# UNION OF INDIA & ANR v. MAJUR MAHAJAN MANDAL & ·oRS

- **Citation:** [1977] 2 S.C.R. 472
- **Court:** Supreme Court of India
- **Decided:** 1974-07-06
- **Case number:** Civil Appeal No. 690 of 1976
- **Bench:** P. K. GoswAMI ANDS. MuRTAZA FAZAL Au
- **Source:** https://unisonlegal.in/judgment/supreme-court-of-india/union-of-india-anr-v-majur-mahajan-mandal-ors-7060
- **Pages:** 7

## Headnote

Additional Emoluments (Compulsory Deposit) Act, 1974-s. 2(b)-"Sanc·
tioned" meaning of.
.
Section 2(b) of the Additional Emoluments (Compulsory Deposit)
Act,.
1974 defines additional dearness allowance to mean such dearness allowance
as may be sanctioned from time to time after the appointed day, i.e., July 6,
1974 over and above the amount of dearness allowance payable in accordance
with the rate in force immediately before the date from which such sanction•
of additional dearness allowance is to take effect. Section 6(2) (b) enjoins,
on the employer the duty to make deductions and to remit to the nominated
authority additional dearness allowance from the emoluments disbursed after
the appomted day. Section 115A of the Bombay Industrial Relations Act, 1946
provides that if any agreement is arrived at between the employer and employees who are parties to an industrial dispute pending before the industrial court,
the award in such proceeding shall be made in terms of such agreement, except
in certain circumstances stated therein.
As a result of negotiations between the employers and employees a settlement was entered into between the parties on June 28, 1974 enhancing the
dearness allowance with retrospective effect from January 1. 1974. The Industrial Court before which certain disputes were pending gave the award in
conformity with the settlement sometime in August-September, 1974.
Arrears
of dearness allowance were paid after the appointed day.
In a petition under Article 226 of the Constitution by the employees' Union;
the High Court issued a writ restraining the employers from effecting any deduction from the arrears of D.A. payable to the employees on the basis of the
settlement and granted certain other reliefs.
In apoeal it was contended that since the settlement of June 28. 1974 could
not be effective prior to the award made in August-September 1974 additional
dearness allowance could be said to be sanctioned only after the award and so
the provisions of s. 2 (b) would be attracted.
Dismissing the appeal
HELD : One of the components of cl. 2(b) namely, that the
additional
dearness allowance is that part of the D.A. which is
sanctioned
after
the
appointed day, is absent since there was no sanction for any rise iii. aearness
allowance after the appointed day.
[477 G]
(1) According to s. 11 SA of the Bombay Industrial Relations Act if the
conditions enumerated therein did not exist the award "shall be made" in terms of
the settlement. Smee the settlement in this case had merged in the award, the
terms of the award are those specified in the settlement. The sanction of the award
in such a case was the sanction under the settlement and since the settlement
was prior to the appointed day, additional dearness allowance could not
b~
said to be sanctioned after the appointed day. [476 F & H]
In the instant case the Industrial Court having passed the award in conformity with the terms of the settlement, the award came into operation on the dat~
specified in it.
(2) Sanction must have relevance to the reality of the transaction between
the parties. Increased dearness allowance payable between January 1, 1974 and
July 5, 1974 was sa!'ctioned prior t!' th~ appointed day.
Once it is found that
the sanction was pnor to the appomted day, s. 2(b) would not be attracted.
[477 c & Fl
!
I
\
•
UNION v.'MAJUR MAHAJAN M:ANDAL (Goswami, J.)
473
(3) From the definition of "additional wages" ins. 2(c) it is clear that the
Act recognises agreements and settlements m the same way as awards
of
Tribunals. Any wage revision .. whether by or unaer au 11greement or settle:·
mem b~twcen !lie parties or any award" comes wi~in the sw~ep of the defi!Jl·
tion clause. Agreements and settlements are d1sum:tly mentioned alo,ng wit~
awards. Settlement is a type of sanction recogn~sed under the Act.
l nere l•
therefore sufficient warrant under the Act to g1 ve ett:ct to the. sa.nct1?n by
voluntary settlement in respect of D.A.
When there is. no amb1gmty 1.n th

## Text

A
B
c
D
E
F
G
472
UNION OF INDIA & ANR.
v.
MAJUR MAHAJAN MANDAL & ·oRS.
December 16, 197 6
[P. K. GoswAMI ANDS. MuRTAZA FAZAL Au, JJ.J
Additional Emoluments (Compulsory Deposit) Act, 1974-s. 2(b)-"Sanc·
tioned" meaning of.
