# smoR ELECTRICITY WORKS LTD v. TIIE GUJARAT ELECTRICITY BOARD AND ANR

- **Citation:** [1969] 3 S.C.R. 438
- **Court:** Supreme Court of India
- **Decided:** 1969-01-29
- **Bench:** C. Shah, V. Ramaswami, A. N. Grover
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/smor-electricity-works-ltd-v-tiie-gujarat-electricity-board-and-anr-4597
- **Pages:** 9

## Headnote

Elfctricity (Supply) Act, 1948, Ss. 2(8) and 19(1 )(b)(ii)-Expres.
sion 'maxinzum demand'-Construction of-Conditions precedent for en ..
cbling Electricity Board to nzake direct supply in area of a licensee.
The appellant carried on the business ~f generating and distributin.g
electriqal" energy within a specified area under a licence granted t? 1t
under the Indian
Electricity
Act, 1910.
The
respondent,
Gu1a_rat
Electricity Board agreed with the second respondent company to give
direct supply of electricity to its factory which wa~ wit~in the area of
supply of the appellant. The appellant brou·ght a suit agamst the respon- .
den~ for declaration that the agreement between the first and the second
respondents without its consent was illegal and ultra vires lhe powers of
the first respondent under the Electricity (Supply) Act., 1948, and sought
an injunction restraining the first respondent from
IDlplementmg
the
decision.
The appellant's case was that the first respondent was not entitled to
give direct supply to the second respondent as the "maximum 'demand"
of the appellant at the time of the request of the second respondent was
262 to 349 KVA between September and December, 1959, and therefore.
mdre than twice the "maximum dem3nd" of the second respondent which
had never exceeded 40 tq 45 KV A. The first respondent dontended, however, that the
0 maximum demand" of the appeJlant company at the time
of request was less than twice the "maximum
demand"
of 398 KVA
asked for bv the second respondent from the first respondent. The trial
court held that the first respondent's decision to give direct supply to the
second respondent was ultra vires its power under section 19 (l)(b)(ii)
of the Act. However, the first appellate court allowed an appeal and the
High Court dismissed a further appeal holding, inter alia, that by virtue
of s. 1'9(1)(b)(ii) the comparison required to be made was between the
maximum demand of the licensee on the Board at the time of request for
direct supply based on electiicity actually supplied and taken during some
reasonable period immediately preceding the time of request for dircc(
supply, and the maximum demand whi<1h the applicant wants to keep the
Board ready on tap when supplying electricity to the applicant.
On appeal to this the Court,
HELD : The appellant was entitled to the grant of a decree in terms
of the trial court's deci'ee.
The "maximum demand" as defined in section 2(8) of the Act has
relation only to an existing state of facts and there can be no maximum
demand in relation to a future period.
On a true construction of section
19(1) (b)(ii), what is required to be compared for determining the
applicability of the clause with the maximum demand of the licensee on
the Board at the time of request fo'r direct ~upply, was the
11maximun1
'demand" by the appliaant on the licensee at that time and not any hypothetical or anticipated demand which the applicant may call upon the
Board be ready to supply, The phrase "supplied and taken" in s. 2(8)
shows that the ascertaimnent of maximum demand is dependent upon the
electricity actually supplied and taken in any particular period in the p .. t
and not electricity which may be supplied and taken in a future period.
[444B]
B
c
D
E
F
G
A
B
c
D
E
F
G
H
ELECT\'. WORKS v. ELECTY. BOARD (Ramaswamy, J.)
439
There was no force in the respondent's contention that
the
words
"asked for by any such person" must be construed to mean any hypothe·
trical or anticipated demand which the applicant may call upon the Board
to be rc.:iJy to supply. Such an interpretation \vould be inconsistent with
the definition of .. maxin1urn demand" in section 2( 8) of the Act.
There
was no reason \.\hy 1he phrase "maximum denu-1nd'' in section 19(1)(b)(ii)
of the Act should be given two different meanings one for the Jicensee
and the· other for the consumer ask in~ for the m:1ximt1m den1and. H cannot
be '.'>l1Pf10sed
th~ll th~ legislature (onten1platcd th:t1 the phntsc "maximum
dem:

## Text

smoR ELECTRICITY WORKS LTD.
v.
