly contemplated by the parties when the
contract was made: section 73 of the Contract Act.
Here it is clear that this was in their express contemplation and they chose to provide against such a
contingency by making clause 6 an express clause in
their contract. There can therefore be no doubt that
the arbitrator was wrong in his law. His construction
of the terms of the contract was at fault. The question now arises whether his decison on this point is
final despite it being wrong in law.
In India this question is governed by section 16(1)
(c) of the Arbitration Act of 1940 which empowers a
Court to remit an award for reconsideration.
"where an objection to the legality of the award
is apparent upon the face of it".
This covers cases in which an error of law appears on
the face of the award. But in determining what such
an error is, a distinction must be drawn between cases
in which a question of law is specifically referred and
those in which a decision on a question of law is incidentally material (however necessary) in
order to
decide the question actually referred. If a question of
law is specifically referred and it is evident that the
8--8 SCT 'ND 182
.BoseJ.
•
54
SUPREME COURT REPORTS
[1955]
1955
parties desire to have a decision from 'the arbitrator
Seth Thawardas
about that rather than one from the Courts, then the
Pher;_mal
Courts. will not interfere, though even there, there is
Th• Union of India authonty for the view that the Coutts will interfere
if it is apparent that the arbitrator has acted illegally
80"' J.
in reaching his decision,
that is to say, if he has
decided on inadmissible evidence or on principles of
construction that the law does not countenance
or
something of that nature. See the speech of Viscount
Cave in Kelantan Government v. Duff Development
Co.(') at page 409. But that is not a matter which arises
in this case.
The law about this is, in our opinion, the same in
England as here and the principles that govern this
class of case have been reviewed at length and set
out with clarity by the House of Lords in F. R.
Absalom Ltd. v. Great Western (London) Garden Village {iociety (') and in Kelantan Government v. Duff
Development Co.('). In Durga Prasad v. Sewkishendas(')
the Privy
Council
appHed the law
expounded in
A bsalom·'s case(') to India: see also Champsey Bhara
& Co. v. Jivraj Balloo Spinning and Weaving Co.(')
and Saleh
Mohomed Umer Dossal v. Nathoornal
Kessamal('). The wider language used
by Lord
Macnaghten in Ghulam Jilani v. Muhammad Hassan(")
had reference to the revisional powers of the High
Court under the Civil Procedure Code and must be
confined to the facts of that case where the question of
law involved there namely limitation, was specifically
referred. An arbitrator is not a conciliator and cannot
ignore the law or misapply it in order to do what he
thinks is just and reasonable. He is a tribunal selected
bv the parties to decide their disputes according to law
and so is bound fo follow and apply the law, and if .he
does not, he can be set right by the Courts provided
his error appears on the face of the award. The single
exception to this is when the parties choose specifically to refer a question of law as a separate and dis-
. '
tmct matter.
(I) [19231 A.C. 395.
(3) 54 C W.N. 74.79.
(5) 54 I.A. 427, 430.
(2l [1933] A.C. 592.
(4) 50 I.A. 324. 330 & 331.
(6) 29 I.A. 51, 60.
2 s.c.R.
SUPREME COURT REPORTS
55
Reference was made to a decision of this Court in
1955
A_. M. Mair & Co. v. Gordhandass Sagarmul!(') where
Seth Thawardas
Fazl Ali, J. quoted a passage from Viscount Simon's
Plterumal
speech in Heyman V. Darwins Ltd. ('~where the lear- The U11io~· of India
ned Lord Chancellor (Viscount Simon) in
turn
·quoted ·from Lord Dunedin in another case. It was
argued on the basis of this that if you have to have
recourse to the contract to establish your case, then
the dispute must fall within the arbitration clause.