.
Section 2(b) of the Additional Emoluments (Compulsory Deposit)
Act,.
1974 defines additional dearness allowance to mean such dearness allowance
as may be sanctioned from time to time after the appointed day, i.e., July 6,
1974 over and above the amount of dearness allowance payable in accordance
with the rate in force immediately before the date from which such sanction•
of additional dearness allowance is to take effect. Section 6(2) (b) enjoins,
on the employer the duty to make deductions and to remit to the nominated
authority additional dearness allowance from the emoluments disbursed after
the appomted day. Section 115A of the Bombay Industrial Relations Act, 1946
provides that if any agreement is arrived at between the employer and employees who are parties to an industrial dispute pending before the industrial court,
the award in such proceeding shall be made in terms of such agreement, except
in certain circumstances stated therein.
As a result of negotiations between the employers and employees a settlement was entered into between the parties on June 28, 1974 enhancing the
dearness allowance with retrospective effect from January 1. 1974. The Industrial Court before which certain disputes were pending gave the award in
conformity with the settlement sometime in August-September, 1974.
Arrears
of dearness allowance were paid after the appointed day.
In a petition under Article 226 of the Constitution by the employees' Union;
the High Court issued a writ restraining the employers from effecting any deduction from the arrears of D.A. payable to the employees on the basis of the
settlement and granted certain other reliefs.
In apoeal it was contended that since the settlement of June 28. 1974 could
not be effective prior to the award made in August-September 1974 additional
dearness allowance could be said to be sanctioned only after the award and so
the provisions of s. 2 (b) would be attracted.
Dismissing the appeal
HELD : One of the components of cl. 2(b) namely, that the
additional
dearness allowance is that part of the D.A. which is
sanctioned
after
the
appointed day, is absent since there was no sanction for any rise iii. aearness
allowance after the appointed day.
[477 G]
(1) According to s. 11 SA of the Bombay Industrial Relations Act if the
conditions enumerated therein did not exist the award "shall be made" in terms of
the settlement. Smee the settlement in this case had merged in the award, the
terms of the award are those specified in the settlement. The sanction of the award
in such a case was the sanction under the settlement and since the settlement
was prior to the appointed day, additional dearness allowance could not
b~
said to be sanctioned after the appointed day. [476 F & H]
In the instant case the Industrial Court having passed the award in conformity with the terms of the settlement, the award came into operation on the dat~
specified in it.
(2) Sanction must have relevance to the reality of the transaction between
the parties. Increased dearness allowance payable between January 1, 1974 and
July 5, 1974 was sa!'ctioned prior t!' th~ appointed day.
Once it is found that
the sanction was pnor to the appomted day, s. 2(b) would not be attracted.
[477 c & Fl
!
I
\
•
UNION v.'MAJUR MAHAJAN M:ANDAL (Goswami, J.)
473
(3) From the definition of "additional wages" ins. 2(c) it is clear that the
Act recognises agreements and settlements m the same way as awards
of
Tribunals. Any wage revision .. whether by or unaer au 11greement or settle:·
mem b~twcen !lie parties or any award" comes wi~in the sw~ep of the defi!Jl·
tion clause. Agreements and settlements are d1sum:tly mentioned alo,ng wit~
awards. Settlement is a type of sanction recogn~sed under the Act.
l nere l•
therefore sufficient warrant under the Act to g1 ve ett:ct to the. sa.nct1?n by
voluntary settlement in respect of D.A.
When there is. no amb1gmty 1.n the
word "sanctioned" in ~. 2(b) recourse to the aim and ob1ect of the Act IS not
called for. [478 A-Bl
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 690 of 1976.
Appeal from the Judgment and Order dated the 16th December, 1975 of
the Gujarat High Court in Special Civil Appln. No. 571/75.
A
B
~
G. S. Sanghi and Girish Chandra for the Appellants.
V. M. Tarkunde, K. L. Hathi and Mrs. P. C. Kapur for ResponC
dent No. 1.
The Judgment of the Court was delivered by
GOSWAMI, J.
This appeal on certificate is from the judgmel!-t ot
the High Court of Gujarat. The appellants 1 and 2 are resrec.tively
the Union of India and the Regional Provident Fund Comm1ss10ne!·
The 1st respondent is Majur Mahajan Manda! (hereinafter to be descn-
.bed as the union), a registered trade union representing the majority
of the textile workers of ihe five textile mills of Baroda (respondents
2 to 6) who are not repr~sented before us and who will be described
hereinafter as the mills.