TIIE GUJARAT ELECTRICITY BOARD AND ANR.
January 29, 1969
(J, C. SHAH, V. RAMASWAMI AND A. N. GROVER, JJ.]
Elfctricity (Supply) Act, 1948, Ss. 2(8) and 19(1 )(b)(ii)-Expres.
sion 'maxinzum demand'-Construction of-Conditions precedent for en ..
cbling Electricity Board to nzake direct supply in area of a licensee.
The appellant carried on the business ~f generating and distributin.g
electriqal" energy within a specified area under a licence granted t? 1t
under the Indian
Electricity
Act, 1910.
The
respondent,
Gu1a_rat
Electricity Board agreed with the second respondent company to give
direct supply of electricity to its factory which wa~ wit~in the area of
supply of the appellant. The appellant brou·ght a suit agamst the respon- .
den~ for declaration that the agreement between the first and the second
respondents without its consent was illegal and ultra vires lhe powers of
the first respondent under the Electricity (Supply) Act., 1948, and sought
an injunction restraining the first respondent from
IDlplementmg
the
decision.
The appellant's case was that the first respondent was not entitled to
give direct supply to the second respondent as the "maximum 'demand"
of the appellant at the time of the request of the second respondent was
262 to 349 KVA between September and December, 1959, and therefore.
mdre than twice the "maximum dem3nd" of the second respondent which
had never exceeded 40 tq 45 KV A. The first respondent dontended, however, that the
0 maximum demand" of the appeJlant company at the time
of request was less than twice the "maximum
demand"
of 398 KVA
asked for bv the second respondent from the first respondent. The trial
court held that the first respondent's decision to give direct supply to the
second respondent was ultra vires its power under section 19 (l)(b)(ii)
of the Act. However, the first appellate court allowed an appeal and the
High Court dismissed a further appeal holding, inter alia, that by virtue
of s. 1'9(1)(b)(ii) the comparison required to be made was between the
maximum demand of the licensee on the Board at the time of request for
direct supply based on electiicity actually supplied and taken during some
reasonable period immediately preceding the time of request for dircc(
supply, and the maximum demand whi<1h the applicant wants to keep the
Board ready on tap when supplying electricity to the applicant.
On appeal to this the Court,
HELD : The appellant was entitled to the grant of a decree in terms
of the trial court's deci'ee.
The "maximum demand" as defined in section 2(8) of the Act has
relation only to an existing state of facts and there can be no maximum
demand in relation to a future period.
On a true construction of section
19(1) (b)(ii), what is required to be compared for determining the
applicability of the clause with the maximum demand of the licensee on
the Board at the time of request fo'r direct ~upply, was the
11maximun1
'demand" by the appliaant on the licensee at that time and not any hypothetical or anticipated demand which the applicant may call upon the
Board be ready to supply, The phrase "supplied and taken" in s. 2(8)
shows that the ascertaimnent of maximum demand is dependent upon the
electricity actually supplied and taken in any particular period in the p .. t
and not electricity which may be supplied and taken in a future period.
[444B]
B
c
D
E
F
G
A
B
c
D
E
F
G
H
ELECT\'. WORKS v. ELECTY. BOARD (Ramaswamy, J.)
439
There was no force in the respondent's contention that
the
words
"asked for by any such person" must be construed to mean any hypothe·
trical or anticipated demand which the applicant may call upon the Board
to be rc.:iJy to supply. Such an interpretation \vould be inconsistent with
the definition of .. maxin1urn demand" in section 2( 8) of the Act.
There
was no reason \.\hy 1he phrase "maximum denu-1nd'' in section 19(1)(b)(ii)
of the Act should be given two different meanings one for the Jicensee
and the· other for the consumer ask in~ for the m:1ximt1m den1and. H cannot
be '.'>l1Pf10sed
th~ll th~ legislature (onten1platcd th:t1 the phntsc "maximum
dem:ind" should he
~dvt>n two ditrcreni
m~anin•!,,, in
lh~ s;1m~
claus~.
1444Ci I
•
•
CIVIL APPELLATE JURISDICT.!ON : Civil Appeals Nos. J52
and 453 of 1966.