That is undeniable but it is not enough that the dispute should fall within the clause. It' is also necessary that the parties should define what the dispute
is and agree to refer the dispute so set out and defined
to arbitration, or,. if they do not, that the Court
should compel them to do so: (see Lord Macmillan in
Heyman's case(') just cited at pages 369 and 370). If,
therefore, rio specific question of law is referred, either
by agreement or by compulsion, the decision of the
arbitrator on that is not final however mueh it may
be within his jurisdiction,
and indeed essential, for
him to decide the question incidentally. Lord Russell
of Killowen and Lord Wright were both in the earlier
case, F. R. A bsafon Ltd. v. Great Western (London)
Garden Vi11age Society ('); as well as in
Heyman's
case(') and they would have pointed to any distinction had there been a likelihood of conflict; but in
fact there is none and we do not read Fazl Ali J.'s
judgment as a decision to . the contrary.
We have next to see w1i.ether the arbitrator was
specifically asked to construe clause 6 of the contract
or any part of the contract, or whether any question
of law was specifica11y referred. We stress the word
"specifically" because parties who make a reference
to arbitration have the right to insist that the tribunal of their choice shall decide their dispute according to law, so before the right can be denied to them
in any particular matter. the Court must be very sure
that both sides wanted the decision of the arbitrator
on a point of law rather than that of the Courts and
that they wanted his decision on that point to be
final.
(J) 1950 S.C.R. 792 at 798. 12) 1942 A.C. 356 at 368. (3) 1933 A.C. 592.
BoseJ.
•
1955
Seslt Thawardas
Pherumal
v.
The Union of India
BoseJ
56
SUPREME COURT REPORTS
[1955]
The clause in the contract that requires disputes
about the contract to be
referred to arbitration is
clause 14 and is in the following terms:
"Except where otherwise provided in the contract
all questions and disputes relating to the meaning of
the specification and instructions hereinbefore mentioned and as to quality of materials or ·as to any
other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, specification, instructions, orders or these conditions, or otherwise concerning the supplies whether
arising during the progress of delivery or after the
completion of abandonment thereof shall be referred
to the arbitration of the Superintending Engineer of
the Circle for the time being in the manner provided
by law relating to arbitration for the time being in
force who after such investigation as he may think
proper shall deliver his award which shall be final,
conclusive and binding on all parties to the contract".
The dispute sprang out of a series of claims made
in a number of letters written by the contractor to
the Additional Chief Engineer, C.P.W.D. and culminated in a petition, Ex. B(l), in which the contractor
summarised his claims. The document is not dated.
On receipt of this, someone on behalf of the C.P.W.D.
invoked the jurisdiction of the arbitrator. That letter
has not been filed. The arbitrator then wrote .to the
contractor and asked him to submit a statement of
claim. That letter has not been filed either but reference
is made to it in Ex. C(l), the statement of claim which
the contractor filed in response to that letter. As the
material documents setting out the terms of reference
are not here, we were asked by both sides to infer
what the terms were from this statement of claim and
the recitals in the award. The learned counsel for the
contractor relied on the following:
In the statement of claim--
" Item 5.-Loss of katcha bricks ...... Rs. 75,900.
The chief reason of the destruction of these hricks
was the failure
of the depa.rtment to
lift
the
2S.C.R.
SUPREME COURT REPORTS
57
monthly quota· of bricks ...... The argument of the de1955
partment that they are not liable to \:!Ompensate us
Se111 Thawardas
On this account because Of clause 6 Of the agreement
Plieruma/
.
~
IS not correct.
Tile U11io11 of J11dia
Clause 6 refers to only such cases over whi~h
Bose J.
the department has no control. But if the department would have lifted the bricks (this was entirely
under their control) then no such loss would have occurred. Also be it noted that clause 6 refers only to
'damage' and not to 'destruction' .................. Damage
means~ only partial loss ........... .it cannot mean total
destructibn".
·
The award states-
"The statement of claims sulnn;tted by the contractor contains seventeen items in respect of which
the contractor claimed
a
total
payment
of Rs.
4, 76,138-12-0 plus interest ... , ....... .i.e.,
approximate
total amount claimed: Rs.
5,03,803-12-0 as detailed
below".
Then follow the seventeen items of which item 5 is·-
"Payment for katcha
bricks destroyed by rain:
Rs. 75,900".
The body of the award deals with this as follows:
"
Claim No. 5
Payment for 88 lacs of katcha bri:::ks destroyed
by rain.
The contractor argued etc ........... .