Since some time in 1973, industrial disputes in respect of dearness
allowance (D.A.) had been pending between the union and the mills
in five references before. the Industrial Court, Gujarat, being Reference
Nos. 406, 407, 408, 409 and 421 of 1973. The rate of D.A. for the
employees in the cotton textile industry in Ahmedabad had earlier been
fixed by an award of an Industrial Tribunal which will be referred to
hereinafter as the Ahmedabad Rate. The prevalent D.A. in 1973 in the
mills with which we are concerned was 90% of the Ahmedabad Rate.
The union was raising the aforesaid disputes for increasing the D.A.
to 100% of the Ahmedabad Rate with effect from October 1, 1972.
D
E
F
i.
~""',,Hence the above references were pending before the Industrial· Court.
}
As a result of negotiations between the parties during the pendency
of the said disputes before the Industrial Court D.A. was agreed to be
paid at the rate of 95% of the Ahmedabad Rate of D.A. with effect
from January 1, 1974, as will appear from an interim award of the
Industrial Court dated June 21, 1974. Thereafter by further negotiations the disputes regarding D.A. were finally resolved by the mills and
the union entering into a settlement on June 28, 1974, by fixing D.A.
at 100% of the Ahmedabad Rate with effect from January 1, 1974.
A wards were later made by the Court in conformity with the said settlement in the pending disputes some time in August and September, 1974.
G
It is not disputed that the workers of the mills
in pursuance of
H
the settlement of the disputes received D.A. at 100% of the Ahmedabad Rate retrospectively with effect from 1st January, 1974. It may
even be assumed that the arrear D.A. for the past period from January
A
B
D
474
SUPREME COURT REPORTS
[1977] 2 S.C.R.
f• 1974, was paid to the workers in August or perhaps even later, that
1s to say, after 6th July, 1974, the significance of which date we will
immediately see.
While the aforesaid disputes
were pending before the Industrial
Col!rt, The Additional Emoluments (Compulsory Deposit) Act 1974
(bnefiy the Act), replacing the earlier Ordinance on the subject, came
into force retrospectively from 6th July, 1974, the appoi~~d day, under
the .Act.
This Act was passed as the preamble s1lys, "to provide, in
the mterests of national economic development, for the comp11lsory deposit of additional emolu01ents and for the framing of a scheme in relation thereto, and for mat!ers connected therewith or incidental thereto".
The employees to whom ~e Act is applicable are classified into
three categories, namely, employees of the Government, of local authorities and other employees.
-
The principal object of the Ordinance and later of the Act is to
control the menacing inflationary trend which has been the bane of the
country's economy.
On the one hand there has been
persistent
demand from employees for revision of wages and increase of D.A. on
account of the high cost of living and on the other the State has to
tackle the national problem of mounting pressure of inflationary forces.
While, therefore, meeting with the demands for rise in emoluments,
simultaneously, steps with equal force had to be taken so that the
additional amounts disbursed do not immediately flow to the market
adding a further fillip to inflation.
The Ordinance and later the Act
thus provide for compul.Sory deposit for a period of one year of the
whole of the additional wages and for a period of three years of half
of the additional D.A.
The additional emoluments earned are thus impounded under the
Act and are not immediately available to the employees for instant
consumption. The Act provides a scheme of beneficial forced saving
and the deposited amounts will be finally repaid to the employees in
different ways specified in the Act with interest at 2t% over and
F
above the Bank deposit rate.
G
H
Before we proceed further we may note some of the provisions of , __......
the Act material for our purpose :
By section 2(a) of the Act "appointed day" means the 6th day of
July, 1974".
By section 2 (b) " 'additional dearness allowance'
means
such
dearness allowance as may be sanctioned from time to time, after the
appointed day, over and above the amount of dearness allowance payable in accordance with the rate in force immediately before the date
from which such sanction of additional dearness allowance is to take
effect".
•
•
•
•
By section 2(e) "'dearness allowance' means all cash payments,
by whatever name called, made to an employee on account of rise in
'./
}
UNION v. MAJUR MAHAJAN MANDAL (Goswami, J.)
475
the cost of living". Under section 2(g) "'emoluments' include wages
and dearness allowance".
Under section 5 every specified authority (herein the employer)
shall open two separate accounts, namely, the Additional ~ages Deposit Account and the Additional Dearness Allowance Deposit Account.