Appeals by special leave from the judgment and order, dated
July 4, 1964 of the Gujarat High Court in Second Appeals Nos. 33
and 34 of 1964.
P.A. Mehta, B. K. Mehta, K. L. Hathi and Atiqur Rehman,
for the appclla(\t (in both the appeals).
l. N. Shroff, for respondent No. I (in both the appeals).
H. L. A11a11d and K. B. Mehta, for respondent No. 2 (in both
the appeals).
The Judgment of the Court was delivered by
Ramaswami, J.
The appellant, the Sihor Electricity Works
Ltd., is a public limited company carrying on the
business of
generating and distributing electrical energy under the licence
granted to it under the Indian Electricity Act, 1910, having its
supply area within the limits of Sihor Town situated in the district
of Bhavna1rnr in Saurashtra. The first respondent is the Gujarat
Electricity Board 'which is a Corporation constituted under the
Electricity (Supply) Act. 1948 for the purposes of generation.
supply and distribution of electricity in the State of Gujarat.
The recond respondent is the Saurashtra Electrical and Metal Industries (Private) Ltd., a private limited company carryirig on
the business of manufacturing electrical accessories etc. and having its factorv at Sihor within the area of supply of the appellant
comnanv. The aopellant company was originally generating and
distributing electricitv but at the relevant time it was a distributing licensee distributing the energy purchased in bulk from the
first respondent within its area of supply.
The appellant brought a suit against the respondents in
the
Court of Civil Judge (Junior Division) of Sihor being Civil Suit
No. 45 &I' 1960 to Obtain a declaration that the decision of the
first respondent as
contained in its letters
dated
3rd June.
1960 and 24th October, 1960 to give direct supPlY to the factory
of the second respondent within the area of supply of the appellant
and without its consent was illegal and ultra vires its powers under
440
SUPREME COURT REPORTS
[1969] 3 S.C.R.
the Electricity (Supply) Act, '1948 (Act No. 54 of 1948) (here·
inafter called the Act), and for a permanent injunction restrain·
ing the first respondent from implementing the said decision .. The
case of the appellant was that the first respondent was not entitled
to give direct supply to the second respondent as the 'maximum
demand' of the appellant at the time of request of the second respondent was more than twice the 'maximum demand' asked for
by the second respondent. The appellant company alleged that
the maximum demand of the appellant company in the relevant
period. namely, September 1959 to December 1959 was between
262 to 349 KY A while the maximum
demand of the second
respondent had never exceeded 40 to 45 KV A. The first respondent contested the suit on the ground that the decision was legal
and proper because the maximum demand of the appellant company at the time of request was less than twice the maximum demand 'asked for' by the second respondent from the first respondent. It was contended that the demand 'asked for' by the second
respondent was 398 KY A, and. therefore, the first respondent was
entitled in law to give direct supply to the second respondent. The
trial Judge held that the decision of the first respondent to give
direct supply of electricity to the second respondent was ultra vires
the power of the first respondent under section 19(1)(b)(ii) of
the Act and was, therefore, null and void and gave a declaration
to that effect in favour of the appellant. The trial Judge, however,
refused to grant the consequential relief of injunction on the
ground that the Board being a public authority could be expected
to respect the law laid down by the Court and it was, therefore,
not necessary to issue any injunction against the respondents,
Aggrieved by the decree passed by the trial Judge the two respondents filed separate appeals in the District Court. The appellant preferred a cross-abjection contending that the trial Judge
was in error in refusing to grant injunction. The appeals and the
cross-abjection were heard by the District Judge of Bhavnagar
and by a common judgment delivered on 12th October, 1963, the
District Judge a,ccepted the contentions urged on behalf of the
respondents and allowed the appeals.
The District Judge held
that the jurisdiction of the Civil Court to entertain the suit was
excluded by reason of s. 76( n .Jf the Act and the dispute between the parties being a dispute covered by that section could be
determined only in the manner provided by that section, viz., by
arbitration. The District Judge also decided that the maximum
demand asked for by the second respondent was in excess of 50
per cent of the maximum demend of the appellant at the time of
request for direct supply and the first respondent was enti&d to
give direct supply of electrical energy to the second respondent
under s. 19(1)(b)(ii) of the Act. The District Judge accordingly
found that the suit was liable to fail not only for want of jurisdiction but also on merits and accordingly a!Jowed the apPeals and
A
B
c
D
E
F
G
H
A
B
c
D
E
F
G
H
ELECTY. WORKS v. ELECIY. BOARD (Ramaswamy, J.)