The Executive
Engineer
stated ... _. ........ The
C.P.W.D. moreover were safeguarded by clause 6 of
the contract. ...................... .
The contractor maintained that clause 6 of the
contract could not be invoked when the department
was at fault as in this case. Clause 6 was meant to
cover contingencies
which were not of the department" s own making.
·
I hold that the removal of the bricks in such a
manner or to prevent accumulation in excess of 60
lacs was an implied contractual obligation on the part
of the C.P.W.D ..................... .I further hold that the
C.P.W.D. cannot take shelter hehind clause 6 of the
contract. This
clause is not. in my opinion. meant
58
SUPREME COURT REPORTS
[1955J
JY55
to absolve the
department from carrying ou~ their
Seth Jhawardas part of the contract. It is
impossible not to admit
Phmmwl
this without offending the rudiments of common sense
v.
.
"
The Union ef India reason1ng .
BoseJ.
We are of opinion that this is not the kind of specific reference on a point of law that the law of arbitrntion requires. In the first place, what was shown to
us is no reference at all. It is only an incidental matter
introduced by the Dominion Government to repel the
claim made by the contractor in general terms under
claim No. 5. In the next place, this was the submission of the contractor alone. A reference rc4uires the
assent of both sides. If one side is not prepared
to
submit a given matter to arbitration when there is an
agreement between them that it should be referred.
then recourse must be had to the Court under section
20 of the Act and the recalcitrant party can then be
compelled to submit the matter under sub-section (4).
In the absence of either, agreement by horh sides about
the terms of reference, or an order of the Court under
section 20(4) compelling a reference, the arbitrator is
not vested with the necessary exclusive jurisdiction.
Therefore, when a question of law is the point at
issue, unless both sides specifically agree to refer it and
agree to be bound by the arbitrator's decision, the
jurisdiction of the Courts to set an arbitration right
when the error js apparent on the face of the award
is 'lot ousted. The mere fact that both parties submit incidental arguments about a point of law in the
course of the proceedings is not enough. The language of Lord Wright in F. R. A bsalom Ltd. v. Great
Western (London) Garden Village Society ('), a case
similar to this so far as this
point is concerned, is
apposite here-
"There is here no.submission of any specific question of law as such and as a specific question of law;
no doubt incidentally, and indeed necessarily, the
arbitrator will have to decide some questions on the
construction of the building contract, but the two
matters submitted"are both
composite questions of
Jaw and fact: there is no express submission of the
(I) [1933) A.C. 592, 616.
2 S.C.R.
SUPREME COURT REPORTS
59
true effect of the contrnct on the
basis of undis1955
puted facts, as in the Kelantan case(') or as a separate
Seth Thawardas
and distinct matter on facts to be separately assumed
Phe~'.mal
or found, as in In re King and D11vee11(') .................. The U11io11 of India
The arbitrator was not being asked simply and specinoseJ.
fically to decide, upon some agreed or assumed basis
of fact. the true interpretation of either clause 26 or
clause 30 of the
conditions or of both together; he
was being required to
make an
award on the two
matters submitted on whatever questions of fact and
law might emerge".
Clause 32 of the contract in the House of Lords case
was the equivalent of clause 14 in ours. It ran--
"Provided
always that in case any
dispute or
difference shall arise ............... as to the construction
of the contract or as to any matter or thing arising
thereunder ......... such dispute shall be and is hereby
referred to the arbitration and final decision of etc.''
The arbitrator relied on that to invest him with jurisdiction to determine, as a matter of law, the construction of clauses 26-30 of that contract. The
House of Lords held that in the absence of a specific
reference about the construction of the contract the
jurisdiction of the Courts was not taken away. Lord
Russell of Killowen put it this way at page 610-
'·No specific question of construction or of law
wa~ submitted. The parties
had,
however, been
ordered to deliver pleadings. and by their statement
of claim the contractor had claimed
th~~t the arbitrator should under his powers revise the last certificate issued etc ................... It is at this point that the
question of the construction 0f condition 30 arose as
a question of law. not specifically suhmittcd, but material in the decision of the matters which had been
submitted. This q11estion of law the arbitrator has
decided; but if upon the face of the award he has decided it wrongly his· decision is, in my opinion. open
to review by the Court".