The employer shaU .open a separate ledger account in the name of
each employee. Section 6(2) (b) of the Act enjo~s on the em.ployer .a
duty to make deductions and to remit to the nommated authority additional wages and additional D.A. from emoluments disbursed after
the appointed day. In the case of additional wages it will be the whole
amount and in the case of additional D.A. it will be half of it.
It is common ground that the Act applies to the mills which are
foe: "employers" under the Act and also "specified authorities" under
the Additional Emoluments Compulsory Deposit (Employees other
than employees of Government and Local Authorities) Scheme, 1974,
which is made under section 10 of the Act.
The union applied to the High Court under Article 226 of the
Coftstitution for a writ of mandamus or other suitable order to permanently restrain the mills from effecting any deduction from the arrears
of dearness allowance payable to their employees from January to June
1974 on the basis of the settlement of 28th June, 1974. There W!\S
a further prayer to permanently restrain the mills from treating the
base for calculation of additional D.A. at a rate less than the agreed
100% of the Ahmedabad Rate and to direct the mills not to deduct
or deposit 2t% of D.A. per month payable to each employee treating
the same as riot being additional D.A. within the meaning of section
2(b) of the Act. Lastly there was a prayer for refund of the amount
already deducted by the mills.
The High Court allowed the writ
application and also granted certificate to appeal to this Court.
The appellants contend that 100% of the Ahmedabad Rate of
D.A. to the workers was sanctioned after the appointed day, that is to
say after 6th July, 1974, when the awards were made between August
and September 1974 in pursuance of the settlement of June 28, 1974.
The claim of the appellants is two-fold : First, since
the increased
D.A. to the workers was sanctioned after the appointed day, only
when the awards were made, the difference between the increased
D.A. at 100% of the Ahmedabad Rate and the prevailing rate payable
in arrears frorn 1st January, 1974 to 30th June, 1974, will be additional D.A. in terms of section 2(b) of the Act and is, therefore,
subject to deduction of 50% of the same. Second, for future deductions of additional D.A., after the appointed day, the base for calculation of additional D.A. should be 95% of the Ahmedabad Rate of
D.A. which was prevailing prior to 6th July, 1974, in terms of the
interim award of 21st June, 1974. In other words, for future deductions of additional D.A. after 6th July,
1974 the appellants
claim that the workers should be treated as if they were in receipt
of D.A., prior to the appointed day, at 95% of the Ahmedabad Rate
which had been in force in terms of the interim award of 21st June,
1974, which is the earlier sanction for the 95% rate. Hence, 2t%
(that is 50% of 5% being the difference between 95% and 100%) ·
of the same will be liable for deduction under the Act from 6th July,
1974.
According to the appellants, the benefit of 100% was available
only after the making of the awards which was, thus, sanctioned after
A
B
c
D
E
F
G
H
476
SUl'RllMB COURT REPORTS
[1977] 2 S.C.R.
1 A
the appointed day notwithstanding the fact that the settlement had
been entered upon on 28th June, 1974. Section 2(b) will, therefore,
be clearly attracted, according to the appellants.
B
c
D
E
F
G
H
It is submitted by the appellants that the word "sanctioned" in the
definition of 'additional dearness allowance' under section 2 (b) is very
significant. It is contended that the settlement during the pendency
of an industrial dispute before the industrial Court has to be approved
by the Court before it can be said to be sanctioned within the meaning
of the provisions of section 2(b). Reference is made to section 115A
of the Bombay Industrial Relations Act, 1946. That section, so far
as it is material for our purpose, provides that if any agreement is
arrived at between an employer and the union which are parties to an
industrial dispute pending before an Industrial Court the award in
such proceeding shall be made in terms of such agreement unless the
Industrial Court is satisfied that the agreement was in contravention
of any of the provisions of the Act or the consent of either party to
the agreement was caused by mistake, misrepresentation, fraud, undue
influence, coercion or threat.
Relying on section 115 A, it is submitted by the appellants, that unless the award is made in pursuance
of the settlement under the said section the settlement is inchoate and
cannot be said to be effective, in law, prior to the making of the award
which was done, in the instant case, between August and September
1974. It is, therefore, submitted that the additional D.A. can be said
to be sanctioned only under the award which was made admittedly
after the appointed day, that is after July 6, 1974.
We are unable to accept this contention. It is true that an agreement arrived at between the parties during the pendency of an industrial dispute before the Industrial Court has to be placed before that
Court. It is also true that if the Industrial Court is satisfied that certain
conditions enumerated in section 115A. exist it will not recognise the
settlement and dispose of the dispute in accordance with law.