44i
dismissed the suit. Thereafter, the appellant preferred appeals to
the High Court of Gujarat being Civil Second Appeals Nos. 33
and 34 of 1964. The said appeals came for hearing before Mr.
Justice P. N. Bhagwati, who dismissed the same by a common
judgment dated 4th July, 1964. The learned Judge took the view
that the Court had jurisdiction to hear the suit as the provision
for arbitration under s. 7 6 of the Act was inserted in the statute
not in the interest of public good but for the benefit of individuals
and therefore either party can waive the right to insist on arbitration.
The learned Judge, however, held that the true effect of
s. 19(1)(b)(ii) was that "the comparison required to be made
was between the maximum demand of the licensee on the Board
at the time of request for direct supply which would of course be
maximum demand based on electricity actually supplied and taken
during some reasonable period immediately preceding the time
of request for direct supply and the maximum demand which the
applicant wants to keep the Board ready on tap when supplying
electricity to the applicant". These appeals are brought by special
leave from the judgment of the Gujarat High Court dated 4th July,
1964 in Second Appeals Nos. 33 and 34 of 1964.
The question of law presented for determination in this case
is whether the High Court was right in holding that section 19 (I)
(b)(ii) of the Act prescribed that a comparison must be made
between the actual maximum demand of the licensee company and
the anticipated maximum demand of the consumer before the
Electricity Board can decide to give direct supply to the consumer
within the area of supply of the licensee company.
Section 19(1) of the Act states :-
"The Board may, subject to the provisions of this
Act, supply electricity to any licensee or person requiring such supply in any area in which a scheme sanctioned under Chapter V is in force;
Provided that the Board shall not-
( a) supply electricity for any purpose directly to
any licensee for use in any part of the area of supply of
a bulk-licensee without the consent of the bulk-licensee,
unless the licensee to be supplied has an absolute right
of veto on any right of the bulk-licensee to supply electricity for such purpose in the said part of such area, or
unless the bulk-licensee is unable or unwilling to supply
electricity for such purpose in the said part of such area
on reasonable terms and conditions and within a reasonable time, or
(b) supply electricity for any purpose to any
persons, not being a licensee for use in any part of the
~lJPKEME COURl REPORTS
[l969j 3 S.C.R.
area of supply of a licensee without the consent of the
A
licensee, unless-
( i) the actual effective capacity of the licensee's
generating station computed in accordance with paragraph IX of the First Schedule at the time when such
supply was required was Jess than twice the maximum
demand asked for by any such person; or
B
(ii) the maximum demand of the licensee, being a
distributing licensee and taking a supply of energy in
bulk is, at the time of the request, less than twice the
maximum demand asked for by any such person; or
(iii) the licensee is unable or unwilling to_ supply
c
electricity for such purpose in the said part of such area
on reasonable terms and conditions and within a reasonable time/'
Section 2 ( 8) of the Act delines 'maximum demand' as follows :-
" 'Maximum demand' in relation to any period shall,
unless otherwise provided in any general or special
order of the State Government, mean twice the largest
number of kilowatt-hours or kilo-volt-ampere-hours supplied and talc.en during any consecutive thirty minutes in
that period".
Section 18 deals with general duties of the Board and reads
"Subject to the provisions of this Act, the Board
shall be charged with the general duty of promoting the
coordinated development of the generation, supply and
distribution of electricity within the State in the most efficient and economical manner, with particular reference
to such development in areas not for the time being
served or adequately served by any licensee, and without
prejudice to the generality of the foregoing provisions it
shall be the duty of the Board-
(a) to prepare and carry out schemes sanctioned
under Chapter V;
( b) to supply electricity to owners of controlled
stations and to licensees whose stations are closed down
under this Act;
( c) to supply electricity as soon as practicable to
any other licensees or persons requiring such supply and
whom the Board may be competent under this Act so to
supply."