That is exactly the position
here.
Simply because
the matter was referred to incidentally in the plead-
(1) [19231 A.C. 395.
(2) [1913) 2 K.B. 32, 36,
60
SUPREME COURT REPORTS
[ 1955]
1955
ings and arguments . in
support of, or against, the
Seth Thawbrdas general issue about liability for damages, that is l}Ot
Phemmal
enough to clothe the arbitrator with exclusive jurisT/re Unio~· of India diction on a point of law.
noseJ.
The next question is whether the error is apparent
on the face of the award. That, in our opinion, is
clear from the
passages we have quoted from the
award.
We hold that clause 6 ex;pressly relieves the Union
Government of all liability under this head of claim
and that the arbitrator was wrong in awarding any
sum on that account.
The next head in dispute is item No. 8 in the statement of claim:
"Cost of additional wages paid to the coolies on
account of non-supply of ration and cloth-Rs.
51,495".
Here again no specific question of law was referred,
so all we have to see is whether there is an error of
law apparent on the face of the award.
The contractor put his case as ,follows in the statement of claim:
"At the time when this work was allotted to us
there was rationing system in the locality. As per
conditions of contract we were· bound not to employ
local labour and we had to imnort coolies from far
olT places. We had in ouF employ about 1800 coolies
and it was an impossibility to arrange their ration
from open market. This difficulty was brought to the
notice of the authorities concerned, and they promised
us to supply ration. It was only after this promise
tha.t we signed the agreement. ........ From a perusal of
these letters it is clear that the department promised
us to supply ration .. .... These circumstantial evidences
are sufficient enough to show" that there was a mutual
understanding between the parties that ration will be
supplied. In the eyes of law even
circumstantial
evidence is sufficient to
prove that such a promise
was made. Any breach of that promise makes the
department legally
liable
to compensate for that
loss ...... Apart froin the legal
responsibility it
was
also a moral
responsibility for the department
to
supply ration".
2 S.C.R.
SUPREME COURT REPORTS
61
This claim, therefore, was not grounded on any clause
1955
of the contract, nor was it said to be implied in the
Seth Thawardas
contract. What was relied on was a collateral proPherumal
mise evidenced, not by the contract, but by two The U11io~; of India\
letters written by "the. department" and a
promise
BoseJ.
by "the authorities concerned"; and later this promise
is tnrned into a "mutual understanding" and to a
"moral responsibility" in addition to a legal one.
The arbitrator dealt with this as follows. He began
by saying-
"The contractor
his tender on 25-9-45
that the department
arrangements. etc.''
stated that when he submitted
he did so in the hona fide belief
would
make the
necessary
Then he sets out the following dates. On 1-11-45 the
contractor was told that his tender had been accepted.
On 9-11-45 the contractor
"warned" the Executive
Engineer about his "immediate requirements in
respect of rations". The
contract was finally accepted
and signed on 22-11-45.
Now it is admitted that the contract contains no
ciause about rations and it is also evident that the
question was not raised when the tender was accepted
on behalf of the Dominion Government. The question was raised in a letter to the Executive Engineer
and the contractor si!:!ned the contract without waiting for a reply.
,
It is well settled that governments can onlv he
bound by contracts that are entered into in a p·arti··
cular wav and which are signed by the proper auth0rit v. A reference to the
agreement. Ex.
AO), will
show that it was accented on behalf of the Dominion
Government by the Additional Chief Fn.iiineer and not
bY an Executive Engineer. A letter written to the
Executive En!!:ineer would
therefore have no effect
and even if it he assumed that the letter was forwarded to the Addition::il Chief Enl!ineer for consideration, what does it amount to? A tender embodvinl!
certain terms is suhmitted and is accented on 1-11-4".