If,
however, the conditions enumerated in section 115A do not exist the
award "shall be made" in terms of the settlement. There is no other
option.
Y,
~·
In this particular case the settlement was placed before the Industrial Court which ultimately passed the awards in conformity with the ·.,,,, •
terms of the settlement. We are not required to consider a case where
the Tndustrial Court has not approved of the settlement under section
115A.
.
Once, therefore, the award is made in terms of the settlement, under
section 75 of the Bombay Industrial Relations Act, the award shall
come into operation on the date specified in the award or where no
sueh date is specified therein on the date on which it is published
under section 74. We are informed that the awards have not yet been
published but that should not detain us in this case. It is common
ground that the awards were in terms of the settlement which had
retrospective operation from January 1, 1974.
Since the settlement has merged in the awards the terms of the
\
awards are tho~e specified in the settlement. It is those dates which
_...,_=~ _,._.., ___ ·~---*·-
-
······--~--""""'~'--'~
\
,7
l
UNION. v. MAJUR MAHAJAN MANDAL (Goswami, !.)
477
:are, therefore, specified in the awards and, under sect~on 75 of ~he
Bombay Industrial Relations Act, the awards came mto operat10n
·with effect. from January 1, 1974.
The sanction of _the awards in
:such a case is the sanction under the settlement and smce the settl~
ment was prior to July 6, 1974, the additional. D.A. cannot be said
to be sanctioned after the appointed day.
100% of the Ahmedabad
.Rate of D.A. will be payable to the workers with effect from January
l 1974 and the sanction for that rise was on 28th June, 1974, the
d~te of the settlement which was prior to the appointed day.
Sanction must have relevance to the reality of the
transaction
.between the parties. The settlement of 28th June, 1974, makes the
increased D.A. of 100% payable with effect from January 1, 1974.
'Hence the said rate of increased D.A. which was payable to the workers
between January 1, 1974 and July 5, 1974, was sanctioned prior to
the appointed day.
We have already noted the definition of additional D.A. in section
2(b) which is an integrated definition. The definition clause has twin
·components both of which will have to be satisfied in order that a
particular amount can be held to be additional D.A. To put it clearly
the two components are-
-
(1) additional D.A. is that part of the D.A. which is sanctioned
after the appointed day; and
(2) which is over and above what was payable immediately
before the date from which sanction of the particular rise
in D .A. is to take effect.
With regard to the first component any unilateral decision to in-
<:rease the D.A. or a bilateral settlement for its increase, to take only
two instances, must take place after the appointed day.
It is manifest that if the sanction is after the appointed day it is
then only the question of additional D.A. will arise within the meaning
of section 2 (b). Once it is found that the sanction of rise in D.A.
A
B
c
D
E
is prior to the appointed day, section 2(b) will not at all be attracted.
F
In that event it will not be necessary even to consider the second
component of the definition mentioned above.. In the instant case
we have already held that the rise in D.A. to 100% of the Ahmedabad
Rate of D.A. was sanctioned under the settlement of 28th June, 1974,
that is, before the appointed day.
One of the principal components
·Of the definition clause is, therefore, clearly absent in this case since
there is no sanction for any rise in D.A. after the appointed day.
G
We should observe that this is not a case where Explanation-I to
-section 2 (b) is applicable.
Mr. Singhvi for the appellants submits that in view of the aim and
object of the Act the Court should lean in favour of an interpretation
advancing the remedy by construing the word "sanctioned" in section
2(b) to mean sanctioned by the award and not by the settlement.
We have already given our reasons for our inability to accept this
submission.
One other reason may be added.
•
H
478
SUPREME COURT REPORTS
[1977] 2 S.C.R.
A
The Act recognises agreements and settlements in the same way
as awards of Tribunals, vide, section 2 ( c). The definition of "additional wages" under section 2(c) clearly points to that. Any wage
revision "whether by or under an agreement or settlement between,
the parties or any award .... " comes within the sweep of the aforesaid definition clause.
Agreements and settlements are separately
and distinctly mentioned along with awards. Settlement is a type of
B
sanction recognised under the Act. There is, therefore, sufficient warrant under the Act to give effect to the sanction by voluntary settlement in respect of D.A. when the same has never been repudiated by
any of the concerned parties. When there is no ambiguity in the word
"sanctioned" in section 2 (b), recourse to the aim and object of the
Act is not even called for in this case.
c
Both the contentions of the appellants, therefore, fail on the solitary
ground, namely, that the particular sanction of additional D.A. in this
case is not after the appointed day.
The appeal is dismissed with
costs.
P.B.R.