Section 26 of the Act clothes the Board with all powers and obligations of a licensee under the Electricity Act, 1910, with this
D
E
F
G
H
A
II
c
D
E
F
G
H
ELECTY. WORKS v. ELEC'fY. IJOARD (Ramci:>1vamy, /.)
HJ
exception that certain sections, including section 22 relating to
the duties and 'obligations of a licensee, are declared not to apply
to the Board. Since section 22 is excepted from its applicauon
to the Board, it is evident that unlike a licensee under the Electricity Act, 1910, the Board is under no obligation to supply electricity to any person applying to it for supply. Section 49 of the
Act empowers the Board to fix the terms and conditions on which
it will supply electricity to a person other than a licensee and that
power is conferred in wide terms subject only to the provisions ot
the Act and any regulations which may be made by the Board in
that behalf.
The legal position therefore is that the. Board cannot supply
electricity to any licensee or a person other than a licensee unless
the Board 1s competent to do so under the Act.
Under Section
19(1) the Board would ordinarily be competent to supply electricity to a licensee or to a person requiring such supply m any area
in which a scheme sanctioned under Chapter V 1s in force. But
there are two provisos which limit the genera! power of the Board
to supply electrji;ity. Proviso (a) relates to a case of a licensee
requiring supply of electricity in any part of the area of supply ot
a bulk licensee. Proviso (b) is material to the present case. This
proviso enjoins the Board not to supply electricity for any purpose
to any person other than a licensee for use in any part of the area
of the licensee unless the case falls within any of the three clauses,
namely, clauses (i), (ii) and (iii). The intention of the legislature seems to be that if any person requires supply of electricity
for any purpose for use in any part of the area of supply of a
licensee, he must approach the licensee in the first instance and
the licensee alone must have the right to supply electricity to him
unless of course the licensee consents to his taking of supply of
electricity from the Board in which event the Board would
be
free to supply electricity to him.
This provision was apparently
enacted with a view to protect the interest of the licensee who has
incurred capital expenditure in putting up generating plants, transformers, mains and transmission lines and who should be therefore entitled to secure a reasonable return by having a sufficient
number of consumers to take the electricity which may be generated by the licensee or which .may be taken in bulk by the licensee
from the Board. But the legislature engrafted certain exceptions
to this rule by enacting clauses (i), (ii) and (iii) and providing
that in cases covered by any of these clauses, the Board shall be
at liberty to supply electricity to any person applying to it for
supply despite the want of consent of the licensee. It is common
ground that the exceptions set out in clauses (i) and (iii) do not
apply to the present case and the only exception relied on by the
respondents is that set out in clause (ii). On behalf of the respondents it was contended that the High Court has takon a correct
view with regard to the interpretation of s. 19(1)(b)(ii) of the
444
SUPREME COURT REPORTS
[1969] 3 S.C.R,
Act and the first respondent was entitled to supply electricity to
the second respondent without the consent of
the appellant
as the conditions oi clause (ii) of the sub-section have been satisfied.
We are unable to accept this argument. In our opinion,
the ·maximum demand' as denned in section 2(8) of the Act has
relation oruy to an existing state of facts and there can be no
max1mmn demand in relat10n to a futu(e period'" and, therefore,
on a true construction of section 19(l)(b)(ii) of the Act what is
required to be compared for determining the applicability of the
clause with the maxinmm demand of the licensee on the Board
at the time of request for direct supply, was the 'maximum demand'
by the applicant on tl1e licensee at that time and not any hypothetical or anucipated demand which the applicant may call upon the
Board be ready to supply. It is manifest that section 2 ( 8) of the
Act gives a technical meaning to the expression 'maximum
demand' by. defining it as twice the largest number of kilowatt
hours or k.Jlo-volt,ampere . hours supplied and taken during any
consecutive thirty minutes in any particular period. It follows from
the language of the definition that the concept of maximum demand is a concept ba>cd on existing facts and it is not possible to
think of a maximwn demand in relation to a future point of time.
Reference should be made in this connection to the phrase
"supplied and taken" in section 2(8) of the Act. This phrase
also shows that the ascertainment of maximum demand is dependent upon the electricity actually supplied and taken in any particular period in the past and not electricity which may be supplied
and taken in a future period. In other words, the 'maximum
demand' as defined in s. 2 ( 8) of the Act has always reference to
a past period and there can be no maximum demand in relation
to a future period. On behalf of the respondents attention was
invited to the words "asked for by any such person" in section
J9(J)(b)(ii) of the Act.