B0th sides are a.l!reed on all matters' contained ih it
and their conduct shows that hoth side~ indic::iterl
thCit the contract should be reduced to writing. Re9-8 SCIIND'82
62
SUPREME COURT REPORTS
[19551
1955
fore the agreement is signed, one party wants to inS•th Thawardas elude a further
condition in the contract. We will
Pherumal
assume that the reque~t was made to the other conTh< Unio~· of India tr acting party. But
without wailing fo~ the
assent
Bose J~
of the other side, both sides accept and sign the contract as it existed before the fresh suggestion was made.
It is an error in law to dednce from this that there
was acceptance ofl the fresh proposal. On the contrary.
the legal conclusion is that the new suggestion was
dropped and that the contractor was
content to
accept the contract as it was without this condition.
In any case, a person cannot be bound by a one-sided
offer which is never accepted, particularly when the
parties intend that the contract should be reduced to
writing. That is the whole point of insisting on a
document. It excludes speculation as to what was
and what was not agreed to however much the matter
might have been raised by one of the partie~ dur~ng
the stage of negotiation.
The arbitrator continues that the contractor stated
that-
"it was a well
known and established fact that
Sindri was a rationed area; that the C.P.W.D. were
giving rations at controlled rates to their employees
and contractors through arrangements with the Joe~ I
Ci•.1il Supply Authorities; that nobody working under
the C.P.W.D. was
allowed
to
make
independent
arrangements or approach the Civil Supply Authorities direct"
and the contractor contended that the verv fact that
he tendered such low rates showed that he ·exvected to
supply his labourers with rations at controlled rates.
The arbitrator then sets out some more of the c0111ractor's contentions and from them concludes that
"there was an implied contractual obligation for
the C.P.W.D. to make available controlled rations to
the contractor and that this obligation '.\'as not fulfillecl with due diligence and care".
He accordingly awarded Rs. 40.000 as compensation
under this head.
The error is apparent. Facts must he based either
on evidence or on admissions; they cannot be found to
2 S.C.R.
SUPREME COURT REPORTS
63
exist from a mere
contention by one side especially
1955
when they are expressly denied by the other. The
Seth Thawardas
inference from the facts stated above is th&~ the conPherumal
tractor entered into the agreement with his eyes open The Unio~· of India
and whatever his one-sided hopes may have been he
was content to enter into the agreement as it stood
without binding the other side to the uew conditions
and without even waiting to ascertain the reaction of
the other side to his further proposals.
It has to be remembered that rationing was not a
111atter that was under the direction and control of
the Dominion Government. It was a local matter
handled by the then Provincial authorities and under
their direction
and
control. The C.P.W.D.; as a.
department of the Dominion Government, was not concerned with rationing except that its employees had to
submit to rationing like everybody else in the Sindri
area. This confusion between the Dominion Government and the Provincial Government occurs in the
arbitrator's opening sentence under this head where
he sets out the contractor's contention that
"commodities such as
rations and cloth which
were absolutelv essential for the maintenance of his
labourers and i1·hich 11·erl:' unda Govemml:'nt control".
As the arbitrator bases solely on the ..::ontrator's contentions it is evident that he failed to appreciate the
fact that the Dominion Government and the Provincial rationing authorities were separate entities distinct. from one another. The position accordingly
reduces itself to this: two persons, neither of which is
a part ot the Provincial Government or has any control
over rationing. chose to enter into an agreement for
work i-ri a rationed area. They insisted that their contract should be
reduced to writing, and that indeed
was essential, this being a contract with the Dominion
Government which was
incapable of contracting in
any other way; they agreed upon and concluded all
their terms; then. at the last minute, one side raised
a point about rationing but without waiting for a
repiy and without having the term entered in the
'
contract. he <;igned the contract as it stood before the
point was raised even during the negotiation. It is
Bose!.
• 64
SUPREME COURT REPORTS
(1955]
\
.
1955
an error in law to hold that any contractual obligation can be inferred or implied. from these .circumScth Thawardas
Pherunial
stances.,:· ·
·'
:
v.
Then there is still another error~
If this implied
.The Union.of India agreement about rations and cloth does not spring\ 1
-
out of the written contract but is to be inferred colBosc J.
laterally as a distinct and subsidiary contract, and
we gather that that is the finding, especially as reference was made to section 9 of the . Contract Act,
then that is not a contract 'to which the arbitration clause can apply. . Wide though it is, clause 14 is
confined to any matter relating to the written contract and if ration and cloth are not~ covered by the
written contract, they are not matters that relate to
it. If parties choose to add a fresh contract in addition to or in substitution for the old, then the. arbitration clause-cannot cover .the new contract. - See
Lord l\Iacmillan in Heyman v. Darwins Ltd.(') . .
The last item in dispute in this appeal is claim No.
17 about interest. The statement of claims sets out-_
"Item 17-Interest on the amount of money involved in this claim at the rate of Rs. 6 per cent.-·
Rs. 27,6~5. ·
·.
_ ·
.
This work was finished in l\Iay 1946 and it . was
proper for the department to have decided all our
claims at least by 31st December 1947 ....................... .
But this was not done ... Due to this a heavy amount
remained blocked up and we were compelled to take
money from our bankers on interest.
\Ve therefore pray for interest for '16 months from 1-1-48 to
31-4-49". .
.
The arbitrator held-
"The contractor's contention that his claims
should have been settled by January l!J48 is, in my
opinion, reasonable.
I therefore award interest at
6% for 16 months on the total amount of the awards
given i.e., Rs. 17,363".
_
Then the arbitrator sets out the amounts awarded
under each head of claim. A perusal of them shows·
that each head relates to a claim for an unliquidated
sum. The Interest Act, 1839 applies, as interest is
(1) (1942] A.C. 35G at 371.
2 S.C.R.
SUPREME COURT REPORTS
65
not otherwise payable by law in this kind of case (see
J<Jss
Bengal Nagpur Ry. Co. v. Ruttanji Rumji (')), but even
Seth Tlzawartlas
if it be assumed that an arbitrator is a "court" within
Plzerumal
the meaning of that Act, (a fact that by no means ap- Tlze U11io~· of India
pears to be the case), the following among other condition:, must be fulfilled before interest can be awarded under the Act:-.
(1) there must be a debt or a sum certain;
(2) it must be payable at a certain lime or otherwise;
(3) these debts or sums must be payable by virtue
of some written contract at a certain time;
(4) There must have been a demand in writing
stating that interest will be demanded from the date
. of the demand.
Not one of these elements is present, so the arbitrator
erred in law in thinking that he had the power to
allow interest simply because he thought the der:pand
was reasonable.
'
It was suggested that at least interest from the
date of "suit" could be awarded on the analogy of
section 34 of the Civil Procedure Code, 1908. But section 34 does not apply because an arbitrator is not a
"court" within the meaning of the Code nor does the
Code apply to arbitrators, and, but for section 34, even
a Court would not have the power to give interest
after the suit. This was. therefore. also rightly struck
oat from the award.
We pause to note that there was only a delay of
five days at the outside in the over-all picture. The
last date for removal of the last instalment of bricks
was 25-5-46 and the contractor says under this head
that the whole contract was
completed by the end
of May, 1946. lt is difficult to see how 88 lacs of
bricks could have been damaged by rain in the last
five· days of May, and if the damage occurred before it would have occurred anyway, for on the contractor's case he had to have a large stack of unbaked
bricks on hand ready to enter the kilns in order to
kcer race with his time tahle. However. that was a
(1)651.A.66.
BoseJ.
6'6
SUPREME COURT REPORTS
[ 1955)
1955
matter within the jurisdiction of the arbitrator and is
Seth Thawardas not ~ matter in which the Courts can interfere.
Pherumal
Th• Unio;· 0f Julia
That concludes Civil Appeal No. 260 of 1953 and
-
'
we now turn to the other appeal, Civil Appeal No. 12
BoseJ.
of 1954. Only two items are in dispute here. Heads
4 and 17 of the claim.
The overall pattern of the clai'm is the same as in
the other case. 'fhere was a contractor and he entered into an agreement containing the same terms
and conditions, except about the details of supply.
It was signed on the same day as the other and by
the same authority on behalf of the Dominion Government, and the matter went before the same arbitrator and the award in this case was given on 1-5-1949,
one week before the
other
award.