But these words are inserted in the
section merely by way of description and they must be construed
to mean that the Board will make direct supply only when the
applicant makes a request for such direct supply from the Board
and not otherwise. It is not possible to accept the argumC!llt of
the respondents that the words "asked for by any such person"
must be construed to mean any hypothetical or anticipated demand
which the applicant may call upon the Board to be ready to supply.
Such an interpretation would be inconsistent with the definition
of 'maximum demand' in section 2 ( 8) of the Act.
We also see
no reason why the phrase 'maximum demand' in section 19(1)
(b) (ii) of the Act should be given two different meanings one for
the licensee and the other for the consumer asking for the maxi ..
mum demand. It cannot be supposed that the legislature contemp·
lated that tl1e phrase ·maxinrnm demand' should be given
two
different meanings in the 'amc clause.
A
B
c
D
E
F
G
H
B
c
D
'.E
ELECTY. WORKS v. ELECTY. l30ARD (Ramaswami, J.)
445
It was pointed out on behalf of the respondents that if the
phrase 'maximum demand' in section 19(1)(b)(ii) of the Act
is given the technical meaning as !Ilention~d in section 2 ( 8) ?f
the Act, hardship may be caused m certam cases.
It was said
that an applicant may not be taking electritity supplied by the
licensee and may still be desirous of taking electricity from
the
Board for the first time. Such an applicant would have no maximum demand at the time of request for direct supply but when
asking for direct supply he is required to intimate to the Board
what is the maximum demand he would require.
It was said that
the applicant may have a potential peak demand which the
licensee may not be able to supply.
In such a case it was not
reasonable to require the applicant to approach the licensee in the
first instance and thereafter make an application to the Board. It
was also argued that there was no reason why the applicability of
clause (ii) should be restricted only to persons taking electricity
supplied by the licensee. In our opinion, there is no warrant for
this argument.
As we have already indicated the language of
section 19 (I ) (b )(ii) of the Act must be construed in the light
of the definition of 'maximum demand' contained in section 2 ( 8)
of the Act. Upori that construction it is clear that the applicability of clause (ii) is restricted to persons taking electricity supplied
by the licensee. There is also no hardship caused to an applicant
who may not 'take electricity supplied by the licensee and who may
be desirous' of taking electricity for the first time from the Board
in view of his anticipated requirements.
It is open to such an
applicant to take recourse to the provision of clause (iii) of section 19 ( 1) (b) of the Act which provides that the Board may
supply electricity direct without the consent of the licensee if the
later is unable and unwilling to supply electricity for the purpose
of the applicant on reasonable terms and conditions and within a
reasonable time. In our opinion, no anomaly or inconvenience
would result if the construction contended for on behalf of the
appellant with regard to section
19 (I )(b )(ii) of the
Act
is
accepted.
If our interpretation of s. 19(1 )(b) (ii) of the Act is correct,
the appellant is entitled to the grant of a decree in terms of the
~ trial Court's decree.
It is pointed out by Mr. Justice Bhagwati
in his judgment that right up to' the end of December, 1959 the
maximum off take of electricity by the second respondent from
the appellant was not more than 50 KV A. The maximum demand
of the licensee on that period was 291 KVA, and so, the conditions
of s. 19( 1 )(b )(ii) of the Act were not satisfied.
It follows that
the first respondent was not entitled under that clause to supply
H
electricity direct to the second respondent.
For the reasons expressed we hold that the judgment of the
Gujarat High Court in· Second Appeals Nos. 33 and 34 of 1964
L8 Sup Cl/69-10
446
SUPREME COURT REPORTS
[1969] 3 s.c.R.
dated 4th July, 1964 and of the District Judge of Bhavnagar dated
12th October, 1963 should be set aside and the judgment and
decree of the Civil Judge (Junior Division) at Sihor dated 31st
March, 1960 should be restored. The apPt<als are accordingly
allowed with costs in this Court and the High Court.
R.K.P.S.
Appeals allowed.
B